NOT FOR DISSEMINATION OR DISTRIBUTION IN THE UNITED STATES AND NOT FOR
DISTRIBUTION TO US NEWSWIRE SERVICES.
MELBOURNE, Australia, Jan. 21, 2013 /CNW/ - OceanaGold Corporation (ASX: OGC, TSX: OGC, NZX: OGC) (the "Company") is pleased to release its fourth quarter report for
the quarter ended 31 December 2012, in accordance with the Australian
Securities Exchange ("ASX") Listing Rule 5.1. Please note that the
numbers contained in this document are unaudited and subject to
finalisation. As a Toronto Stock Exchange ("TSX") listed company, the
Company will release its complete 2012 audited financial and
operational results on 14 February 2013 (Australian Eastern Daylight
Time). A conference call to discuss the results will take place on 15
February 2013.
Key Highlights
-
Fourth quarter 2012 gold production of 76,844 ounces resulting in gold
production of 232,909 ounces for 2012
-
Fourth quarter 2012 gold sales of 69,761 ounces sold at unaudited cash
costs of US$638 per ounce
-
FY2012 gold sales of 230,119 ounces at unaudited cash costs of $940 per
ounce
-
First marketable grade copper-gold concentrate produced at Didipio in
December 2012
Mick Wilkes, Managing Director and CEO commented, "I am pleased to
report that OceanaGold finished 2012 with strong production from the
New Zealand operations resulting in production and cash cost guidance
for the year being met. As expected both Macraes and Reefton delivered
higher grades to the mill during the fourth quarter and thus production
was up 55% on the previous quarter."
He went on to say, "Throughout the year, the Didipio Project team has
consistently met each Project milestone and in December, construction
was completed on schedule and first saleable copper-gold concentrate
produced. Another major milestone was also met last week when the first
truckloads of concentrate were delivered to the port. Daily plant
throughput rates have reached annualized rates of 2.4Mtpa and are well
ahead of our ramp-up schedule for this point in the commissioning
program. However, following a minor incident during commissioning we
have identified some deficiencies in the tailings delivery system that
require modifications. We will be making these improvements over the
next few weeks to ensure long-term reliability as the plant ramps up to
3.5 Mtpa. During this time the plant will be temporarily off-line."
Mr. Wilkes continued, "2013 is a transformational year for the Company
as we transition Didipio to operations and become a multi-national gold
producer consolidating on the great gains we have made in 2012."
Operations
Fourth quarter gold production of 76,844 ounces was up 55% on the
previous quarter bringing the total for 2012 to 232,909 ounces. Macraes
Goldfield fourth quarter production was 58,872 ounces representing an
increase of 60% compared to the third quarter due primarily to higher
grades and improved gold recoveries. Reefton Goldfield fourth quarter
production was 17,972 ounces representing an increase of 42% compared
to the previous quarter, which was mainly attributable to the higher
grades through the mill from the Souvenir Pit, and improved gold
recoveries.
Subsequent to the year end, the Macraes Open Pit experienced a major
movement of the footwall, an area of the mine that has been subject to
frequent movement over the past 16 years. In this case, a heavy
rainfall event has triggered the ground movement resulting in
restricted access to high grade ore at the base of the pit for a period
of 16 days. The monitoring system in place gave ample warning of the
higher movement allowing all personnel and equipment to be evacuated
from the pit and underground without harm. Access to the underground
was re-established and normal operations recommenced there after four
days. Access to the base of the open pit has now been re-established
and further rehabilitation of the haul roads in this area is ongoing.
Mining activities have continued unaffected in other areas of the open
pit. The Company expects that this will have some effect on production
for the first quarter as high grade ore stockpiles on the ROM are
consumed. Production over the year is expected to be variable by
quarter as grade profiles vary, combined with the timing of planned
plant maintenance etc. An update on the effect of this event on full
year production will be provided in due course however it is not
expected to affect the 2013 production guidance range provided last
month.
Revenue for the fourth quarter was US$119 million with the average gold
price received during the period being US$1,705 per ounce on 69,761
ounces sold. Unaudited cash costs were US$638 per ounce for the fourth
quarter and US$940 for the full year 2012, which was below the
Company's revised cost guidance of US$1,000 to US$1,050 per ounce. The
decrease in cash costs from the third quarter 2012 was mainly
attributable to higher ounces of gold sold.
