Capacity of Taiwan Plant vs Demo Plant
Based on what we know...
Demo Plant Capacity
- 500 kg/day x 1.63 higher leaching capacity achieved = 815 kg/day
- 815 kg/day x 365 days/yr = 297,475 kg/yr
- 297,475 kg/yr / 1000 kg/tonne = approx 300 tonnes/yr
Taiwan Plant Capacity
- 2000 tonnes/yr
So Taiwan's capacity will be about 7 times that of the demo plant.
EagleNest.
Comment by
Trachy on Jul 08, 2023 7:40am
And what is the costs vs market price lithium, cobalt, nickel, manganese, aluminum at this full capacity of 2000 tonnes/yr? What would they earn at current prices? Hard to say, no? How much lithium,cobalt, nickel, manganese, aluminum are in those 300 tonnes, what''s the ratio of each?