Vancouver, British Columbia--(Newsfile Corp. - July 11, 2017) - Austral Gold Limited (ASX: AGD) (TSXV: AGLD) ("Austral" or the
"Company") is pleased to announce the filing on SEDAR and the ASX of a Technical Report, prepared in accordance with National
Instrument 43-101 and JORC Code, on the Guanaco and Amancaya Gold Project, Region II, Chile, dated 16 June, 2017, with an effective
date of 31st December 2016 (the "Technical Report"). The Technical Report supports the Company's pre-feasibility
study, disclosed in the Company's announcement dated 9 June 2017.
Highlights of the Technical Report;
- After-Tax Net Present Value (NPV): $US71.3m at a 5.0% discount rate*
- Mine life of 5 years, based on Mineral Reserves
- Metal prices: based on a ramp-up from current prices to reserve prices of $US1,300/oz gold and $US20/oz silver, based on
consensus of independent forecasts
- All-In Sustaining Cost ("AISC") of $US892/oz gold
- Combined average annual production of approximately 53,000 ozs gold, 370,000 ozs silver.
- Metallurgical recovery estimated to average 92% for gold, 80% for silver for the new processing plant
- Average operating cost over the mine life is $US111 per tonne milled.
- Life of Mine ("LOM") sustaining capital costs total $US66.4 million, including reclamation
and closure.
- No additional CAPEX requirements for operation are envisaged, as all infrastructure plant and equipment has been fully funded
as of end of December, 2016.
*Due to an adjustment to the capital cost estimate, economic results differ slightly from the Company's previous News Release on
June 9, 2017.
Stabro Kasaneva, CEO of Austral Gold stated: "This is a significant step for Austral Gold in executing on its focus on
high-margin production growth. Once the new processing plant enters operation the Company plans to transport the high grade
Amancaya production, currently being stockpiled at Amancaya, to the new plant. We hope to see the efficiencies of the new plant
positively impact our cash flow, with gold recoveries expected to improve by at least 25%. We hope to complete final commissioning
of the new plant shortly and commence combined operations thereafter."
SUMMARY OF RESERVE AND RESOURCE ESTIMATES
Table 1: Amancaya and Guanaco Mineral Reserves - as at December 31, 2016
Austral Gold Ltd. - Guanaco and Amancaya Gold Project
|
Area |
Category |
Tonnage
(kt) |
Grades (g/t) |
Contained Metal Ounces (koz) |
Au |
Ag |
AuEq |
Au |
Ag |
AuEq |
Amancaya
|
Underground |
Proven & Probable |
693 |
6.48 |
42.5 |
7.05 |
144.4 |
946.7 |
157.1 |
Open Pit |
Probable |
255 |
7.56 |
119.5 |
9.16 |
61.9 |
978.1 |
75.0 |
All |
Proven & Probable |
948 |
6.77 |
63.2 |
7.61 |
206.3 |
1,924.7 |
232.1 |
Guanaco |
Underground |
Proven & Probable |
490 |
2.99 |
3.6 |
3.04 |
47.1 |
57.3 |
47.9 |
Combined |
All |
1,438 |
5.48 |
42.9 |
6.05 |
253.4 |
1,982.1 |
280.0 |
Notes: Amancaya Mineral Reserve
1. Mineral Reserves followed the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") Definitions, 2014 and are
compliant with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves ("JORC") Code,
2012.
2. Underground Mineral Reserves are estimated at a break-even cut-off grade of 2.5 g/t AuEq for stopes and an incremental cut-off
grade of 1.5 g/t AuEq for drifts. Open Pit Mineral Reserves are estimated at a cut-off grade of 1.53 g/t AuEq.
3. Mineral Reserves are estimated using an average long-term gold price of US$1,300 per ounce and silver price of US$20 per ounce.
4. Gold Equivalents (AuEq) were calculated as AuEq = Au + 0.0134 x Ag, based on a Au and Ag price of $1,300/oz and $20/oz and
recoveries of Au and Ag of 92% and 80%, respectively.
