Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Bullboard - Stock Discussion Forum Great Basin Gold Ltd GBGLF

"Great Basin Gold Ltd is a mining company engaged in the acquisition, exploration and development of precious metal deposits."

OTCPK:GBGLF - Post Discussion

Great Basin Gold Ltd > « ...BURNSTONE is located in the South Rand Goldfield...
View:
Post by GoldenPolarBear on May 20, 2018 6:57pm

« ...BURNSTONE is located in the South Rand Goldfield...

« ...BURNSTONE

Burnstone is located in the South Rand Goldfield of the Witwatersrand Basin near the town of Balfour, approximately 75km east of Johannesburg in the Mpumalanga province of South Africa.

Sibanye acquired the Burnstone assets in April 2014, comprising two shaft complexes, namely the surface portal and mechanised vehicle access decline and the vertical shaft (shaft bottom at 495m below surface), as well as a 125,000tpm gold processing plant, the tailings storage facility and surface infrastructure to support a producing operation, albeit with areas still to be constructed. 

Burnstone had previously produced approximately 38,000oz of gold before being placed on care and maintenance in mid-2012.

The Burnstone project feasibility study was approved by the Board for project execution in November 2015. The project is planned with a five-year build-up to steady-state production by 2021, then averaging 120,000oz annually for nine years till the end of 2029. Thereafter a 10-year period of decreasing but profitable production supports an initial 26-year life-of-mine plan, yielding 2.05Moz of gold production. This initial LoM plan was limited to approximately 60% of the total Burnstone resource as the mine design and schedule in the feasibility study were limited to mineable reserves within a 3km radius of the shaft infrastructure.

First gold production is planned in the second half of 2018 when there is sufficient on-reef development stockpiled (2.5 years) to start up the metallurgical plant, albeit at a reduced milling capacity. The full production run rate is planned to be achieved in 2021 and the total LoM project capital is estimated at R1,852 million (in 2015 terms).

In 2015, concurrent with completing the feasibility study, R272 million was spent on completing the mine-dewatering and permanent pumping infrastructure, re-aligning the shaft steelwork for rock-hoisting, and completing approximately 2km of development to commence accessing the orebody. The development was completed utilising the existing mechanised development machines which were first refurbished before being put back into production. Three development fleets of equipment were in production by year end.

In 2016, R531 million was spent in the first full year of the feasibility study build-up where the expenditure provided for:

 

·

 

4,950m of development. In the fourth quarter, with all development fleets in production, 1,915m of the planned 2,100m was produced and the team’s performance has steadily improved

 

·

 

mine infrastructure running costs

 

·

 

planned project capital infrastructure

 

·

 

procurement of additional mechanised mining fleets and ancillary support vehicles

The budget for 2017 has been revised to R400 million – compared to an initial budget of R672 million – to deliver 6,000m of access development (this is a reduction from the feasibility study’s 8,300m of access development) and to run the mine in support of this revised plan and defer certain project infrastructure.... »


https://www.sec.gov/Archives/edgar/data/1561694/000155837017002504/sbgl-20161231x20f.htm

https://cfcanada.fticonsulting.com/GBGL/docs/FTI%20GBGL%20Receiver's%20Fourth%20Report.pdf

CREDIT SUISSE AG has filed a case in the Supreme Court of British Columbia seeking information from former Great Basin Gold Ltd. director Walter Segsworth over what it sees as a massive mine ...
https://www.pressreader.com/canada/stockwatch-daily/20160831/281479275846850
Be the first to comment on this post
The Market Update
{{currentVideo.title}} {{currentVideo.relativeTime}}
< Previous bulletin
Next bulletin >

At the Bell logo
A daily snapshot of everything
from market open to close.

{{currentVideo.companyName}}
{{currentVideo.intervieweeName}}{{currentVideo.intervieweeTitle}}
< Previous
Next >
Dealroom for high-potential pre-IPO opportunities