Fredfudpucker00 on May 20, 2022 5:11pm
Article
On Northern Ontario Business havealook.
Mining the Northwest: Mine builder aims for early 2023 construction start of Marathon palladium mine
Comment by
JAUBE123 on May 20, 2022 5:30pm
Why does Drew say approval by October when it's 90 days? Is that like final approval after EA is approved?
Comment by
Specific on May 20, 2022 6:15pm
I think provincial is 90 days and 120 days thereafter for federal. Or vice versa
Comment by
Sacks45 on May 20, 2022 6:59pm
The Panel gets 90 days and governments get 120. That is 7 months which would bring us to dec 2022 maybe January 2023. Drew said October for both Panel and governments is what they are hoping for.
Comment by
Mistyblue on May 21, 2022 9:26am
Better add another three months to that timeline for the summer break and the swearing in of a new ON govt.. April 1/23 ???