5. A minimum mining width of 1.5 m was used for stopes and 3.5 m for drifts.
6. Stope dilution: 0.5 m in the hanging wall and 0.5 m in the footwall (1.0 m total).
7. Drift dilution: 0.25 m in each of the side walls (0.5 m total).
8. Bulk density is 2.5 t/m3.
9. Numbers may not add due to rounding.
Notes: Guanaco Mineral Reserve
1. Mineral Reserves followed CIM definitions, 2014 and are compliant with the JORC Code.
2. Mineral Reserves are estimated at a break-even cut-off grade of 2.0 g/t AuEq for stopes and an incremental cut-off grade of 1.0
g/t AuEq for drifts.
3. Mineral Reserves are estimated using an average long-term gold price of US$1,300 per ounce and silver price of US$20 per ounce.
4. Gold Equivalents (AuEq) were calculated as AuEq = Au + 0.0134 x Ag, based on a Au and Ag price of $1,300/oz and $20/oz and
recoveries of Au and Ag of 92% and 80%, respectively.
5. A minimum mining width of 1.5 m was used for stopes and 3.5 m for drifts.
6. Stope dilution: 0.5 m in the hanging wall and 0.5 m in the footwall (1.0 m total).
7. Drift dilution: 0.25 m in each of the side walls (0.5 m total).
8. Bulk density is 2.5 t/m3.
9. Numbers may not add due to rounding.
Table 2: Amancaya and Guanaco Mineral Resources -as at December 31, 2016
Austral Gold Ltd. - Guanaco and Amancaya Gold Project
Location
|
Area
|
Category
|
Tonnes
(kt) |
Grades (g/t) |
Ounces (koz) |
Au |
Ag |
AuEq |
Au |
Ag |
AuEq |
Amancaya |
Open Pit
|
Indicated |
171.5 |
11.24 |
177.5 |
13.6 |
62.0 |
978.9 |
75.1 |
Inferred |
59.7 |
7.57 |
110.0 |
9.0 |
15.0 |
210.0 |
20.0 |
Underground
|
Indicated |
633.2 |
9.21 |
54.5 |
9.9 |
187.4 |
1,109.5 |
202.3 |
Inferred |
900 |
6.7 |
31.4 |
7.2 |
195 |
910 |
210 |
Total
|
Indicated |
804.7 |
9.64 |
80.7 |
10.7 |
249.4 |
2,088.4 |
277.4 |
Inferred |
960 |
6.8 |
36 |
7.3 |
210 |
1,110 |
220 |
Guanaco |
Underground |
Measured |
641.0 |
3.02 |
12.9 |
3.2 |
62.0 |
266.0 |
65.8 |
Indicated |
1552.0 |
2.86 |
13.0 |
3.0 |
143.0 |
650.0 |
151.0 |
Inferred |
1200 |
2.6 |
13 |
2.8 |
100 |
500 |
110 |
Combined |
All
|
Measured |
641.0 |
3.02 |
12.9 |
3.2 |
62.0 |
266.0 |
65.8 |
Indicated |
2,356.7 |
5.17 |
36.1 |
5.7 |
392.4 |
2,738.4 |
428.4 |
Total M+I |
2,997.7 |
4.71 |
31.2 |
5.1 |
454.4 |
3,004.4 |
494.2 |
Inferred |
2,150 |
4.5 |
23 |
4.7 |
310 |
1,600 |
330 |
Notes: Amancaya Resource
1. Mineral Resources followed CIM definitions, 2014 and are compliant with the JORC Code.
2. Mineral Resources are reported inclusive of Mineral Reserves.
3. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
4. Open pit Mineral Resources are reported at a cut-off grade of 1.5 g/t AuEq. Pit optimization shells were used to constrain the
resources. Underground Mineral Resources are estimated at a cut-off grade of 2.5 g/t AuEq beneath the open pit shells.
5. Mineral Resources are estimated using a long-term gold price of US$1,300 per ounce, and a silver price of US$20 per ounce.
6. Gold Equivalents (AuEq) were calculated as AuEq = Au + 0.0134 x Ag, based on a gold and silver price of $1,300/oz and $20/oz and
recoveries of gold and silver of 92% and 80%, respectively.
7. Minimum width for the open pit resource is 1.0 m and 1.5 m for the underground resource.
8. Bulk density is 2.50 t/m3.
9. Numbers may not add due to rounding.
Notes: Guanaco Resource
1. Mineral Resources followed CIM definitions, 2014 and are compliant with the JORC Code.
2. Mineral Resources are reported inclusive of Mineral Reserves and do not include dilution.
3. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
4. Mineral Resources are reported at a 1.5 g/t AuEq cut-off grade where AuEq = Au + (0.0134 * Ag).
5. Mineral Resources are estimated using a long-term gold price of US$1,300 per ounce, and a silver price of US$20 per ounce.
