Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.

Silvercorp Reports Financial and Operating Results for the Third Quarter of Fiscal Year 2014

T.SVM

VANCOUVER, BRITISH COLUMBIA--(Marketwired - Feb. 13, 2014) - Silvercorp Metals Inc. ("Silvercorp" or the "Company") (TSX:SVM)(NYSE:SVM) reported its financial and operating results for the third quarter ended December 31, 2013 ("Q3 Fiscal 2014").

THIRD QUARTER HIGHLIGHTS

  • Silver production of 0.9 million ounces and gold production of 1,985 ounces;
  • Lead production of 9.0 million pounds and zinc production of 1.7 million pounds;
  • Sales of $24.0 million;
  • Gross margin of 44%;
  • Cash flow from operations of $9.9 million, or $0.06 per share;
  • Net income of $2.2 million, or $0.01 per share; and
  • Cash cost per ounce of silver, net of by-product credits, of $2.00.

FINANCIALS

In Q3 Fiscal 2014, net income attributable to equity holders of the Company was $2.2 million or $0.01 per share compared to $5.2 million, or $0.03 per share for the three months ended December 31, 2012 ("Q3 Fiscal 2013").

In Q3 Fiscal 2014, the Company realized sales of $24.0 million, a decrease of 59% from $58.7 million in Q3 Fiscal 2013. The Company's financial results were mainly impacted by the following: (i) lower metal production as silver, lead and zinc production decreased 42%, 45%, and 58% respectively, compared to Q3 Fiscal 2013; and (ii) a significantly lower net realized silver price of $16.20 per ounce in this quarter, down $8.70 per ounce or 35% from $24.90 per ounce in Q3 Fiscal 2013.

Cost of sales in Q3 Fiscal 2014 was $13.5 million compared to $21.2 million in Q3 Fiscal 2013 and included cash costs of $10.9 million compared to $17.1 million in Q3 Fiscal 2013. The decrease of cost of sales was due to the reduction in ore production in this quarter.

The gross profit margin in Q3 Fiscal 2014 was 44%, compared to 64% in Q3 Fiscal 2013.

Cash flow from operations in Q3 Fiscal 2014 was $9.9 million or $0.06 per share, compared to $27.8 million, or $0.16 per share, in Q3 Fiscal 2013.

For the nine months ended December 31, 2013, net loss, attributable to the equity holders of the Company, was $36.5 million or $0.21 per share, which included impairment charges of $42.8 million, net of tax. The impairment reduced the carrying value of the BYP mine, as well as the XBG and Silvertip projects, both of which are sold. Adjusted net income was $6.5 million or $0.04 per share, compared to net income of $20.9 million or $0.12 per share, in the same prior year period. During the same comparative period, sales were $92.3 million compared to $148.5 million, cost of sales was $50.8 million compared to $57.0 million, which resulted in a gross profit margin of 45% compared to 62%.

Cash flow from operations was $33.1 million compared to $71.0 million in the same comparative period. As of December 31, 2013, the Company has $98.0 million in cash and short-term investments.

OPERATIONS

In Q3 Fiscal 2014, on a consolidated basis, the Company produced 0.9 million ounces of silver, 1,985 ounces of gold, 9.0 million pounds of lead, and 1.7 million pounds of zinc, compared to 1.5 million ounces of silver, 5,676 ounces of gold, 16.4 million pounds of lead, and 4.0 million pounds of zinc, respectively, in Q3 Fiscal 2013.

For the nine months ended December 31, 2013, the Company produced 3.3 million ounces of silver, 8,774 ounces of gold, 32.0 million pounds of lead, and 7.6 million pounds of zinc, compared to 4.0 million ounces of silver, 10,810 ounces of gold, 44.1 million pounds of lead and 10.5 million pounds of zinc, in the same prior year period.

1. Ying Mining District, Henan Province, China

In Q3 Fiscal 2014, the Ying Mining District mined 148,850 tonnes of ore, producing 0.9 million ounces of silver, 911 ounces of gold, 8.8 million pounds of lead, and 1.6 million pounds of zinc, compared to 236,694 tonnes of ore in Q3 Fiscal 2013, producing 1.5 million ounces of silver, 1,285 ounces of gold, 15.6 million pounds of lead, and 3.2 million pounds of zinc, respectively.

In Q3 Fiscal 2014, head grades at the Ying Mining District were 202 grams per tonne ("g/t") for silver, 2.9% for lead, and 0.7% for zinc, compared to 222 g/t for silver, 3.2% for lead, and 1.0% for zinc, respectively, in Q3 Fiscal 2013.

In the quarter, mine production and head grades were adversely impacted by a number of factors. Firstly, underground safety standardization work was undertaken in the main production portal of PD924 at the LM West mine and the CM105-S2 Shaft at the SGX mine to comply with new safety regulations. The required safety work included rebuilding the refuge stations, enlarging main access tunnels, and replacing sections of the PVC compress air lines with steel ones, suspending production for approximately one month.

