Milestone/Kronau Mine
They have said there will be 50 semi loads of potash coming out of the plant per day starting Nov 29.
Comment by
mdjbrown on Nov 06, 2023 10:54pm
U11672, who are "They", you are refering too as I have not seen that reported anywhere. Is the dredge now officially dredging in the pond, as without an operating dredge there will be no potash to load.
Comment by
User11672 on Nov 07, 2023 1:40pm
I live in a nearby community and heard that western potash had a meeting with people in kronau/surrounding area about where they were at with the plans. I was recently out at the mine as a contractor and seen the way things were coming along
Comment by
mdjbrown on Nov 07, 2023 8:05pm
Thank you for the update U11672. Was the dredge in the pond then, as if there is plan to fill 50 semis a day at the end of this month, there should already be a huge stockpile of potash on site.
Comment by
skygarden on Nov 30, 2023 5:27pm
User11672on Nov 06, 2023 6:28pm Milestone/Kronau Mine They have said there will be 50 semi loads of potash coming out of the plant per day starting Nov 29. Was it just some of the local residents who were gossiping about this as a possibility? I would think something like 50 semi loads daily would have a statement from the company.
Comment by
Wiser8SST on Mar 13, 2024 11:18am
Very slim chance of any semi loads of potash leaving this site before next winter. Load out is still not finished the construction phase. Contractors removed from site, due to low cash flow. Dredge is still siting on shore line. Drilling rig removed from site in Feb, and caverns not fully developed.
Comment by
oldsalt72 on Mar 13, 2024 9:22pm