8 more months of drilling?
10,000 meters of core so far this year and 15,000 meters to go.
At the present rate of drilling 2 drills took 8 months to drill 10,000 meters, so with 3 drills now turning the remaining 15,000 meters should take another 8 months.
So not halfway through the campaign, where the drills go after FDP?, or will they remain at FDP/Butia.
Lots of results to come.
Approximately 10,000 metres of a 25,000-metre drilling budget has been completed on the LDS project since the beginning of 2024. Most of the drilling has focused on Buti and Fazenda do Posto.
Comment by
Trevor111 on Sep 09, 2024 10:39pm
Drilling will be more efficient with change of seasons. Lavras lost a few months due to rainy season. I expect far more news/results next3months