Second, as explained in the prior quarter, the Company identified that dilutive practices of certain mining contractors resulted in head grade declines and took remedial action by modifying the method of calculating the amount of ore mined for the purpose of compensating the contractors and miners. This change in compensation method resulted in miner shortages as some miners felt uncertain about their pay and left the mine sites. Unfortunately, our contractors have experienced difficulty in replacing the departed miners, particularly prior to the Chinese New Year. For this reason, mining in the PD16 Shaft, one of the main portals at the SGX mine, was suspended for approximately two months in this quarter.

Finally, the change in mining strategy, which began approximately a year ago, has yielded mixed results in its initial year of application. The change in mining strategy focused on reducing the use of re-suing method and increasing the use of shrinkage method. The key requirement of this strategy is the ability to control dilution. Certain mines, such as the LM mine, yielded good results, where dilution was low and cash mining cost were reduced. However, in other mines, such as SGX mine, dilution control was inadequate which negatively impacted head grades.

The Company has performed a comprehensive review of its operation at the Ying Mining District. From the review, a series of improvements covering all aspects of operations, including mine planning and strategy, contractor compensation methods, quality control, and a performance-based (linked to tonnage and grade) compensation package for mine management, were enacted. In the next quarter, the Company will monitor the effects of the new improvements and expect to be in a position to provide normalized production guidance for the Ying Mining District when we release our quarterly results in May.

In Q3 Fiscal 2014, total and cash mining costs per tonne were $60.89 and $50.59 compared to $64.47 and $54.92 in Q3 Fiscal 2013, respectively. The decrease in cash mining cost was mainly due to the reduction of contractor fees in this quarter.

For the nine months ended December 31, 2013, the Ying Mining District mined 535,210 tonnes of ore, producing 3.3 million ounces of silver, 3,066 ounces of gold, 31.4 million pounds of lead, and 6.7 million pounds of zinc, compared to 623,523 tonnes of ore producing 4.0 million ounces of silver, 3,352 ounces of gold, 42.8 million pounds of lead, and 9.6 million pounds of zinc in the same prior year period, respectively. During the same comparative period, head grades were 206 g/t for silver, 2.8% for lead, and 0.9% for zinc, compared to 224 g/t for silver, 3.4% for lead and 1.1% for zinc, respectively.

In Q3 Fiscal 2014, total ore milled was 149,755 tonnes, a decrease of 34% compared to 226,764 tonnes in Q3 Fiscal 2013. Cash milling costs per tonne were $16.00 compared to $12.61 in Q3 Fiscal 2013. The increase in unit cost is mainly due to the reduced tonnage milled. For the nine months ended December 31, 2013, total ore milled was 543,221 tonnes compared to 616,389 tonnes in the same prior year period. During the same time period, cash milling costs per tonne were $13.98 compared to $12.92.

In Q3 Fiscal 2014, the consolidated total production cost and cash cost per ounce of silver, net of by-product credits, were $4.39 and $2.00 compared to $1.52 and negative $0.17, respectively, in Q3 Fiscal 2013. For the nine months ended December 31, 2013, the consolidated total production cost and cash cost per ounce of silver, net of by-product credits, were $4.47 and $2.04 compared to $1.66 and negative $0.26, respectively, in the same prior year period.

The overall increase in cash cost per ounce of silver, net of by-product credits, is mainly due to decreases in by-product credits. Compared to the nine months ended December 31, 2012, lead and zinc production in the current fiscal year decreased 27% and 30%, respectively, along with decreases in realized selling price for lead and zinc of 6% and 2%, respectively.

The consolidated operational results for the past five quarters at the Ying Mining District are summarized in the table below:

Quarterly opertional results - Ying Mining District
  Q3 2014
31-Dec-13
Q2 2014
30-Sep-13
Q1 2014
30-Jun-13
Q4 2013
31-Mar-13
Q3 2013
31-Dec-12
Ore Mined (tonne)          
  Direct Smelting Ore (tonne) 715 503 963 1,309 2,334
  Stockpiled Ore (tonne) 148,135 152,599 232,294 152,014 234,360
  148,850 153,102 233,257 153,323 236,694
Run of Mine Ore (tonne)          
  Direct Smelting Ore (tonne) 715 503 963 1,309 2,334
  Ore Milled (tonne) 149,040 156,790 235,210 156,836 224,430
  149,755 157,293 236,173 158,145 226,764
Metal Sales          
  Silver (in thousands of ounces) 883 1,021 1,364 933 1,508
  Gold (in thousands of ounces) 0.9 0.9 1.3 0.8 1.3
  Lead (in thousands of pounds) 8,814 9,519 13,063 9,462 15,642
  Zinc (in thousands of pounds) 1,572 2,199 2,926 1,554 3,231
Head Grade of Run of Mine Ore          
  Silver (gram/tonne) 202 217 200 205 222
  Lead (%) 2.9 2.9 2.7 2.9 3.2
  Zinc (%) 0.7 1.0 0.8 0.7 1.0
Recovery Rate of Run of Mine Ore          
  Silver (%) 93.1 92.7 92.3 93.5 93.3
  Lead (%) 95.7 94.8 94.6 94.5 95.1
  Zinc (%) 64.2 68.5 68.4 60.3 70.4
Cash Mining Cost ($ per tonne) 50.59 45.22 54.95 61.67 54.92
Total Mining Costs($ per tonne) 60.89 56.08 65.09 72.56 64.47
Cash Milling Cost ($ per tonne) 16.00 14.89 12.06 16.05 12.61
Total Milling Cost ($ per tonne) 18.60 17.29 13.62 18.61 14.20
Cash Cost per Ounce of Silver ($) 2.00 0.49 3.23 3.65 (0.17)
           
