Heritage Miran West-1 was spud 21 December 2008 and reached a total depth of 2,935 metres on 25 March 2009.
This gives a drilling penetration rate of approximately 31 meters per day.
Using the above Heritage drill penetration rates; LFD should be able to drill to 1700 meters in approximately 54 days.
The first 2 LFD wells will be drilled and completed very quickly one after the other.
When LFD mobilizes the rig, they will contract to drill 2 wells, one immediately after the other.