CC: LLoydminster Upgrader TURNAROUND CAPEX: $ 210-220M- 56 DAYS (DELAYED by 7 DAYS due to BAD WEATHER)
- over 1 million MANHOURS of labor
- over 3,200 CONTRACT PERSONS on site
- LARGEST in the UPGRADER'S history
- BOOKED ENTIRE COST in Q2/2024
- NEXT MAJOR TURNAROUND is DUE in 4 YEARS
- they are HARDENING the DOWNSTREAM OPERATIONS as they undergo turnarounds to IMPROVE RELIABILITY and RESILIENCY and hopefully LOWERING OPERATING COSTS