Comment by
bogfit on Dec 01, 2021 11:25am
"the grinding, flotation, thickening, and concentrate filtration circuits performing well mechanically. " I would like more information on recovery percentages. Is the ore chemistry basically homogeneous? Even so it can take a few months to get the grind correct for maximum recovery. b.
Comment by
ZouZS3 on Dec 01, 2021 3:44pm
Further updates on the Companys 2022 development plan will be released shortly." fans are on schedule to arrive on site in approximately 3 weeks with installation and commissioning expected to be completed on time
Comment by
patchh on Dec 01, 2021 9:05pm
Lateral development continues on multiple headings, providing access to ore mining zones in the East South orebody and advancing development towards the East North orebody.