Total Production Cost per Ounce of Silver ($) 4.39 3.41 5.33 5.82 1.52

2. BYP Mine, Hunan Province, China

In Q3 Fiscal 2014, the BYP mine processed 19,574 tonnes of ore compared to 32,699 tonnes in Q3 Fiscal 2013. During the same comparative periods, the Company sold 1,050 ounces of gold at a cash cost per ounce of gold of $502 compared to 4,309 ounces of gold at a cash cost per ounce of gold of $266, respectively. Gold head grade for Q3 Fiscal 2014 was 2.7 g/t compared to 3.7 g/t in Q3 Fiscal 2013. In Q3 Fiscal 2014, total and cash mining costs per tonne were $53.22 and $22.81 compared to $70.48 and $24.72 in Q3 Fiscal 2013, respectively.

DEVELOPMENT AND EXPLORATION

1. Ying Mining District, Henan Province, China

As at the end of Q3 Fiscal 2014, approximately 2,500 metres ("m") of the development work for the 4,800m access ramp at the LM Mine West are complete.

During the quarter, the Company also completed approximately 18,000m of horizontal tunnels, raises and declines. During the quarter the Company decided to suspend the construction of Shaft 969 at LM Mine West and certain other surface facilities within the Ying Mining District to better allocate resources during the current market.

In Q3 Fiscal 2014, exploration and development expenditures for the Ying Mining District were $8.5 million compared to $9.1 million in Q3 Fiscal 2013. For the nine months ended December 31, 2013, exploration and development expenditures for the Ying Mining District were $26.7 million compared to $28.1 million in the same prior year period.

2. GC Project, Guangdong Province, China

The required surface environmental protection facilities together with water and soil conservation engineering work are complete and have undergone test operations. During the quarter, the concrete rooms for the pumping station and underground main power station at the -50m elevation was completed and the pumps and pipes were installed, which represented the key component prior to the safety inspection, in accordance with safety requirements in the Mine Design.

A temporary Safety Production Permit, valid until the end of June 2014, has been issued to the Company, which allows the Company to conduct trial mine production. A final Safety Production Permit is expected to be issued around the end of June 2014. Before obtaining the Safety Production Permit and commencing significant mining, in the next few quarters, the Company will focus on trial mining and stope preparation work.

As the Company has completed the first phase of mine development and moves to trial mine production, the existing mine contractor, which was originally contracted to carry out mine development, was terminated and is being replaced with a mining contractor specializing in longhole and shrinkage stope mining. Transitioning to the new contractor will take some time and may cause some delays to the start-up of the trial mining.

The Company continued to use development ore to test mill equipment and to fine tune the mill circuits to achieve the desired metallurgical recoveries for silver, lead, zinc, tin, and sulphur. The testing process has identified numerous issues and many improvements were made in the mill circuits. While the floatation test results are approaching the designed recovery rates for silver (60%), lead (85%), zinc (86%), and sulphur, the gravity circuit only recovers approximately 5% tin, significantly lower than the 40% recovery rate in the metallurgic tests. The Company will focus on improving the tin recovery in the next several months.

The tailing dewatering facility for dry stacking has also been improved with modifications to equipment achieving desired results. The construction of the tailing dry stacking dam and reservoir facility has been completed and has passed government inspection.

During Q3 Fiscal 2014, approximately 4,800m of tunnels, including 700m of development tunnels, 2,000m of exploration tunnels and 2,100m of mining preparation tunnels, were completed.

In Q3 Fiscal 2014, $4.6 million (Q3 Fiscal 2013 - $4.7 million) of exploration and development expenditures were incurred at the GC mine. For the nine months ended December 31, 2013, $13.9 million (nine months ended December 31, 2012 - $10.9 million) of exploration and development expenditures were incurred at the GC mine.

3. BYP Mine, Hunan Province, China

In Q3 Fiscal 2014, the construction of the head frame continued. Once completed, the newly completed shaft will facilitate mining of the #3 gold mineralization body and the #5 zinc and lead ore body. In addition, the construction of a 1,500 t/d tailings-backfill facility is complete and trial runs are ongoing. Exploration and development expenditures at the BYP mine were $1.3 million in the current fiscal year compared to $4.6 million in the prior year.

4. X Mines, Henan Province, China

The X Mines consist of two mining projects: the XBG project and XHP project.

During the nine months ended December 31, 2013, the Company entered into a share transfer agreement with an arm's length private Chinese company. Pursuant to the agreement, the Company's subsidiary, Henan Found Mining Co. Ltd., sold its 90% equity interest in Zhongxing Mining Co. Ltd. (XBG project) for $12.5 million (RMB 76 million). This transaction was completed in this quarter.