6. Gold Equivalents (AuEq) were calculated as AuEq = Au + 0.0134 x Ag, based on a Au and Ag price of $1,300/oz and $20/oz and
recoveries of Au and Ag of 92% and 80%, respectively.
7. A minimum mining width of 1.5 m was not used for the estimation of the Mineral Resource.
8. Bulk density is 2.50 t/m3.
9. Numbers may not add due to rounding.
The conversion of the Indicated Resources into Mineral Reserves for Amancaya is approximately 84%, reflecting the high-grade
nature of the deposit. Inferred Resources are not included in the Mineral Reserve estimate or the economic analysis.
BACKGROUND
The Guanaco Gold Project is currently held by Austral Gold through its wholly-owned subsidiary Guanaco Mining Company Ltd (GMC).
GMC has a 99.99% interest in Guanaco Compañía (Cía.) Minera SpA (GCM), the subsidiary entity in Chile that owns and currently
operates the Guanaco Mine. The Guanaco Gold Project has produced approximately 50,000 oz of gold per year for the last four years
and is projected to continue at this rate for the next five years, as described in the LOM plan. Following purchase of the Amancaya
project from Yamana Gold in 2014 and an infill drilling program in 2016 the Company has been assessing the possibility to run both
Guanaco and Amancaya as a combined operation, with all production treated at a new processing plant built at Guanaco. RPA was
commissioned to undertake the Technical Report used by the Company to undertake a Pre-Feasibility Study.
MINING METHODOLOGY
The mining methodology used at Guanaco consists of sub-level open stoping (SLOS) and mining is carried out by following the
veins with drifts on two levels, separated by 16 m (20 m floor to floor). The main production at Guanaco comes from the Cachinalito
West vein, with additional production coming from the Dumbo and Perseverancia veins.
Stopes are designed at a minimum mining thickness of 1.5 m with planned dilution of 0.5 m on either side resulting in final
stope widths of 2.5 m. Drifts are designed at 3.5 m with 0.25 m of dilution on either side resulting in a final width of 4 m. Sill
pillars of four metres in height are left every 40 m (vertical) and ten metre wide rib pillars are left every 70 m
(horizontal).
The Amancaya deposit consists of mainly northwest and southeast veins, with dip direction of 70° to 85°. The country rock
comprises highly competent dacite-andesite.
The open pit mine at Amancaya will be carried out as a conventional operation using 30 t trucks and a combination of excavators
and front-end loaders. Waste and ore will be blasted and mined separately using a "trenching" method to reduce the amount of
dilution.
The SLOS mining methods planned at Amancaya are similar to those used at the Guanaco Mine. The Amancaya orebody is generally
thinner than Guanaco resulting in the use of split-blasting to minimize dilution during drift development. Split blasting involves
the separate blasting of ore and waste in the drift face.
Vertical crater retreat (VCR) mining will be used to connect the upper and lower drifts and create an open face for longhole
blasting.
Ore from Amancaya will be hauled by contractor via a 75 km road to the new mill located at the Guanaco mining complex.
The underground operations at Guanaco and Amancaya are designed to produce approximately 1,000 tpd and 800 tpd, respectively.
The open pit at Amancaya is expected to produce 400 tpd. Each operation will overlap to produce an average mill feed of
approximately 1,000 tpd during peak production in 2017 and 2018.
MINERAL PROCESSING
The Company restarted leach pad stacking in September 2010 and the first gold bar was poured in December 2010. With the
acquisition and start of mining at Amancaya, commissioning of a 1,500 tpd agitated leach milling circuit commenced in March 2017,
and is expected to be fully operational by July 2017. The capacity of the mill was selected to allow for potential increases in
production. The new plant is integrated into the existing operation in order to minimize construction and capital costs as much as
possible. The existing crushing operation will be utilized to prepare feed for the milling circuit. The existing Merrill-Crowe
circuit was refurbished to accommodate ore with higher silver concentrations from Amancaya and the zinc precipitate that is
produced in the Merrill-Crowe circuit will be processed in the existing refinery.
The Company plans to direct all ore to the milling circuit and stop heap leaching as soon as the plant is operational. Ore that
is already stacked on the leach pad will continue leaching as long as it is economic to do so. At the end of leaching, the ore will
be rinsed with water to remove residual cyanide that is entrained in the leach pad.
