The 2022 FS , based on using the Nuggett Pond gold circuit , estimated milling costs per ton at just over $48 ....see link below.
The last full year of production by Signal , The Pine Cove mill had a milling cost of $26.24 per ton milled.
Note also that the upgraded Pine cove mill will have a recovery close to 98 % versus about 87 % previously.
This gain in recovery efficiency will also lower milling costs of the Pine Cove mill.
In summary, the updated HD FS will show substantial decline in milling costs due to the Pine Cove mill having much greater milling efficiency .
In addition , there will be close to 100 km reduction in trucking distance , as the Pine Cove mill is that distance per trip closer to HD.
From these two cost perspectives , the updated FS will show substantially reduced milling and trucking costs..
https://maritimeresourcescorp.com/maritime-resources-reports-positive-feasibility-study-for-hammerdown-gold-project-with-48-1-irr/