Timeline forecasts from 3/12 NR:
Feb: several test pits dug and material processed thru washplant. Implied grade has yielded positive results
Mar: further minor modifications expected to increase recovery rates. Heaviest rains of year? First revenue from gold.
April: handle constant processing of moderate volumes. Heaviest rains of year? Coming weeks 2 more trommels from Songea modified for gold and form the backbone of 2 other washplant systems
Early April: full time daily production
Mid April: deliveries of essential earth moving equipment to the production site from the Songea and DES areas
End of April: All mining equipment repaired and moved onsite by end of April
Late summer: maximum daily ore process rates from entire fleet—(3 trommels, 200 tons/hr?)