The processing circuits include:
- Three stage crushing circuit
- Reversing conveyor to feed either the heap leach operation or the milling circuit
- Covered stockpile
- Single stage ball milling circuit operated in closed circuit with hydro-cyclones
- Pre-leach thickener
- Three-stage agitated leach circuit
- Three-stage counter-current-decantation (CCD) wash circuit
- Filter feed tank and plate and frame pressure filters to recover solution and produce filtered tailings
- Loading of the tailings with a front end loader and truck haulage to dry tailings deposit
- Dry tailings deposit
- Refurbished Merrill-Crowe circuit for precious metal recovery including:
- Zinc cementation (i.e., precipitation)
From the covered stockpile, two vibrating feeders are used to remove ore from the bottom of the stockpile and feed it to a
series of conveyors that are used to feed the ball mill.
ENVIRONMENTAL, PERMITTING AND SOCIAL CONSIDERATIONS
Environmental Impact Statements ("DIAs") have been approved for the Guanaco and Amancaya Projects, including:
- The Guanaco operation that was permitted by Amax
- Reopening of the Guanaco operation by Austral Gold
- Opening of the Amancaya Mine
- Installing the 33 kV Electrical Transmission Line
In addition to the DIAs, environmental studies and numerous environmental permits have been issued to support mining at Guanaco
and Amancaya, as outlined in Section 20 of the Technical Report.
Due to the remote location, Guanaco and Amancaya do not have a large impact on local residents, which are generally supportive
of mining operations. Environmental studies and environmental permits have been issued to support mining at Guanaco and
Amancaya.
CAPITAL AND OPERATING COST ESTIMATES
The estimated sustaining capital costs for Amancaya and Guanaco from December 31, 2016 forward are summarized in Table 3. Since
the capital costs for the new mill were incurred in 2016, all costs from 2017 forward are treated as sustaining capital costs. The
Company expects to be able fund these from operations. This, however, remains uncertain and the Company will assess any funding
needs on a needs basis.
TABLE 3: SUMMARY OF CAPITAL COSTS
Austral Gold Limited — Guanaco and Amancaya Mines
Sustaining Capital Cost |
Unit |
Value |
Amancaya Mine Development |
US$ '000 |
20,869 |
Guanaco Mine Development |
US$ '000 |
3,029 |
General Sustaining UG Capex |
US$ '000 |
4,020 |
Equipment Lease Payments |
US$ '000 |
18,999 |
Processing |
US$ '000 |
2,081 |
Exploration |
US$ '000 |
9,000 |
Other |
US$ '000 |
552 |
Reclamation and closure |
US$ '000 |
7,876 |
Total Capital Cost |
US$ '000 |
66,426 |
Unit operating costs for the LOM plan are shown in Table 4. The average operating cost over the life of mine is estimated at
US$111 per tonne milled.
TABLE 4: SUMMARY OF LOM UNIT OPERATING COSTS
Austral Gold Limited — Guanaco and Amancaya Mines
Area |
Unit |
Value |
Mining (Amancaya Open Pit) |
US$/t moved |
4.10 |
Mining (Amancaya Open Pit) |
US$/t milled |
58.35 |
Mining (Amancaya Underground) |
US$/t mined |
40.30 |
Mining (Guanaco Underground) |
US$/t mined |
47.56 |
Processing (Mill) |
US$/t milled |
35.14 |
Processing (Heap Leach) |
US$/t milled |
20.00 |
|
|
|
Area |
Unit |
Value |
Mining (Average) |
US$/t milled |
44.99 |
Haul (Amancaya to Guanaco) |
US$/t milled |
8.60 |
Processing (Average) |
US$/t milled |
31.66 |
G&A |
US$/t milled |
25.77 |
Total Unit Operating Cost |
US$/t milled |
111.01 |
The total operating cost over the life of mine is estimated at US$160 million.
CASH FLOW ANALYSIS
Considering Guanaco and Amancaya on a stand-alone basis, the undiscounted pre-tax cash flow totals $93 million over the current
mine life.
After-Tax Net Present Values (NPV) at various discount rates are:
- 5% discount rate is $71.3 million.
- 7.5% discount rate is $66.1 million.
- 10% discount rate is $61.4 million.
