VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jan. 3, 2017) - Monument Mining Limited (TSX
VENTURE:MMY)(FRANKFURT:D7Q1) "Monument" or the "Company" is pleased to announce the operational readiness work progress at the
Burnakura Gold Project in Western Australia. The Burnakura Gold Project has progressed to early stage gold production to bring
forward cash flow to de-risk its operations.
President and CEO Robert Baldock commented, "The arrival of the crushing circuit at the Burnakura Mine site along with all the
off-site work being completed has reduced construction time by several months according to our implementation plan, this will
allow us to ramp up our targeted gold production quicker than expected."
A photo gallery of the "Operational Readiness Work" at Burnakura can be found in the |
Murchison Photo Gallery at our website: www.monumentmining.com |
Mine Plan Optimization
With the mine optimization, high grade ore will be processed through the CIL plant first, low grade ore will be stockpiled and
processed through heap leach facilities, planned to be constructed during the second year of the gold commercial production. In
April/May 2016 the final design footprint of the Heap Leach facility was finalized.
The internal economic study including the geological models, mine plans, engineering works and economic analysis has been sent
to independent consultants for due diligence review; and additional metallurgical test work and detailed mine delivery schedules
for certain deposits are scheduled to complete early 2017 to mitigate the construction and operation risks, and lift a level of
confidence to achieve targeted economic viability. The internal economic assessment shows that the life of mine for early stage
production could potentially be extended.
Construction
The operational readiness work for early stage production of the CIL plant circuit commenced in April 2016, with the off-site
work being awarded to Como Engineers Pty Ltd ("Como Engineers") to complete. This off-site engineering design, refurbishment and
procurement work has been completed on long lead items including the purchase of a new TRIO CT2436 jaw crusher to replace the
existing crusher on site, new and refurbished feed /discharge conveyors together with supporting steel works, self-cleaning
magnet, triple deck screen and refurbished secondary Symons 51 cone crusher and a fully integrated MCC for plant control. All
equipment was completed and ready for mobilization to the Burnakura mine site.
The first delivery to the Burnakura mine site from Como Engineers transported in mid-December 2016. This crushing circuit was
unloaded at Burnakura and ready for assembly and installation at the mine site, in early 2017, subject to completion of funding
arrangements. The Heap Leach plant equipment including stackers and agglomerator are now stored adjacent to the proposed heap
pad.
The scoping work to complete early recommissioning of the CIL plant was completed in August 2016 ready for planned fabrication
in 2017. A site inspection was completed with Como Engineers and a detailed proposal for primary secondary and tertiary crushing
circuit, together with CIL feed plan and CIL recommissioning plan was proposed and a construction schedule was developed for
implementation. Off-site work has reduced construction time by several months.
Site Development
Pre-stripping and mining are planned to stockpile ore for the CIL mill feed. The stockpile areas have been surveyed and will
be established near the plant for ease of placing material through the heap leach equipment and stacking in due course. Other
mine development activities include completion of a power strategy assessment and building the site power model. Pit dewatering
has been assessed for early stage production.
Since August 2016, ongoing pre-construction site development activities have taken place at the Burnakura mine site including,
preparing the light vehicle and processing workshop ready for construction activities in the New Year. Recommissioning of site
communications and re-establishing the administration and technical service area was completed in September. Preparing the store
area for cataloguing and receipt of first fill inventory for the project was completed in October, 2016. Preparing the Gensets
for mobilizing off site together with preparing the 3KVa Transformer for repair were completed in the same period.
The existing laboratory was cleaned out ready for refurbishment to its new position in November, 2016. Construction of access
road, ROM pad and crusher feed ramp, sorting of store area ready for operational start up have also been completed. The core farm
was reorganized. Plant control laboratory expansion and upgrade and associated works have been completed as well as camp
accommodation and kitchen are prepared in readiness for FEED engineers and mining contractors to arrive on site, anticipated to
be in January 2017.
Permitting
In October 2016 the Project received approval from the Department Environmental Regulation for operation of the proposed
500,000 tonne per annum Heap Leach facility. A Mining Proposal was submitted in December 2016 and it is anticipated that the Mine
Closure Plan will be submitted in January 2017, this will complete all DER licensing requirements for operational readiness. The
Amended Environmental Protection License for Crushing, Heap Leach and Dewatering was received.
Workforce Preparation
The workforce planning and action plan has been submitted to management for review. The key operation management personnel are
now on board including general manager, project manager and chief managing geologist, among other additions.
The Company's production decision is not based on a feasibility study of mineral reserves demonstrating economic and technical
viability under NI 43-101 standards. Therefore, there is increased uncertainty with economic and technical risks of failure
associated with this project, including but not limited to the risk that mineral quantities and grades might be lower than
expected, and construction or ongoing mining and milling operations are more difficult or more expensive than expected;
production and economic variables may vary considerably, due to the absence of detailed economic and technical analysis prepared
in accordance with NI 43-101. There is no guarantee that production will begin as anticipated or at all or that that the
production will be able to generate positive cash flow as anticipated in order to return the Company's capital investment.
About Monument
Monument Mining Limited (TSX VENTURE:MMY)(FRANKFURT:D7Q1) is an established Canadian gold producer that owns and operates the
Selinsing Gold Mine in Malaysia. Its experienced management team is committed to growth and is advancing several exploration
and development projects including the Mengapur Polymetallic Project, in Pahang State of Malaysia, and the Murchison Gold
Projects comprising Burnakura, Gabanintha and Tuckanarra in the Murchison area of Western Australia. The Company employs
approximately 240 people in both regions and is committed to the highest standards of environmental management, social
responsibility, and health and safety for its employees and neighboring communities.
Robert F. Baldock, President and CEO |
Monument Mining Limited |
Suite 1580 -1100 Melville Street |
Vancouver, BC V6E 4A6 |
FOR FURTHER INFORMATION visit the company web site at www.monumentmining.com.
"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."
Forward-Looking Statement
This news release includes statements containing forward-looking information about Monument, its business and future plans
("forward-looking statements"). Forward-looking statements are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the Company's plans with respect to its mineral projects and the timing
and results of proposed programs and events referred to in this news release. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such
words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur"
or "be achieved". The forward-looking statements in this news release are subject to various risks, uncertainties and other
factors that could cause actual results or achievements to differ materially from those expressed or implied by the
forward-looking statements. These risks and certain other factors include, without limitation: risks related to general
business, economic, competitive, geopolitical and social uncertainties; uncertainties regarding the results of current
exploration activities; uncertainties in the progress and timing of development activities; foreign operations risks; other risks
inherent in the mining industry and other risks described in the management discussion and analysis of the Company and the
technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at www.sedar.com.
Material factors and assumptions used to develop forward-looking statements in this news release
include: expectations regarding the estimated cash cost per ounce of gold production and the estimated cash flows which may
be generated from the operations, general economic factors and other factors that may be beyond the control of Monument;
assumptions and expectations regarding the results of exploration on the Company's projects; assumptions regarding the future
price of gold of other minerals; the timing and amount of estimated future production; the expected timing and results of
development and exploration activities; costs of future activities; capital and operating expenditures; success of exploration
activities; mining or processing issues; exchange rates; and all of the factors and assumptions described in the management
discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the
profile of the Company on SEDAR at www.sedar.com. Although the Company
has attempted to identify important factors that could cause actual results to differ materially from those contained in
forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or
intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on
forward-looking statements. The Company does not undertake to update any forward-looking statements, except in accordance
with applicable securities laws.