RE:Something I wish Western management understood..In fairness, MM, we don't have a compelling story right now.
- 12 months from entering permitting
- 36-48 months from there
- Ottawa providing provisional $$ for pre-feasibility on the grid connect. No clue how long that takes.
- 5 years of being strung along by Rio (remember, they landed in Yukon November '19)
- Uncertain FN buy-in to the project - we're still too far from permitting to know how they really feel about us, but that permitting has been delayed since 10/22 bodes ill.
- Literally everyone besides the active posters here - industry, institutionals, commentators - all turning their noses up at Capex, or have a poor understanding of NPV/IRR.
- Uncertain fall-out from Victoria's HLP failure as it relates to Casino's starter pit.