TORONTO, March 1, 2013 /CNW/ - Gran Colombia Gold Corp. (TSX: GCM)
provides its 2013 outlook and a business update, including its progress
on the development of a new mine and mill at its Pampa Verde Project in
Colombia.
2013 Outlook
As announced on January 25, 2013, Gran Colombia's total gold production
for 2012 was 100,895 ounces, a 10 percent increase over 2011. Fourth
quarter production at the company's Segovia Operations was primarily
impacted by unexpected downtime caused by power disruptions on almost a
daily basis over a 25-day period, beginning in mid-November, that
reduced throughput by about 40% during that period. The power supply
situation in Segovia has since returned to normal and there have been
no recurrences since that time. The company has taken steps to resolve
the issue, including establishing suitable notice periods with the
local power supplier and signing a contract with Colombia based,
Proelectrica & CIA S.C.A. ESP (Proelectrica) to provide backup diesel
generating plants for the company's current Segovia Operations, which
the company expects to be operational in the first half of 2013
"We are focused on the profitability of our existing production at our
Segovia and Marmato operations and we have set 2013 targets that
deliver the cash flow required to meet our current development needs,
while we bring our new Pampa Verde Project to completion on time and
under budget", said Serafino Iacono, Executive Co-Chairman of Gran
Colombia. "The new processing plant and mechanized mining operation
that are part of the Pampa Verde Project will be the foundation of our
Segovia operations of the future".
In 2013, the Company will focus on cost reductions and limiting capital
investments to support an expected production level of 110,000 ounces
of gold. Production at its Segovia Operations is expected to reach
90,000 ounces of gold in 2013 and production from the underground mine
at Marmato is expected to total approximately 20,000 ounces of gold. In
January 2013, management embarked on a comprehensive review of its
operations to identify and implement US$12 million in annual cost
savings. To date, cost actions taken will realize approximately
US$850,000 per month (US$10 million annualized) of savings starting by
March 2013. Further reductions have been identified and are being
evaluated. Management is confident it will reach its cost reductions
target.
In 2013, the company is adopting an "all-in sustaining cash cost"
measure that the company believes more fully defines the total costs
associated with producing gold. All-in sustaining cash costs include
cash costs (on a by-product credit basis), sustaining capital,
corporate general and administrative expenses (G&A) and exploration
expense. As the measure seeks to reflect the full cost of gold
production from current operations, new project capital is not included
in the calculation. For 2013, the company expects its all-in sustaining
cash cost to be approximately US$1,380 per ounce of gold. This
comprises cash operating cost of approximately US$1,170 per ounce, G&A
of US$130 per ounce, sustaining capital of US$40 per ounce and Marmato
Project ongoing costs of US$40 per ounce.
Sustaining capital expenditures for 2013 will total approximately US$4.5
million. These will be funded internally from unrestricted cash
balances and operating cash flow and will focus on sustaining capex at
our two operating mines, including the completion of Maria Dama mill
upgrades, the environmental program at Segovia and a crusher upgrade at
the Marmato underground mining operation. An additional US$4.5 million
is expected to be spent on social and other ongoing programs at the
Marmato project site.
Capital expenditures and exploration in support of the Pampa Verde
Project will be funded separately from the proceeds generated by the
gold-linked notes (see October 30, 2012 press release) and are not
included in all-in sustaining cash cost.
The company expects to provide its full 2012 results around the last
week of March 2013.
Pampa Verde Project
As announced on October 30, 2012, Gran Colombia closed a US$100 million
financing with the proceeds to be used for the Pampa Verde project at
the Company's Segovia Operations in Colombia. This new mechanized
mining operation and plant is designed to significantly lower
production costs and increase the production rate to 200,000 ounces of
gold annually. The project includes the construction of a 2,500 tpd
mill and the development of a new, mechanized underground mine to
access new vein deposits, as well as improve access to the existing
mining operations.
