1 Perforation Equipment Arrives:
Our advanced R/U and PCE wireline equipment, essential for perforating additional gas pay and optimizing natural gas production, has arrived and is set up.
2 Pre-Work HSE Safety Induction:
Conducted a comprehensive Health, Safety, and Environment (HSE) safety induction to ensure all personnel know safety procedures and protocols.
3 Equipment Installation:
Install the Wellhead: Successfully installed the wellhead, forming the foundation of our well control system.
Mount the BOP Stack: Securely attached the Blowout Preventer (BOP) to the wellhead to maintain well control and prevent blowouts during operations.
Attach PCE: Connected lubricators and control equipment to the top of the BOP stack to manage wellpressure and ensure safe tool handling during operations.
4 Perform Testing:
Conducted thorough pressure tests to ensure the integrity and proper function of the entire setup. Thisincluded sealing the system, applying pressure, inspecting for leaks, and verifying the functionality of all components.
July 6:
• Rig Up Tractors and Prepare Guns: All-day operation to rig up Welltec tractors on the Akakoca platform and prepare perforation guns.
7-July:
• South Akakoca-2 Perforation: Weather conditions are forecasted to be unfavourable. Despite this, we will try to proceed with the operation and run in hole (RIH) for the SA-2 perforation.
8-July:
• Guluc-2 First Perforation: Scheduled first perforation at Guluc-2.
9-July:
• Guluc-2 Second Perforation: Scheduled second perforation at Guluc-2.
10-July:
• West Akakoca-1 First Perforation: Scheduled first perforation at WA-1.
11-July:
• West Akakoca-1 Second Perforation: Scheduled second perforation at WA-1.
12-July:
• Akakoca-3 Perforation: Scheduled perforation at A-3.
13-July:
• R/D WLU: Rig down wireline unit.
Weather Conditions:
• Operations are dependent on favourable weather conditions. While we have plans in place, adverse weather may cause delays. We are closely monitoring forecasts and will adjust our schedule as necessary to ensure the safety of our operations and personnel.
GLTA