RE:RE:RE:Does the management have ulterior motives to let SP tank?The last I heard was that the optimization process would take to the end of November.
Subsequently, it commissioning would be effected by processing Approx 100,000 tons of stockpiled ore and gold fines which are now at the mill.
My guess is that it might take between 2 and 3 months to process that ore which yield about 3500 ounced of gold.
Assuming that all goes well, it may continue processing gold tailings from TSF#1 as those are recovered .
My info is that HD mine would resume production around early summer...bootstrapped test mining until
full mining capacity is achieved by exit 2025.
However, grade control drilling of HD is now expected to be completed by exit 2024 which is well ahead of my expectations .,..grade control is the last stage before mining and mining benches are configured.
It would seem, generally , that events are on an accelerated pace since the financing was approved in early Sept.
Hope this helps