- Table 1 -
Combined Operating Statistics
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Combined Operating Statistics
|
|
Q4
Dec 31 2012
|
|
Q3
Sep 30 2012
|
|
Q4
Dec 31 2011
|
|
Year
2012
|
|
Year
2011
|
|
Year
2010
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gold Produced (ounces)
|
|
76,844
|
|
49,514
|
|
65,750
|
|
232,909
|
|
252,499
|
|
268,602
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Ore Mined (tonnes)
|
|
2,219,617
|
|
1,674,062
|
|
2,310,815
|
|
6,872,686
|
|
8,103,693
|
|
7,905,464
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ore Mined Grade (grams/tonne)
|
|
1.60
|
|
1.08
|
|
1.26
|
|
1.34
|
|
1.21
|
|
1.43
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Waste Mined (tonnes) incl pre-strip
|
|
14,059,837
|
|
12,904,895
|
|
14,369,845
|
|
54,580,473
|
|
59,176,017
|
|
57,643,657
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mill Feed (dry milled tonnes)
|
|
1,826,880
|
|
1,889,121
|
|
1,902,368
|
|
7,432,375
|
|
7,588,354
|
|
7,081,488
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mill Feed Grade (grams/tonne)
|
|
1.59
|
|
1.01
|
|
1.31
|
|
1.20
|
|
1.25
|
|
1.45
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Recovery (%)
|
|
82.8%
|
|
80.7%
|
|
82.2%
|
|
81.0%
|
|
82.9%
|
|
81.6%
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- Table 2 -
Macraes Operating Statistics
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Macraes Goldfield
Operating Statistics
|
|
Q4
Dec 31 2012
|
|
Q3
Sep 30 2012
|
|
Q4
Dec 31 2011
|
|
Year
2012
|
|
Year
2011
|
|
Year
2010
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gold Produced (ounces)
|
|
58,872
|
|
36,874
|
|
44,451
|
|
169,609
|
|
174,851
|
|
182,759
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Ore Mined (tonnes)
|
|
1,815,587
|
|
1,350,939
|
|
1,894,369
|
|
5,558,056
|
|
6,589,904
|
|
6,365,855
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ore Mined Grade (grams/tonne)
|
|
1.57
|
|
1.06
|
|
1.12
|
|
1.29
|
|
1.07
|
|
1.26
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Waste Mined (tonnes) incl pre-strip
|
|
9,496,424
|
|
8,457,277
|
|
10,489,708
|
|
36,363,043
|
|
44,407,352
|
|
43,944,947
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mill Feed (dry milled tonnes)
|
|
1,454,089
|
|
1,465,357
|
|
1,470,713
|
|
5,789,255
|
|
5,817,001
|
|
5,458,607
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mill Feed Grade (grams/tonne)
|
|
1.52
|
|
0.96
|
|
1.14
|
|
1.12
|
|
1.12
|
|
1.28
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Recovery (%)
|
|
83.2%
|
|
81.1%
|
|
82.5%
|
|
81.1%
|
|
83.3%
|
|
81.3%
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- Table 3 -
Reefton Operating Statistics
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Reefton Goldfields
Operating Statistics
|
|
Q4
Dec 31 2012
|
|
Q3
Sep 30 2012
|
|
Q4
Dec 31 2011
|
|
Year
2012
|
|
Year
2011
|
|
Year
2010
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gold Produced (ounces)
|
|
17,972
|
|
12,640
|
|
21,299
|
|
63,300
|
|
77,648
|
|
85,843
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Ore Mined (tonnes)
|
|
404,030
|
|
323,123
|
|
416,446
|
|
1,314,630
|
|
1,513,789
|
|
1,539,609
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ore Mined Grade (grams/tonne)
|
|
1.71
|
|
1.18
|
|
1.87
|
|
1.56
|
|
1.80
|
|
2.11
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Waste Mined (tonnes) incl pre-strip
|
|
4,563,413
|
|
4,447,618
|
|
3,880,137
|
|
18,217,430
|
|
14,768,665
|
|
13,698,710
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mill Feed (dry milled tonnes)
|
|
372,791
|
|
423,764
|
|
431,655
|
|
1,643,120
|
|
1,771,353
|
|
1,622,881
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mill Feed Grade (grams/tonne)
|
|
1.84
|
|
1.16
|
|
1.89
|
|
1.48
|
|
1.67
|
|
2.01
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Recovery (%)
|
|
81.1%
|
|
79.5%
|
|
81.3%
|
|
80.6%
|
|
81.4%
|
|
82.5%
|
Didipio Project Construction & Commissioning
In the fourth quarter, construction activities at the Didipio Project
transitioned to commissioning with the crushing circuit commissioned in
October and milling activities commencing in November. In December, the
Company announced production of first copper-gold concentrate with the
process plant ramp up achieving higher than expected daily throughput
rates by year end. Throughput rates are steadily increasing and have
approached 2.5Mtpa rates with recoveries of greater than 80% for gold
and 85% for copper already being consistently achieved. Last week, the
first truckloads of marketable copper-gold concentrate were delivered
to the port. Some areas requiring modifications have been identified
including the tailings delivery system that is being examined for long
term-term reliability as the plant ramps up to 3.5Mtpa rate. With the
plant ramping up faster than expected, these works will be undertaken
over the next few weeks resulting in the process plant being
temporarily off-line as is necessary to facilitate these improvements.