Since the end of the first quarter, the Company has suspended major activities at the XHP project as part of its cost saving measures.

QUARTERLY DIVIDEND

To maintain the Company's strong balance sheet and liquidity during the current lower metal price environment, on February 12, 2014, the Board of Directors decided to reduce the quarterly dividend from CAD$0.025 to CAD$0.005 per share per quarter. This measure will save the Company approximately $12 million over the next full year, and ensure that the Company remains in a strong position to act on opportunities that develop in the current downturn. The declaration and payment of future dividends is at the discretion of the Board of Directors and any future decision to increase, or eliminate dividend payments will be based on a number of factors including commodity prices, market conditions, financial results, cash requirements and other relevant factors.

Myles Gao, P.Geo., President & CEO, is the Qualified Person for Silvercorp under NI 43-101 and has reviewed and given consent to the technical information contained in this News Release.

This earnings release should be read in conjunction with the Company's Management Discussion & Analysis, Financial Statements and Notes to Financial Statements for the corresponding period, which have been posted on SEDAR at www.sedar.com and are also available on the Company's website at www.silvercorp.ca. All figures are in United States dollars unless otherwise stated.

About Silvercorp

Silvercorp is a low-cost silver-producing Canadian mining company with multiple mines in China. The Company is currently developing the GC project in southern China which it expects will become its next operating mine. The Company's vision is to deliver shareholder value by focusing on the acquisition of under developed projects with resource potential and the ability to grow organically. For more information, please visit our website at www.silvercorp.ca.

CAUTIONARY DISCLAIMER - FORWARD LOOKING STATEMENTS

Certain of the statements and information in this press release constitute "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable Canadian provincial securities laws. Any statements or information that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects", "is expected", "anticipates", "believes", "plans", "projects", "estimates", "assumes", "intends", "strategies", "targets", "goals", "forecasts", "objectives", "budgets", "schedules", "potential" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements or information. Forward-looking statements or information relate to, among other things: the price of silver and other metals; the accuracy of mineral resource and mineral reserve estimates at the Company's material properties; the sufficiency of the Company's capital to finance the Company's operations; estimates of the Company's revenues and capital expenditures; estimated production from the Company's mines in the Ying Mining District; timing of receipt of permits and regulatory approvals; availability of funds from production to finance the Company's operations; and access to and availability of funding for future construction, use of proceeds from any financing and development of the Company's properties.

Forward-looking statements or information are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those reflected in the forward-looking statements or information, including, without limitation, risks relating to: fluctuating commodity prices; calculation of resources, reserves and mineralization and precious and base metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; feasibility and engineering reports; permits and licences; title to properties; property interests; joint venture partners; acquisition of commercially mineable mineral rights; financing; recent market events and conditions; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions into the Company's existing operations; competition; operations and political conditions; regulatory environment in China and Canada; environmental risks; foreign exchange rate fluctuations; insurance; risks and hazards of mining operations; key personnel; conflicts of interest; dependence on management; internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act; and bringing actions and enforcing judgments under U.S. securities laws.

This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements or information. Forward-looking statements or information are statements about the future and are inherently uncertain, and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward-looking statements or information due to a variety of risks, uncertainties and other factors, including, without limitation, those referred to in the Company's Annual Information Form for the year ended March 31, 2013 under the heading "Risk Factors". Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated, described or intended. Accordingly, readers should not place undue reliance on forward-looking statements or information.

The Company's forward-looking statements and information are based on the assumptions, beliefs, expectations and opinions of management as of the date of this press release, and other than as required by applicable securities laws, the Company does not assume any obligation to update forward-looking statements and information if circumstances or management's assumptions, beliefs, expectations or opinions should change, or changes in any other events affecting such statements or information. For the reasons set forth above, investors should not place undue reliance on forward-looking statements and information.

SILVERCORP METALS INC.
Condensed Consolidated Interim Balance Sheets
(Unaudited) (Expressed in thousands of U.S. dollars)
 
  December 31, 2013 March 31, 2013
ASSETS            
Current Assets            
  Cash and cash equivalents $ 79,561   $ 72,283  
  Short-term investments   18,428     45,623  
  Trade and other receivables   6,019     1,442  
  Inventories   6,073     7,522  
  Due from related parties   23     123  
  Prepaids and deposits   5,446     5,118  
    115,550     132,111  
             
Non-current Assets            
  Long-term prepaids and deposits   2,053     1,877  
  Investment in an associate   6,080     6,523  
  Other investments   11,417     15,516  
  Plant and equipment   104,922     103,517  
  Mineral rights and properties   268,107     316,678  
TOTAL ASSETS $ 508,129   $ 576,222  
             
LIABILITIES AND EQUITY            
Current Liabilities            
  Accounts payable and accrued liabilities $ 32,143   $ 29,285  
  Deposits received   8,961     11,497  
  Dividends payable   4,017     4,204  
  Income tax payable   1,224     1,349  
  Due to related parties   1,640     1,207  
    47,985     47,542  
             
