Bunker Hill Provides Project Restart Update Early 2024 milestones
- Arrival of mill and other key components from the shuttered Golden Sunlight mine brings the procurement of Processing Plant equipment past the 80% threshold.
- Power cables and infrastructure have now been ‘dropped’ underground, bringing all parts of the mine - surface and subsurface - onto low-cost, hydroelectric-dominated mainline electric grid power.
- Drilling contract for resource definition and expansion to commence in Q2 2024 has been awarded to Dynamic Drilling, Inc. of Osburn, ID.
Remaining Q1 2024 events
- Demolition of the old mining offices to create space for a new, purpose-built Filtration Plant is underway and due to complete by the end of Q1 2024.
- LFI of Hutchinson, KS is due to deploy in early March to commence drilling of auger-cast piles as part of the pre-foundation work for the Process Plant and Filtration Plant buildings.
PDAC Conference – Metro Toronto Conference Centre (3-6 March 2024)
- Bunker Hill Mining Corp. will be represented at its Company Stand 3214 within the Metro Toronto Conference Centre, and attended by the Executive Chair, CEO, CFO, Chief Geologist and Director: Finance.
TORONTO, Feb. 29, 2024 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. (TSX-V: BNKR) (OTCQB: BHLL) (“Bunker Hill” or the “Company”) is pleased to announce that project restart activities have accelerated in early 2024 with early stage construction activities about to commence in support of new purpose built Process and Filtration Plant buildings.
Bunker Hill Provides Project Restart Update February 2024 (globenewswire.com)