So let me get this straightGRB has no cash and a $7.9 million working capital deficiency?
And as schneps posted:
" The fair value of the development project as a whole is not possible to reliably estimate as of yet, given we have not yet received all necessary permits or begun construction "
And yet on March 18, they issued the following in a news release:
" The schedule to break ground on Sage Ranch will be within the month of April, 2024 "
How could they predict a start date for Sage when they didn't have the permits on March 31?
And here we are, May 31.