RE:RE:Interesting..MAE allocates Space for Shoreline ExpansionMy comment was made in the context of preparing for resumption of mining and associated develoment operations which will take most of 2025.
In fact, Maritime has hire Shoreline and its crews to reclaim TSF#1 Tailings Pond including recovered
gold tailings .
Initial operations ceased in late January due to freeze up and will resume in April with normal melt.
I estimate Approx 20,000 ounces can be recovered.
Likewise, Shoreline also resumes aggregate crushing in April at which time the gravity circuit will be re installed at Shorelines Wash plant for recovery of gold fines.
So, reclamation, recovery and reprocessing of tailings fines has been initiated by Maritime, beginning with TSF#1 which is adjacent to the Line cove mill.
Beyond that, it remains to be seen if Shoreline/ Maritime submitted a proposal to the Task Force for the reprocessing of several tailings dumps outside Maritime's TSF#1 tailings Pond.