VANCOUVER, Aug. 9, 2017 /PRNewswire/ - SSR Mining Inc. (NASDAQ:
SSRM) (TSX: SSRM) ("SSR Mining") reports consolidated financial results for the second quarter ended June 30, 2017.
Paul Benson, President and CEO said, "We delivered another strong quarter as production
exceeded 100,000 gold equivalent ounces, which generated free cash flow to further strengthen our balance sheet to over
$350 million in cash. Pleasingly, we have improved guidance at all operations after a strong first
half and our confidence in the second half outlook. We continue to deliver on our goals to create value and growth for
shareholders through disciplined investment, which now includes greenfields exploration and a third strong operating leg to our
business, the Puna Operations joint venture, in addition to our ongoing Operational Excellence initiatives."
Second Quarter 2017 Highlights:
(All figures are in U.S. dollars unless otherwise noted)
- Continued strong financial performance: Attributable net income of $37.3 million or
$0.31 per share and attributable adjusted net income of $13.0
million or $0.11 per share.
- Increased cash generation: Quarter-end cash increased to $353.5 million, up
$13.0 million, from cash generated by operating activities of $38.6
million.
- Continued strong production: Quarterly attributable production was 102,930 gold equivalent ounces at cash costs of
$682 and AISC of $889 per payable gold equivalent ounce sold.
- Improved annual guidance: Production guidance improved at Seabee and Puna Operations and cash costs guidance
improved at Marigold and Puna Operations.
- Increased tonnage at Marigold: Mined 18.0 million tonnes and stacked 6.9 million tonnes of ore, both a
quarter-on-quarter increase.
- Gold production at Marigold on plan: Produced 55,558 ounces of gold at cash costs of $632 and AISC of $833 per payable ounce of gold sold.
- Higher mill throughput at Seabee: Record monthly ore milled at approximately 1,050 tonnes per day in June,
supporting strong quarterly mill ore tonnage of 928 tonnes per day.
- Robust gold production at Seabee: Produced 20,690 ounces of gold at cash costs of $592 and AISC of $831 per payable ounce of gold sold.
- Exceeded planned operating performance at Pirquitas: Produced 1.9 million ounces of silver, 28% higher than in the
first quarter, contributing to lower quarterly cash costs of $12.15 and AISC of $12.78 per payable ounce of silver sold.
- Extended Pirquitas operating life: Formed Puna Operations joint venture comprised of our Pirquitas property and
Golden Arrow's Chinchillas project whereby we are the operator with a 75% interest.
Marigold mine, U.S.
|
Three months ended
|
Operating data
|
June 30
2017
|
|
March 31
2017
|
|
December 31
2016
|
|
September 30
2016
|
|
June 30
2016
|
Total material mined (kt)
|
17,985
|
|
16,736
|
|
19,559
|
|
19,558
|
|
18,685
|
Waste removed (kt)
|
11,075
|
|
11,062
|
|
13,123
|
|
14,741
|
|
12,005
|
Total ore stacked (kt)
|
6,910
|
|
5,674
|
|
6,436
|
|
4,817
|
|
6,680
|
Strip ratio
|
1.6
|
|
1.9
|
|
2.0
|
|
3.1
|
|
1.8
|
Mining costs ($/t mined)
|
1.67
|
|
1.65
|
|
1.52
|
|
1.48
|
|
1.55
|
Gold stacked grade (g/t)
|
0.31
|
|
0.42
|
|
0.48
|
|
0.42
|
|
0.44
|
Processing costs ($/t processed)
|
0.82
|
|
0.89
|
|
0.80
|
|
0.95
|
|
0.70
|
Gold recovery (%)
|
73.0
|
|
74.0
|
|
75.0
|
|
71.0
|
|
70.7
|
General and admin costs ($/t processed)
|
0.42
|
|
0.52
|
|
0.46
|
|
0.56
|
|
0.38
|
|
|
|
|
|
|
Gold produced (oz)
|
55,558
|
|
55,215
|
|
59,945
|
|
47,456
|
|
47,195
|
Gold sold (oz)
|
57,426
|
|
52,528
|
|
61,308
|
|
47,278
|
|
47,124
|
|
|
|
|
|
|
Realized gold price ($/oz) (1)
|
1,265
|
|
1,214
|
|
1,247
|
|
1,330
|
|
1,259
|
|
|
|
|
|
|
Cash costs ($/oz) (1)
|
632
|
|
585
|
|
585
|
|
636
|
|
663
|
AISC ($/oz) (1)
|
833
|
|
799
|
|
835
|
|
1,139
|
|
1,067
|
|
|
|
|
|
|
Financial data ($000s)
|
|
|
|
|
|
Revenue
|
72,451
|
|
63,762
|
|
77,047
|
|
62,831
|
|
59,197
|
Income from mine operations
|
21,373
|
|
21,327
|
|
28,648
|
|
23,156
|
|
17,641
|
Capital expenditures
|
5,272
|
|
3,043
|
|
3,271
|
|
8,310
|
|
10,154
|
Capitalized stripping
|
4,350
|
|
6,745
|
|
10,171
|
|
13,787
|
|
7,231
|
Exploration expenditures (2)
|
1,538
|
|
1,024
|
|
1,276
|
|
1,145
|
|
1,597
|
|
|
(1)
|
We report the non-GAAP financial measures of realized gold prices, cash
costs and all-in sustaining costs ("AISC") per payable ounce of gold sold to manage and evaluate operating performance at
the Marigold mine. For a better understanding and a reconciliation of these measures to cost of sales, as shown in our
consolidated interim statements of comprehensive income (loss), please refer to "Non-GAAP and Additional GAAP Financial
Measures" in section 12 of our management's discussion and analysis of the financial position and results of operation
for the three and six months ended June 30, 2017 ("MD&A").
|
(2)
|
Includes capitalized and expensed exploration expenses.
|
Mine production
In the second quarter of 2017, the Marigold mine produced 55,558 ounces of gold, in line with the previous quarter
production.
A total of 18.0 million tonnes were mined in the second quarter of 2017, 7% more than the first quarter of 2017, primarily due
to improved weather conditions. Approximately 6.9 million tonnes of ore were delivered to the heap leach pads at an average gold
grade of 0.31 g/t as we completed the current mining phase at the Mackay pit. This compares to 5.7 million tonnes of ore
delivered to the heap leach pads at a gold grade of 0.42 g/t in the first quarter of 2017. Gold grade mined in the second quarter
was 26% lower than the first quarter due to planned pit phase sequencing and mining a higher amount of lower-grade ore as we
completed the deeper phase of the Mackay pit. The strip ratio declined to 1.6:1 in the quarter, an 18% reduction compared to the
previous quarter.
Mine operating costs
Cash costs and AISC per payable ounce of gold sold are non-GAAP financial measures. Please see "Cautionary Note Regarding
Non-GAAP Measures".
Cash costs, which include all costs of inventory, refining costs and royalties, of $632 per
payable ounce of gold sold in the second quarter of 2017 was 8% higher than the first quarter as higher tonnes stacked were at
lower grade resulting in more operating costs being recognized against a similar number of ounces stacked. Total mining costs of
$1.67 per tonne were similar to the first quarter primarily due to the timing of maintenance
repairs on mobile equipment offset by a 7% increase in total tonnes mined. During the second half of the year, mining will
benefit from a short waste haul to an exhausted pit, which we believe should increase mining efficiency and lead to a reduction
in unit cost per tonne mined through the second half of 2017. Processing unit costs were 8% lower in the second quarter of 2017
than in the first quarter of 2017 due to the increase in tonnes stacked. General and administrative unit costs were also lower in
the second quarter of 2017 than in the first quarter due to the increase in tonnes stacked but were comparable on an absolute
basis.
AISC of $833 per payable ounce of gold sold in the second quarter of 2017 increased from
$799 in the first quarter of 2017 predominantly due to higher cash costs as noted above.
Mine sales
A total of 57,426 ounces of gold were sold at an average price of $1,265 per ounce during the
second quarter of 2017, compared to 52,528 ounces of gold sold at a 4% lower average price of $1,214 per ounce during the first quarter of 2017.
