Eurasia Mining plc (AIM: EUA)
("Eurasia" or the "Company")
West Kytlim Mining operation update - July 2016
Eurasia Mining plc, the PGM and gold mining company, is pleased to update on developments at its
West Kytlim platinum and gold mine. As reported on 21 June 2016, machinery and personnel from both Eurasia and its
contractor SK Region-Stroy ("SKRS") are working at the site building necessary infrastructure and
preparing open pits for mining. Work remains on schedule with the first black sand platinum and gold bearing concentrates
planned for shipment for refining by mid -August 2016.
Highlights:
- Machinery including two excavators, two bulldozers, three dump
trucks and one loader are being operated on a shift rota;
- Water pond to manage processing water now fully
excavated;
- Work is continuing on a trench to protect the open pit from water
ingress;
- Southern end of tailings dump retaining wall now complete, work
continues at the northern end;
- Some washplant components including conveyer belts and parts of
the sluices have arrived, other components due;
- Construction has commenced on the field laboratory which will
upgrade concentrates ahead of shipping for refining.
Further detail
Excellent progress has been made by the team onsite at the West Kytlim Project in the five weeks
since commencing the operation. The preparatory work necessary to organise a safe, effective and environmentally sound work site
to mine an alluvial orebody is now well advanced. As described previously, (see RNS's date 25 May 2016 And 21 June 1016), the
current phase of operations is a start-up operation utilising diesel powered machinery to produce near and at surface ore bodies
in the area known as Malaya Sosnovka. Significant capital expansion to include draglines operating on mains grid power is planned
for year 2 and for the projected ten-year life of mine.
Once preparatory work has been completed the focus will
immediately shift to production from the 5 defined reserve blocks in the Malaya Sosnovka area. Critical elements of the washplant
have arrived to site ahead of time while other longer lead time parts are now due. The washplant when constructed will have
sufficient capacity to fulfil the 2016 mining schedule. A second washplant owned by Eurasia is being refurbished and can be used
to process a small volume of metal bearing gravels before the main washplant is installed.
Documentation and reporting;
The Exploration Project Report covering upgrade of Resource blocks to Reserves, on the entire
21Km2 mining licence will be submitted in the coming weeks. Under the terms of the agreement with SKRS, Eurasia are
responsible for exploration on the licence which will be phased to ensure supply of sufficient reserves for the mining
operation.
Christian Schaffalitzky, MD at Eurasia Mining commented'
"Our 2016 field season is off to an excellent start thanks to the experienced field personnel in
both Eurasia and SKRS. As a consequence we are now a matter of weeks away from producing our first concentrates for refining with
no major delays envisaged. We anticipate that the final components of the washplant will be delivered and the washplant
commissioned within two to three weeks, which gives us enough time to complete the tailings dam and install the final elements of
the mine design, including the facility for upgrading to a shippable black sand concentrate. We are also finalizing our plans for
metal refining which will be announced shortly."
Enquiries:
Eurasia Mining Plc
Christian Schaffalitzky/Michael de Villiers
+44 (0)207 932 0418
WH Ireland Limited
Katy Mitchell/Liam Gribben
+44 (0)161 832 2174
Beaufort Securities
Elliot Hance
+44 (0)207 382 8300
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCQQLFLQDFLBBZ