Phase 1 to Phase 2 Development at Sangdong
Related to the comment today, and mentioned previously, about having loads of ore already at the site from underground development.
In the ramp up from phase 1 to phase 2 production levels, can someone remind me if all of the work required for this doubling of production is underground or is there upgrades to the processing plant.
I think I recall a discussion that the processing plant already has ample capacity for the doubled production level but don't recall with certainty.
The reason I ask, and I understand that benefits of ramping up production in a methodical way thanks to past posts on this forum, but would it be possible to increase production, closer to phase 2 levels before the underground work for phase 2 is complete because of all of the ore already available on site?
Thanks for any input.
Comment by
QuarterDollar on Apr 18, 2024 10:22am
I vaguely recall LB saying that Almonty can process significantly more than 1.2M tonnes. I was left with the impression of 50% or more.
Comment by
5ilverlining808 on Apr 18, 2024 10:44am
I was just picking a possible percentage, but if you remember that (and now that rings a bell to me), then I would say "yes" without any hesitation at all. This CEO thinks way outside of the box and might come from a different planet to us. I still tip my hat to him.
Comment by
QuarterDollar on Apr 18, 2024 11:05am
for sure LB is a strategic thinker. I believe in an interview, LB referred to Almonty being able handle double capacity when either he talked about the installation of the mills or when the Dept of Commerced approached him, but it was 1-2 years ago.