Exploration
Exploration activities maintained momentum on Mineral Resource to Mineral Reserve conversion with the objective of maximizing
Mineral Reserve growth in proximity to existing open pit reserves. During the period we completed 15,300 meters of drilling in 55
reverse circulation holes as part of our planned $5.0 million exploration expenditure at the site
for 2017. Drilling was conducted at the Mackay Pit, East Basalt, and North Red Dot targets, with the former two areas
representing Mineral Reserve addition opportunities and the latter being a Mineral Resource addition opportunity.
Drilling at depth in the Mackay Pit and at East Basalt intersected gold mineralization adjacent to the existing Mineral
Reserves pit outline that is expected to expand Mineral Resources.
In the second quarter of 2017, we received results from four drillholes at North Red Dot. Structural and compilation work
completed early in the year was tested in the second quarter confirming continuity of mineral controlling fault systems. We
plan to complete additional drilling with the objective of defining a Mineral Resource in this area in the third quarter of
2017.
As part of our deep sulphide exploration program, we completed and received analytical results from one core hole collared in
the southern part of the Marigold property during the quarter. Drillhole DDH-6421 intercepted 0.39 g/t gold over 43 meters
including 0.15 meters grading 9.86 g/t gold in a sheared carbonaceous mudstone approximately 700 meters below surface. Refer to
Table 1 at the end of this news release for drillhole results. This is our first encounter with mineralized mudstone lithology
typically associated with high grade deposits in Carlin-type systems. We view the result as
encouraging and will review all the data from the deep sulphide exploration program to determine if follow up holes will be
drilled in the second half of 2017.
Seabee Gold Operation, Canada
|
Three months ended
|
Operating data
|
June 30
2017
|
|
March 31
2017
|
|
December 31
2016
|
|
September 30
2016
|
|
Period from
Acquisition to June
30, 2016 (1)
|
Total ore milled (t)
|
84,469
|
|
72,394
|
|
84,526
|
|
82,756
|
|
18,856
|
Ore milled per day (t/day)
|
928
|
|
804
|
|
919
|
|
900
|
|
629
|
Gold mill feed grade (g/t)
|
7.97
|
|
9.22
|
|
7.40
|
|
7.40
|
|
7.79
|
Mining costs ($/t mined)
|
60
|
|
68
|
|
62
|
|
58
|
|
110
|
Processing costs ($/t processed)
|
20
|
|
23
|
|
19
|
|
19
|
|
29
|
Gold recovery (%)
|
97.3
|
|
97.7
|
|
97.0
|
|
96.5
|
|
96.6
|
General and admin costs ($/t processed)
|
50
|
|
59
|
|
44
|
|
37
|
|
61
|
|
|
|
|
|
|
Gold produced (oz)
|
20,690
|
|
21,023
|
|
19,711
|
|
20,142
|
|
6,721
|
Gold sold (oz)
|
17,909
|
|
22,411
|
|
17,229
|
|
21,911
|
|
11,306
|
|
|
|
|
|
|
Realized gold price ($/oz) (2)
|
1,257
|
|
1,233
|
|
1,230
|
|
1,334
|
|
1,278
|
|
|
|
|
|
|
Cash costs ($/oz) (2, 4)
|
592
|
|
574
|
|
595
|
|
661
|
|
663
|
AISC ($/oz) (2, 4)
|
831
|
|
990
|
|
833
|
|
841
|
|
776
|
|
|
|
|
|
|
Financial data ($000s)
|
|
|
|
|
|
Revenue
|
22,502
|
|
27,609
|
|
21,175
|
|
29,214
|
|
14,437
|
Income from mine operations
|
4,083
|
|
4,995
|
|
2,864
|
|
4,126
|
|
1,216
|
Capital expenditures
|
711
|
|
4,760
|
|
1,010
|
|
579
|
|
337
|
Capitalized development
|
2,165
|
|
2,514
|
|
2,432
|
|
2,104
|
|
803
|
Exploration expenditures (3)
|
1,566
|
|
1,953
|
|
829
|
|
1,206
|
|
117
|
|
|
(1)
|
The data presented in this column is for the period from May 31, 2016 to
June 30, 2016, the period for which we were entitled to all economic benefits of the Seabee Gold Operation following our
acquisition of SGO Mining Inc. (formerly Claude Resources Inc.) ("SGO Mining").
|
(2)
|
We report the non-GAAP financial measures of realized gold prices, cash
costs and AISC per payable ounce of gold sold to manage and evaluate operating performance at the Seabee Gold Operation.
