Post by
gamaray on Aug 20, 2024 4:42pm
tubings are not being installed
we have been told that new tubings are being installed until the latest interview. Today Art said the partner consent is required and the dispute is about one well! Why you did not start with others then. Why you are waiting? With each interview or release we discover more issues with this company. Why you did not say all program is subject to partner approval. Did you purchase all the material without your partner consent? It means you paid it 100% right? What happens if you cant get the green light to go? You say you use a snubbing unit not a rig. I thought it is already installed on the platform. I dont believe that you can mob a unit to Turkey in 2 weeks time after your partner let you to start. Lets be realistic. Please dont lie and let us know the truth.
They try to show the perfs as a big victory but TCF seems to forget the real purpose of the program is the velocity string which has not started yet.
Comment by
FishInTheWater on Aug 20, 2024 5:40pm
that what someone with selective hearing would say