Non-current Liabilities            
  Deferred income tax liabilities   15,755     24,603  
  Environmental rehabilitation   6,108     5,974  
Total Liabilities   69,848     78,119  
             
Equity            
  Share capital   233,503     233,082  
  Share option reserve   10,051     8,314  
  Reserves   25,409     24,717  
  Accumulated other comprehensive loss   (927 )   (1,495 )
  Retained earnings   106,307     155,817  
Total equity attributable to the equity holders of the Company   374,343     420,435  
             
Non-controlling interests   63,938     77,668  
Total Equity   438,281     498,103  
             
TOTAL LIABILITIES AND EQUITY $ 508,129   $ 576,222  
             
SILVERCORP METALS INC.
Condensed Consolidated Interim Statements of Income
(Unaudited) (Expressed in thousands of U.S. dollars, except for per share figures)
 
  Three Months Ended
December 31,
  Nine Months Ended
December 31,
2013 2012   2013 2012
                           
Sales $ 23,970   $ 58,717     $ 92,265   $ 148,475  
Cost of sales   13,501     21,241       50,806     57,029  
Gross profit   10,469     37,476       41,459     91,446  
                           
General and administrative   6,338     6,445       20,893     19,482  
General exploration and property investigation   654     1,345       2,466     3,198  
Other taxes   408     854       1,575     2,502  
Foreign exchange gain   (1,667 )   (697 )     (2,750 )   (332 )
Loss on disposal of plant and equipment   21     60       144     85  
Loss on disposal of mineral rights and properties   181     -       181     -  
Share of loss in associate   -     42       153     231  
Impairment on associate   -     9,640       -     9,640  
Impairment of mineral rights and properties   -     -       66,573     -  
Loss on investments   65     78       608     671  
Other income   39     (214 )     (117 )   (382 )
Income (loss) from operations   4,430     19,923       (48,267 )   56,351  
                           
Finance income   1,047     999       2,953     2,841  
Finance costs   (33 )   (24 )     (99 )   (69 )
Income (loss) before income taxes   5,444     20,898       (45,413 )   59,123  
                           
Income tax expense (recovery)   2,300     10,267       (1,734 )   25,471  
Net income (loss) $ 3,144   $ 10,631     $ (43,679 ) $ 33,652  
                           
Attributable to:                          
  Equity holders of the Company $ 2,163   $ 5,236     $ (36,476 ) $ 20,850  
  Non-controlling interests   981     5,395       (7,203 )   12,802  
  $ 3,144   $ 10,631     $ (43,679 ) $ 33,652  
                           
Earnings (loss) per share attributable to the equity holders of the Company                          
Basic earnings (loss) per share $ 0.01   $ 0.03     $ (0.21 ) $ 0.12  
Diluted earnings (loss) per share $ 0.01   $ 0.03     $ (0.21 ) $ 0.12  
Weighted Average Number of Shares Outstanding - Basic   170,878,775     170,748,449       170,813,858     170,720,668  
Weighted Average Number of Shares Outstanding - Diluted   170,925,150     171,072,001       170,813,858     171,072,034  
                           
SILVERCORP METALS INC.
Condensed Consolidated Interim Statements of Cash Flow
(Unaudited) (Expressed in thousands of U.S. dollars)
 
  Three Months Ended
December 31,
  Nine Months Ended
December 31,
  2013 2012   2013 2012
Cash provided by                          
Operating activities                          
  Net income (loss) $ 3,144   $ 10,631     $ (43,679 ) $ 33,652  
  Add (deduct) items not affecting cash:                          
    Unwinding of discount of environmental rehabilitation   33     24       99     69  
    Depreciation, amortization and depletion   2,936     4,463       11,418     11,653  
    Share of loss in associate   -     42       153     231  
    Impairment on associate   -     9,640       -     9,640  
    Impairment of mineral rights and properties   -     -       66,573     -  
    Write down of inventories   -     -       -     348  
    Income tax expense (recovery)   2,300     10,267       (1,734 )   25,471  
    Loss on investments   65     78       608     671  
    Loss on disposal of plant and equipment   21     60       144     85  
    Loss on disposal of mineral rights and properties   181     -       181     -  
    Share-based compensation   561     546       1,878     2,154  
  Income tax paid   (2,111 )   (7,948 )     (5,461 )   (22,323 )
  Changes in non-cash operating working capital   2,743     20       2,948     9,341  
Net cash provided by operating activities   9,873     27,823       33,128     70,992  
                           
Investing activities                          
  Mineral rights and properties                          
    Capital expenditures   (15,922 )   (15,442 )     (42,527 )   (41,855 )
    Proceeds on disposals   13,349     -       13,349     -  
  Plant and equipment                          
    Additions   (1,604 )   (7,138 )     (13,031 )   (24,723 )
    Proceeds on disposals   1,418     -       1,418     -  
  Other investments                          
    Acquisition   -     -       -     (595 )
  Net redemptions (purchases) of short-term investments   4,257     (13,884 )     26,894     (16,239 )
  Proceeds on sale of a subsidiary (net of cash disposed, $4)   3,274     -       8,160     -  
Net cash provided by (used in) investing activities   4,772     (36,464 )     (5,737 )   (83,412 )
                           
