To PUT In PERSPECTIVE: How Much Is 354 MW ?
The Liberals are criticizing the Coalition Avenir Qubec for granting a 354-megawatt energy block to the multinational without setting a deadline, while refusing electricity supplies to other Quebec companies that want to decarbonize.
https://stockhouse.com/companies/bullboard?symbol=t.su&postid=36236120 ^^^
- the NEWEST natural gas-powered ELECTRIC POWER PLANT built in Canada is in Alberta (Cascade Power Project)
* power output: 900MW
* 2 X 450MW {steam turbine COUPLED with gas turbine generator}
* Cost: C$ 1.5 Billion
- so ~ 39% of the Cascade Power Project electric power CAPACITY
- the 354 MW power block in Quebec is GENERATED by HYDROPOWER