For a better understanding and a reconciliation of these measures to cost of sales, as shown in our consolidated interim
statements of comprehensive income (loss), please refer to "Non-GAAP and Additional GAAP Financial Measures" in section
12 of our MD&A.
|
(3)
|
Includes capitalized and expensed exploration expenses.
|
(4)
|
The non-GAAP financial measures of cash costs per payable ounce of gold
sold and AISC per payable ounce of gold sold from the Seabee Gold Operation were adjusted to eliminate the adjustment of
inventory to fair value as at the date of our acquisition of SGO Mining.
|
Mine production
In the second quarter of 2017, the Seabee Gold Operation produced 20,690 ounces of gold.
A near-quarterly record 84,469 tonnes of ore were milled at an average gold grade of 7.97 g/t during the second quarter of
2017. This compares to a total of 72,394 tonnes of ore at an average gold grade of 9.22 g/t in the first quarter. Ore was mined
at both the Santoy and Seabee mines with lower grade ore at Seabee reducing the overall average mill grade during the second
quarter. The Santoy mine complex supplied 76% of ore milled, predominantly from long hole stopes. Gold recovery remained
relatively consistent at 97.3% in the current quarter.
Stope production at Santoy was impacted by a fall of ground early in the second quarter. While there were no injuries to
people or damage to equipment, restrictions were put in place until a full review of the ground support in the area was
completed. These self-imposed restrictions had the effect of reducing tonnage and grade to the plant during the quarter.
Following modifications to the support design and installation, production from Santoy returned to planned levels in June.
During the second quarter, the mill achieved a record average throughput of 928 tonnes per day, 15% higher than the previous
quarter, with a monthly record of 1,049 tonnes per day milled in June, as the site focused on Operational Excellence initiatives
to deliver and process more ore tonnage.
Mine operating costs
Cash costs and AISC per payable ounce of gold sold are non-GAAP financial measures. Please see "Cautionary Note Regarding
Non-GAAP Measures".
Cash costs per payable ounce of gold sold, which include all costs of inventory, refining costs and royalties, were
$592 in the second quarter of 2017, higher than the $574 in the first
quarter of 2017. Costs per tonne mined were $60 in the second quarter of 2017, 12% lower than in
the previous quarter due to higher tonnes mined. Processing and general and administration unit costs were lower by 13% and 15%,
respectively, in the second quarter of 2017 compared to the first quarter of 2017 due to higher tonnes milled; however, the mill
feed grade was 14% lower in the current quarter than in the preceding period with lower production resulting in higher cash costs
in the period.
AISC per payable ounce of gold sold were $831 in the second quarter of 2017, lower than the
$990 in the first quarter of 2017 when a significant portion of planned capital spending was
incurred due to the delivery of capital items over the ice road. Exploration spending also decreased, but spending is consistent
with our objective of adding Mineral Reserves and Mineral Resources at the mine.
Mine sales
A total of 17,909 ounces of gold were sold at an average price of $1,257 per ounce during the
second quarter of 2017 due to a buildup in finished goods inventory, 20% lower than the 22,411 ounces of gold sold at a
comparable price of $1,233 per ounce in the first quarter of 2017.
Exploration
Exploration drilling remained focused on Mineral Resource upgrade and conversion. In the second quarter of 2017, we completed
16,400 meters of underground and 9,700 meters of surface drilling. Underground drilling was active at both mine operations with
the majority of expenditures at the Santoy mine.
Results received during the quarter have been successful at extending existing mineralization at Santoy Gap up to 200 meters
down plunge and still remains open at depth and laterally. Drill results at Santoy 8A have converted a significant area of
Inferred Mineral Resources to Indicated Mineral Resources, and expanded the scope of Inferred Mineral Resources at depth. As a
result, we expect to increase Mineral Reserves in this area to be reported in February 2018. At the Seabee Mine we
completed drill programs on three targets which resulted in an incremental addition to Mineral Resources.