Financing activities                          
  Related parties                          
    Payments made   (320 )   (16 )     (1,642 )   (365 )
    Repayments received   102     313       317     972  
  Non-controlling interests                          
    Distribution   (5,168 )   (7,224 )     (5,168 )   (14,612 )
  Cash dividends distributed   (4,148 )   (4,295 )     (12,438 )   (12,820 )
  Proceeds from issuance of common shares   192     126       280     239  
Net cash used in financing activities   (9,342 )   (11,096 )     (18,651 )   (26,586 )
                           
Effect of exchange rate changes on cash and cash equivalents   (1,821 )   1,239       (1,462 )   (118 )
                           
Increase (decrease) in cash and cash equivalents   3,482     (18,498 )     7,278     (39,124 )
                           
Cash and cash equivalents, beginning of the period   76,079     89,334       72,283     109,960  
Cash and cash equivalents included in assets held for sale   -     (1,818 )     -     (1,818 )
                           
Cash and cash equivalents, end of the period $ 79,561   $ 69,018     $ 79,561   $ 69,018  
                           
SILVERCORP METALS INC.
Mining Data
(Expressed in thousands of U.S. dollars, except for mining data figures)
 
  Three months ended December 31, 2013
  Ying
Mining
District
1
X Mines2 BYP Total
           
Production Data          
  Mine Data          
    Ore Mined (tonne)          
    Direct Smelting Ore (tonne) 715 -   - 715
    Stockpiled Ore (tonne) 148,135 -   20,690 168,825
    148,850 -   20,690 169,540
  Run of Mine Ore (tonne)          
    Direct Smelting Ore (tonne) 715 -   - 715
    Ore Milled (tonne) 149,040 3,496 * 19,574 172,110
    149,755 3,496   19,574 172,825
             
  Mining cost per tonne of ore mined ($) 60.89 -   53.22 59.95
    Cash mining cost per tonne of ore mined ($) 50.59 -   22.81 47.20
    Non cash mining cost per tonne of ore mined ($) 10.30 -   30.41 12.75
             
  Unit shipping costs ($) 4.06 -   - 3.57
             
  Milling cost per tonne of ore milled ($) 18.60 -   15.31 18.22
    Cash milling cost per tonne of ore milled ($) 16.00 -   13.76 15.74
    Non cash milling cost per tonne of ore milled ($) 2.60 -   1.55 2.48
             
  Average Production Cost          
    Silver ($ per ounce) 8.83 -   - 9.12
    Gold ($ per ounce) 483 -   959 532
    Lead ($ per pound) 0.42 -   - 0.44
    Zinc ($ per pound) 0.34 -   - 0.35
             
  Total production cost per ounce of Silver ($) 4.39 -     4.39
  Total cash cost per ounce of Silver ($) 2.00 -     2.00
             
  Total production cost per ounce of Gold ($)       959 959
  Total cash cost per ounce of Gold ($)       502 502
             
  Total Recovery of the Run of Mine Ore          
    Silver (%) 93.1 -     93.1
    Gold (%)       92.7 92.7
    Lead (%) 95.7 -     95.7
    Zinc (%) 64.2 -     64.2
             
  Head Grades of Run of Mine Ore          
    Silver (gram/tonne) 202 -     202
    Gold (gram/tonne)       2.7 2.7
    Lead (%) 2.9 -     2.9
    Zinc (%) 0.7 -     0.7
           
Sales Data          
  Metal Sales          
    Silver (in thousands of ounces) 883 2 * - 885
    Gold (in thousands of ounces) 0.9 -   1.1 2.0
    Lead (in thousands of pounds) 8,814 186 * - 9,000
    Zinc (in thousands of pounds) 1,572 100 * - 1,672
           
  Metal Sales          
    Silver (in thousands of $) 14,304 -   - 14,304
    Gold (in thousands of $) 808 -   1,045 1,853
    Lead (in thousands of $) 6,824 -   - 6,824
    Zinc (in thousands of $) 989 -   - 989
  22,925 -   1,045 23,970
  Average Selling Price, Net of Value Added Tax and Smelter Charges          
    Silver ($ per ounce) 16.20 -   - 16.20
    Gold ($ per ounce) 887 -   995 945
    Lead ($ per pound) 0.77 -   - 0.77
    Zinc ($ per pound) 0.63 -   - 0.63
           
1 Ying Mining District includes mines: SGX, TLP, HPG&LM.
2 X Mines includes the XHP project.
* Represents development tunnelling ore at the X mines.
 
