RE:RE:RE:Chill everyoneBased on the latest Q&A.
- (Powder) The project did not get cancelled and is very much underway. The titanium powder is being delivered on a different schedule than originally anticipated.
- (SPARC) The client recently informed PyroGenesis of delays to the construction of their facility that is being built to house the SPARC™ unit, pushing the expected SPARC™ delivery date to early 2025.
- (S.O.W.) As noted in those releases, the client was taking steps to secure financing for its overall project.
- (Ciment) The client is currently raising financing for the development of a pilot plant.
Reasons why I don't think much will get signed until 2025.
Other than the above, many other things might be under development or discussion or negotiation, but I'm not too optimistic about it, we were thrown large $ contract potential in the past and nothing came of it.
So I need to stay Long another year at least.
EtheGreat wrote: Is "not much going to happen" based on Q1 "0 - 3 Months" & "3 - 6 Months" Outlook Guidance ? -- if "yes" what is the relative starting reference for these ?
Is it Q1 Jan'24: ? , Q2 start ? , Date of Q1 Report communicated to Public ? --
IMO "0 - 3 Months" & "3 - 6 Months" are general time frames & depending on starting date of reference can skew different interpretations ::
So As of today which are we in "0 - 3 Months" OR "3 - 6 Months" ??? -- which is it ?
"...but not much is going to happen in the next 3 months, if things go as planed maybe between 3-6 months"