from another chat:
"$CWSFF just got back from visiting the Aldersyde site again this morning (Saturday) and wouldn't you know it, plant manager Kevin was still there and work was progressing. These guys don't fool around. They don't take Saturdays off. I don't think they take 'any' days off.
The entire desulphurization module is installed. The final stage is underway of insulating pipe and whatever else they have to insulate for heat control. Kevin said that task will be completed in 10 days or less. Then they will pressure the entire system up and make sure all pressures are holding rock solid. Once pressures are proven, the 'commissioning' begins with actual feedstocks going through. He said that should take 3 weeks or less. He expects they'll be fully underway, producing top grade desulphurized product in the last week of June... exactly as promised.
These guys are just awesome."