SILVERCORP METALS INC. 
Mining Data 
(Expressed in thousands of U.S. dollars, except for mining data figures) 
 
  Three months ended December 31, 2012
  Ying
Mining
District
1
X Mines2 BYP Total
           
Production Data          
  Mine Data          
    Ore Mined (tonne)          
    Direct Smelting Ore (tonne) 2,334 -   - 2,334
    Stockpiled Ore (tonne) 234,360 8,932 * 35,558 278,850
    236,694 8,932   35,558 281,184
  Run of Mine Ore (tonne)          
    Direct Smelting Ore (tonne) 2,334 -   - 2,334
    Ore Milled (tonne) 224,430 27,265 * 32,699 284,394
    226,764 27,265   32,699 286,728
             
  Mining cost per tonne of ore mined ($) 64.47 -   70.48 65.26
    Cash mining cost per tonne of ore mined ($) 54.92 -   24.72 50.98
    Non cash mining cost per tonne of ore mined ($) 9.55 -   45.76 14.28
             
  Unit shipping costs ($) 3.62 -   - 3.15
             
  Milling cost per tonne of ore milled ($) 14.21 -   14.38 14.23
    Cash milling cost per tonne of ore milled ($) 12.61 -   13.49 12.72
    Non cash milling cost per tonne of ore milled ($) 1.60 -   0.89 1.51
             
  Average Production Cost          
    Silver ($ per ounce) 8.53 -   - 9.01
    Gold ($ per ounce) 409 -   646 418
    Lead ($ per pound) 0.27 -   - 0.29
    Zinc ($ per pound) 0.22 -   - 0.23
             
  Total production cost per ounce of Silver ($) 1.52 -     1.52
  Total cash cost per ounce of Silver ($) (0.17) -     (0.17)
             
  Total production cost per ounce of Gold ($)       630 630
  Total cash cost per ounce of Gold ($)       266 266
             
  Total Recovery of the Run of Mine Ore          
    Silver (%) 93.3 -     93.3
    Gold (%)       92.7 92.7
    Lead (%) 95.1 -     95.1
    Zinc (%) 70.4 -     70.4
             
  Head Grades of Run of Mine Ore          
    Silver (gram/tonne) 222 -     222
    Gold (gram/tonne)       3.7 3.7
    Lead (%) 3.2 -     3.2
    Zinc (%) 1.0 -     1.0
           
Sales Data          
  Metal Sales          
    Silver (in thousands of ounces) 1,508 11 * - 1,519
    Gold (in thousands of ounces) 1.3 0.1 * 4.3 5.7
    Lead (in thousands of pounds) 15,642 788 * - 16,430
    Zinc (in thousands of pounds) 3,231 463 * 283 3,977
           
  Metal Sales          
    Silver (in thousands of $) 37,551 -   - 37,551
    Gold (in thousands of $) 1,533 -   4,934 6,467
    Lead (in thousands of $) 12,480 -   - 12,480
    Zinc (in thousands of $) 2,061 -   158 2,219
  53,625 -   5,092 58,717
  Average Selling Price, Net of Value Added Tax and Smelter Charges          
    Silver ($ per ounce) 24.90 -   - 24.90
    Gold ($ per ounce) 1,193 -   1,145 1,155
    Lead ($ per pound) 0.80 -   - 0.80
    Zinc ($ per pound) 0.64 -   0.56 0.63
           
1 Ying Mining District includes mines: SGX, TLP, HPG&LM.
2 X Mines includes the XBG project and XHP project.
* Represents development tunnelling ore at the X mines.
 
SILVERCORP METALS INC.
Mining Data
(Expressed in thousands of U.S. dollars, except for mining data figures)
 
  Nine months ended December 31, 2013
  Ying
Mining
District
1
X Mines2 BYP Total
           
Production Data          
  Mine Data          
    Ore Mined (tonne)          
    Direct Smelting Ore (tonne) 2,181 -   - 2,181
    Stockpiled Ore (tonne) 533,029 -   67,418 600,447
    535,210 -   67,418 602,628
  Run of Mine Ore (tonne)          
    Direct Smelting Ore (tonne) 2,181 -   - 2,181
    Ore Milled (tonne) 541,040 10,425 * 69,621 621,086
    543,221 10,425   69,621 623,267
             
  Mining cost per tonne of ore mined ($) 61.42 -   54.35 60.63
    Cash mining cost per tonne of ore mined ($) 51.02 -   23.48 47.94
    Non cash mining cost per tonne of ore mined ($) 10.40 -   30.87 12.69
             
  Unit shipping costs ($) 4.33 -   - 3.85
             
  Milling cost per tonne of ore milled ($) 16.07 -   15.35 15.99
    Cash milling cost per tonne of ore milled ($) 13.98 -   14.05 13.99
    Non cash milling cost per tonne of ore milled ($) 2.09 -   1.30 2.00
             
  Average Production Cost          
    Silver ($ per ounce) 8.94 -   - 9.28
    Gold ($ per ounce) 503 -   903 570
    Lead ($ per pound) 0.41 -   - 0.42
    Zinc ($ per pound) 0.33 -   0.45 0.34
             
  Total production cost per ounce of Silver ($) 4.47 -     4.47
  Total cash cost per ounce of Silver ($) 2.04 -     2.04
             
  Total production cost per ounce of Gold ($)       899 899
  Total cash cost per ounce of Gold ($)       473 473
             
  Total Recovery of the Run of Mine Ore          
    Silver (%) 92.6 -     92.6
    Gold (%)       92.6 92.6
    Lead (%) 95.0 -     95.0
    Zinc (%) 67.4 -     67.4
             