In the fourth quarter, OceanaGold continued to invest in community
projects in Didipio and neighbouring communities. This includes a
US$1.4 million commitment toward the development of a municipality road
project to connect Didipio to the municipalities of Kasibu, Solano and
Bambang in Nueva Vizcaya. A number of other OceanaGold funded projects
were completed during the quarter including construction of new
classrooms at the local elementary and secondary schools as well as
local community road and bridge upgrades. As part of the Company's
commitment to President Aquino's National Greening Program, the Company
continued to advance its agroforestry program with the reforestation of
22 hectares of land in Barangay Debibi.
On December 3rd, Category 5 super Typhoon Pablo hit the southern
Philippine island of Mindanao causing mass devastation throughout the
island. OceanaGold provided assistance to the Philippines Natural
Disaster response team in support of the Typhoon Pablo relief efforts.
This assistance included medicine, water and blankets as well as
logistical assistance.
Exploration
Exploration expenditure for the quarter was $4.1 million. The majority
of the expenditure was in New Zealand where exploration activities at
Reefton continued to focus on deep drilling at the historic Blackwater
mine and a combination of helicopter assisted diamond drilling and
reverse circulation (RC) drilling along strike to the north and south
of the Blackwater mine. At Blackwater, the third deep drill hole
(WA25) commenced to test the northern strike extent of the Birthday
Reef. Results from this drill hole are expected in the first quarter
of 2013.
Exploration activities at the Macraes Goldfield continued with the
diamond drill program at the Frasers Underground mine. The program was
completed in December and results have confirmed mineralisation to the
north and north-east of the current workings and mineralisation remains
open on both ends.
In the Philippines, exploration focused on preparation for scout
drilling at Mogambos and D'Beau. Through surface exploration
activities and geological modelling, the Company identified additional
anomalous gold and porphyry-style copper-gold mineralisation prospects
within its FTAA boundary. The FTAA exploration extension permit is
expected in the near-term.
FY2012 Results Release and Conference Call
The Company will release its 2012 financial results on 14 February 2013
and host a conference call / webcast to discuss the results at 8:30am
on Friday 15 February 2013 (Melbourne, Australia time) / 4:30pm on
Thursday 14 February (Toronto, Canada time).
Webcast Participants
To register, please copy and paste the link below into your browser:
http://event.on24.com/r.htm?e=565560&s=1&k=FC1F98ECAEA5F711F3D3E7103FB92153
Teleconference Participants (required for those who wish to ask
questions)
Local (toll free) dial in numbers are:
Australia: 1 800 148 052
New Zealand: 0 800 441 017
Canada & United States: 1 888 390 0605
All other countries (toll): + 1 416 764 8609
Playback of Webcast
If you are unable to attend the call, a recording will be available for
viewing on the Company's website from 11:30am on Friday 15 February
(Melbourne, Australia time) / 7.30pm on Thursday 14 February (Toronto,
Canada time).
About OceanaGold
OceanaGold Corporation is a significant Asia Pacific gold producer with
projects located on the South Island of New Zealand and in the
Philippines. The Company's assets encompass New Zealand's largest gold
mining operation at the Macraes Goldfield in Otago which is made up of
the Macraes Open Pit and the Frasers Underground mines. Additionally on
the west coast of the South Island, the Company operates the Reefton
Open Pit mine. The Company's Didipio Project in northern Luzon,
Philippines is in commissioning and is expected to produce 100,000
ounces of gold and 14,000 tonnes of copper per year on average over an
estimated 16 year mine life. OceanaGold expects to produce 285,000 to
325,000 ounces of gold in FY2013 from the New Zealand and Philippine
operations combined.
OceanaGold is listed on the Toronto, Australian and New Zealand stock
exchanges under the symbol OGC.
Cautionary Statement
Statements in this release may be forward-looking statements or
forward-looking information within the meaning of applicable securities
laws. Any statements that express or involve discussions with respect
to predictions, expectations, beliefs, plans, projections, objectives,
assumptions or future events or performance (often, but not always,
using words or phrases such as "expects" or "does not expect", "is
expected", "anticipates" or "does not anticipate", "plans", "estimates"
or "intends", or stating that certain actions, events or results "may",
"could", "would", "might" or "will" be taken, occur or be achieved) are
not statements of historical fact and may be forward-looking
statements. Forward-looking statements such as production forecasts are
subject to a variety of risks and uncertainties which could cause
actual events or results to differ materially from those reflected in
the forward-looking statements. They include, among others, the
accuracy of mineral reserve and resource estimates and related
assumptions, inherent operating risks and those risk factors identified
in the Company's most recent Annual Information Form prepared and filed
with securities regulators which is available on SEDAR at www.sedar.com under the Company's name. There are no assurances the Company can
fulfil such forward-looking statements and, subject to applicable
securities laws, the Company undertakes no obligation to update such
statements. Such forward-looking statements are only predictions based
on current information available to management as of the date that such
predictions are made; actual events or results may differ materially as
a result of risks facing the Company, some of which are beyond the
Company's control. Accordingly, readers should not place undue
reliance on forward-looking statements. The information contained in
this release is not investment or financial product advice.
SOURCE: OceanaGold Corporation