42 Truckloads of ore shipped as of May 27thFrom May 13th nr.
-- Talisker is initiating the Ore Hauling Agreement with the transportation of previously stockpiled material comprising approximately 6,300 tonnes to be processed at the Craigmont milling facility. The first shipment is expected to occur on May 15th.
Terry had said on May 28th that 42 loads had been shipped by the day before, resulting in 1734 tonnes.
He also said, at that time, that they were shipping about 200t/d with a present goal of 200-250t/d.
This means that the company is executing it's plan very well to this point. Let's hope this continues and that any hiccups are minor.
If they have been shipping an average of 200t/d since May 28th then it is possible that Talisker has now shipped as much
5000 tonnes.
Should be interesting once getting through any initial lower grade material.
Grades for the first year, I believe, are expected to be 10+gpt.
Looking forward to the initial reports back from milling.