  Head Grades of Run of Mine Ore          
    Silver (gram/tonne) 206 -     206
    Gold (gram/tonne)       2.9 2.9
    Lead (%) 2.8 -     2.8
    Zinc (%) 0.9 -     0.9
           
Sales Data          
  Metal Sales          
    Silver (in thousands of ounces) 3,269 12 * - 3,281
    Gold (in thousands of ounces) 3.1 0.2 * 5.5 8.8
    Lead (in thousands of pounds) 31,397 590 * - 31,987
    Zinc (in thousands of pounds) 6,697 584 * 282 7,563
           
  Metal Sales          
    Silver (in thousands of $) 55,064 -   - 55,064
    Gold (in thousands of $) 2,909 -   5,991 8,900
    Lead (in thousands of $) 24,006 -   - 24,006
    Zinc (in thousands of $) 4,141 -   154 4,295
  86,120 -   6,145 92,265
  Average Selling Price, Net of Value Added Tax and Smelter Charges          
    Silver ($ per ounce) 16.85 -   - 16.85
    Gold ($ per ounce) 949 -   1,084 1,036
    Lead ($ per pound) 0.76 -   - 0.76
    Zinc ($ per pound) 0.62 -   0.55 0.62
           
1 Ying Mining District includes mines: SGX, TLP, HPG&LM.
2 X Mines includes the XHP project.
* Represents development tunnelling ore at the X mines.
 
SILVERCORP METALS INC.
Mining Data
(Expressed in thousands of U.S. dollars, except for mining data figures)
 
  Nine months ended December 31, 2012
  Ying
Mining
District
1
X Mines2 BYP Total
           
Production Data          
  Mine Data          
    Ore Mined (tonne)          
    Direct Smelting Ore (tonne) 7,027 -   - 7,027
    Stockpiled Ore (tonne) 616,496 19,309 * 89,759 725,564
    623,523 19,309   89,759 732,591
  Run of Mine Ore (tonne)          
    Direct Smelting Ore (tonne) 7,027 -   - 7,027
    Ore Milled (tonne) 609,362 58,349 * 77,862 745,573
    616,389 58,349   77,862 752,600
             
  Mining cost per tonne of ore mined ($) 65.15 -   60.75 64.60
    Cash mining cost per tonne of ore mined ($) 54.53 -   23.86 50.67
    Non cash mining cost per tonne of ore mined ($) 10.62 -   36.89 13.93
             
  Unit shipping costs ($) 3.72 -   - 3.25
             
  Milling cost per tonne of ore milled ($) 14.64 -   15.10 14.69
    Cash milling cost per tonne of ore milled ($) 12.92 -   14.00 13.04
    Non cash milling cost per tonne of ore milled ($) 1.72 -   1.10 1.65
             
  Average Production Cost          
    Silver ($ per ounce) 8.69 -   - 9.07
    Gold ($ per ounce) 425 -   760 452
    Lead ($ per pound) 0.29 -   - 0.31
    Zinc ($ per pound) 0.23 -   - 0.24
             
  Total production cost per ounce of Silver ($) 1.66 -     1.66
  Total cash cost per ounce of Silver ($) (0.26) -     (0.26)
             
  Total production cost per ounce of Gold ($)       752 752
  Total cash cost per ounce of Gold ($)       356 356
             
  Total Recovery of the Run of Mine Ore          
    Silver (%) 92.6 -     92.6
    Gold (%)       92.5 92.5
    Lead (%) 94.5 -     94.5
    Zinc(%) 67.8 -     67.8
             
  Head Grades of Run of Mine Ore          
    Silver (gram/tonne) 224 -     224
    Gold (gram/tonne)       3.1 3.1
    Lead (%) 3.4 -     3.4
    Zinc (%) 1.1 -     1.1
           
Sales Data          
  Metal Sales          
    Silver (in thousands of ounces) 4,009 21 * - 4,030
    Gold (in thousands of ounces) 3.4 0.2 * 7.2 10.8
    Lead (in thousands of pounds) 42,757 1,313 * - 44,070
    Zinc (in thousands of pounds) 9,617 574 * 283 10,474
           
  Metal Sales          
    Silver (in thousands of $) 95,241 -   - 95,241
    Gold (in thousands of $) 3,894 -   8,667 12,561
    Lead (in thousands of $) 34,412 -   - 34,412
    Zinc (in thousands of $) 6,103 -   158 6,261
  139,650 -   8,825 148,475
  Average Selling Price, Net of Value Added Tax and Smelter Charges          
    Silver ($ per ounce) 23.76 -   - 23.76
    Gold ($ per ounce) 1,162 -   1,196 1,185
    Lead ($ per pound) 0.80 -   - 0.80
    Zinc ($ per pound) 0.63 -   0.56 0.63
           
1 Ying Mining District includes mines: SGX, TLP, HPG&LM.
2 X Mines includes the XBG project and XHP project.
* Represents development tunnelling ore at the X mines.

Silvercorp Metals Inc.
Lorne Waldman
Senior Vice President
(604) 669-9397 or Toll Free: 1 (888) 224-1881
investor@silvercorp.ca
www.silvercorp.ca