Q4-21 Production = Lower than Guidance due to abnormally elevated levels of rainfall in November and December.
2021 Production Guidance = 11,400 - 11,800. Mid = 11,600 tonnes
Actual 2021 Production = 10,319 tonnes = 1,081 tonnes or 9.5% below lower-end production guidance.
Actual Q4-21 Production = 2,003 tonnes = 1,257T or ~38% lower than Q3-21, 1,067T or ~35% lower than Q2-21 and about the same as Q1-21 (which was impacted by a planned shut-down).