The company's cross-functional project team is being lead by Vicente
Mendoza, Chief Project Director at Gran Colombia Gold. The 18-month
project plan has been reviewed and optimized by the new project team to
include new access roads and shaft compared to original ramp design,
resulting in significant cost savings, reducing the estimated total
cost of the project from $90 million to $84 million.
As announced on January 29, 2013, the company purchased some of the
mineral processing equipment required for the new Pampa Verde mill for
US$4.3 million. This purchase includes the semi-autogenous grinding
(SAG) and ball mills, which are typically long lead time items. The
mills are reconditioned and have a capacity of 3,500 tpd. The other
equipment purchased includes crushing feeders, cyclones and pumps,
flotation screens and pumps, regrind pumps, CIL loaded carbon screen
and pumps, carbon regeneration furnace and screen and carbon destruct
pumps and screens. All of the aforementioned items are new and include
many spare parts. The company estimates that the value of the
equipment, if purchased new, is approximately US$12 million. The
selection and procurement of the remaining processing equipment is
ongoing with orders are expected to be placed in early March.
Gran Colombia is negotiating an agreement with Proelectrica to provide a
fully operational, turn-key power plant power to meet the requirements
of the new Pampa Verde plant and mine.
Marmato Project
Gran Colombia's near-term focus at the Marmato Project is to complete
and publish the Prefeasibility Study for the upgrade of its current
underground operation, which the company expects to complete by June
2013.
Webcast
As a reminder, the company will host a conference call and webcast on
Friday, March 1, 2013 at 9:00 a.m. Eastern Time (9:00 a.m. Bogota
time).
Webcast and call-in details are as follows:
|
|
|
Live Event link:
|
|
http://www.media-server.com/m/p/5zwpsvmx
|
|
|
Toronto & International:
|
|
1 (847) 585-4405
|
|
|
North America Toll Free:
|
|
1 (888) 771-4371
|
|
|
Colombia Toll Free:
|
|
01 800 9 156 924
|
|
|
Conference ID:
|
|
34372141
|
The presentation and a replay of the webcast will be available at www.grancolombiagold.com until Monday, April 1, 2013.
About Gran Colombia Gold
Gran Colombia is a Canadian-based gold and silver exploration,
development and production company with its primary focus in Colombia.
Gran Colombia is currently the largest underground gold and silver
producer in Colombia with several underground mines in operation at its
Segovia and Marmato Operations. In addition, Gran Colombia is advancing
a project to develop a large-scale, gold and silver mine at its Marmato
operations.
Additional information on Gran Colombia Gold can be found on the
company's website at www.grancolombiagold.com and by reviewing the
company's page on SEDAR at www.sedar.com.
This news release contains "forward-looking information", which may
include, but is not limited to, statements with respect to the future
financial or operating performance of the Company and its projects and,
specifically, statements concerning anticipated growth in annual gold
production and reduction of cash costs. Often, but not always,
forward-looking statements can be identified by the use of words such
as "plans", "expects", "is expected", "budget", "scheduled",
"estimates", "forecasts", "intends", "anticipates", or "believes" or
variations (including negative variations) of such words and phrases,
or state that certain actions, events or results "may", "could",
"would", "might" or "will" be taken, occur or be achieved.
Forward-looking statements involve known and unknown risks,
uncertainties and other factors which may cause the actual results,
performance or achievements of Gran Colombia to be materially different
from any future results, performance or achievements expressed or
implied by the forward-looking statements. Factors that could cause
actual results to differ materially from those anticipated in these
forward-looking statements are described under the caption "Risk
Factors" in the Company's Annual Information Form dated as of March 28,
2012 which is available for view on SEDAR at www.sedar.com. Forward-looking statements contained herein are made as of the date of
this press release and Gran Colombia disclaims, other than as required
by law, any obligation to update any forward-looking statements whether
as a result of new information, results, future events, circumstances,
or if management's estimates or opinions should change, or otherwise.
There can be no assurance that forward-looking statements will prove to
be accurate, as actual results and future events could differ
materially from those anticipated in such statements. Accordingly, the
reader is cautioned not to place undue reliance on forward-looking
statements.
SOURCE: Gran Colombia Gold Corp.