QUALIFIED PERSONS
The Technical Report on the Guanaco and Amancaya Gold Project, Region ii, Chile was prepared in accordance with CIM definitions
2014 in National Instrument 43-101 and JORC Code, 2012. The Technical Report has been filed under the company's profile on SEDAR
and the ASX. The RPA Qualified Persons (QPs) for the Guanaco and Amancaya Technical Report include:
- Kathleen Ann Altman, P.E., Ph.D. (Metallurgy)
- Jason J. Cox, P.Eng. (Mineral Reserves)
- Ian Weir, P.Eng. (Mineral Reserves)
- Chester M. Moore, P.Eng., (Mineral Resources)
This press release has been reviewed and approved by the RPA Qualified Persons.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture
Exchange) accepts responsibility for the adequacy or accuracy of this release.
About Austral Gold
Austral Gold Limited is a growing precious metals mining, development and exploration company building a portfolio of quality
assets in Chile and Argentina. The Company's flagship Guanaco project in Chile is a low-cost gold and silver producing mine with
further exploration upside. Austral commenced open-pit mining operations at Amancaya in 2017. Amancaya is 75km from the
Guanaco processing plant, where the Company intends to transport production. A PFS completed in mid-2017 showed robust financial
performance is expected from operating both operations as a combined operation, with five years of mine life from reserves.
The Company also owns 70% and is operator of the underground silver-gold Casposo mine in San Juan,
Argentina. With an experienced local technical team and highly regarded major shareholder, Austral's goal is to continue to
strengthen its asset base through acquisition and discovery. Austral Gold Limited is listed on the TSX Venture Exchange
(TSXV: AGLD), and the Australian Securities Exchange (ASX: AGD). For more information, please consult the company's
website: www.australgold.com
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture
Exchange) accepts responsibility for the adequacy or accuracy of this release.
On behalf of Austral Gold Limited:
"Stabro Kasaneva"
CEO
For Further Information Please Contact:
Mike Brown, VP Corporate Development
mike.brown@australgold.com
Canada: +1 604 568 2496
Australia: + 61 2 9380 7233
South America: + 54 11 4323 7558
Forward Looking Statements
Statements in this news release that are not historical facts are forward-looking statements. Forward-looking statements are
statements that are not historical, and consist primarily of projections - statements regarding future plans, expectations and
developments. Words such as "expects", "intends", "plans", "may", "could", "potential", "should", "anticipates", "likely",
"believes" and words of similar import tend to identify forward-looking statements. Forward-looking statements in this news release
include the Company's plan to transport the high grade Amancaya production currently being stockpiled at Amancaya to its new plant;
its expectation that the new plant will be operational shortly and its plans to direct all ore to the milling circuit and stop heap
leaching as soon as the plant is in operation; the expectation that efficiencies of the new plant will positively impact cash flows
and improve gold recoveries; and those concerning cost and performance projections, including the LOM plan production. All of these
forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause
actual events or results to differ from those expressed or implied, including, without limitation, business integration risks;
uncertainty of production, development plans and cost estimates, metallurgical recoveries, commodity price fluctuations; political
or economic instability and regulatory changes; currency fluctuations, the state of the capital markets, uncertainty in the
measurement of mineral reserves and resource estimates, Austral's ability to attract and retain qualified personnel and management,
potential labour unrest, reclamation and closure requirements for mineral properties; unpredictable risks and hazards related to
the development and operation of a mine or mineral property that are beyond the Company's control, the availability of capital to
fund all of the Company's projects and other risks and uncertainties identified under the heading "Risk Factors" in the Company's
continuous disclosure documents filed on SEDAR. You are cautioned that the foregoing list is not exhaustive of all factors and
assumptions which may have been used. Austral cannot assure you that actual events, performance or results will be consistent with
these forward-looking statements, and management's assumptions may prove to be incorrect. Austral's forward-looking statements
reflect current expectations regarding future events and operating performance and speak only as of the date hereof and Austral
does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or
opinions should change other than as required by applicable law. For the reasons set forth above, you should not place undue
reliance on forward-looking statements.
Austral Gold Limited ABN 30 075 860 472
(ASX: AGD) (TSXV: AGLD)
Suite 203, 80 William St, Sydney NSW 2011 | T +61 2 9380 7233 | F +61 2 8354 0992 | info@australgold.com.au | www.australgold.com.au