Greenfields exploration on the Seabee property resulted in more positive results at the Carr
target, which is the northern extension of the Santoy shear zone located four kilometers north from Santoy Gap. Late in the first
quarter of 2017, we completed 9 drillholes as follow up to investigate a gold bearing alteration zone with characteristics
similar in nature to Santoy Gap. During the second quarter of 2017 we received encouraging results with our first high grade
intercept at Carr. Drilling is planned to investigate this new discovery further during the 2018
winter drilling season.
At the Fisher property, where we have an option agreement to acquire up to an 80% interest on the adjacent 34,000 hectares
south of the Santoy mine, we mobilized one drill rig to conduct systematic exploration on the southern extension of the Santoy
shear zone as well as other existing gold occurrences identified by previous programs. By the end of the second quarter of 2017,
a camp was established and field work is underway. Drilling is expected to begin later in the third quarter of 2017.
Puna Operations, Argentina (75% interest)
(Amounts presented on a 100% basis unless otherwise stated)
|
Three months ended
|
Operating data
|
June 30
2017
|
|
March 31
2017
|
|
December 31
2016
|
|
September 30
2016
|
|
June 30
2016
|
Ore milled (kt)
|
446
|
|
449
|
|
476
|
|
455
|
|
425
|
Silver mill feed grade (g/t)
|
185
|
|
145
|
|
194
|
|
264
|
|
238
|
Processing costs ($/t milled)
|
12.94
|
|
13.66
|
|
14.17
|
|
14.78
|
|
15.10
|
Silver recovery (%)
|
73.5
|
|
72.6
|
|
74.5
|
|
79.0
|
|
77.6
|
General and admin costs ($/t milled)
|
5.00
|
|
5.22
|
|
6.19
|
|
5.84
|
|
6.22
|
|
|
|
|
|
|
Silver produced ('000 oz)
|
1,947
|
|
1,520
|
|
2,210
|
|
3,047
|
|
2,526
|
Silver produced (attributable) ('000 oz) (1)
|
1,777
|
|
1,520
|
|
2,210
|
|
3,047
|
|
2,526
|
Silver sold ('000 oz)
|
1,655
|
|
1,443
|
|
2,633
|
|
2,947
|
|
2,594
|
Silver sold (attributable) ('000 oz) (1)
|
1,473
|
|
1,443
|
|
2,633
|
|
2,947
|
|
2,594
|
|
|
|
|
|
|
Realized silver price ($/oz) (2)
|
17.31
|
|
17.35
|
|
17.14
|
|
19.64
|
|
16.52
|
|
|
|
|
|
|
Cash costs ($/oz) (2)
|
12.15
|
|
12.68
|
|
9.80
|
|
8.48
|
|
8.87
|
AISC ($/oz) (2)
|
12.78
|
|
14.82
|
|
11.47
|
|
9.87
|
|
10.00
|
|
|
|
|
|
|
Financial Data ($000s)
|
|
|
|
|
|
Revenue
|
22,029
|
|
26,534
|
|
29,095
|
|
51,336
|
|
45,141
|
Income (loss) from mine operations (3)
|
4,006
|
|
13,767
|
|
(4,056)
|
|
31,908
|
|
25,205
|
Capital expenditures
|
420
|
|
2,261
|
|
3,467
|
|
3,158
|
|
2,057
|
Exploration expenditures (4)
|
—
|
|
—
|
|
11
|
|
7
|
|
25
|
|
|
(1)
|
Attributable production and sales figures for the second quarter of 2017
represent 100% for April and May 2017 and 75% for June 2017.
|
(2)
|
We report the non-GAAP financial measures of cash costs per payable
ounce of silver sold, realized silver prices and AISC to manage and evaluate operating performance at Puna Operations
Inc. ("Puna Operations"). For a better understanding and a reconciliation of these measures to cost of sales, as shown in
our consolidated interim statements of comprehensive income (loss), please refer to "Non-GAAP and Additional GAAP
Financial Measures" in section 12 of our MD&A.
|
(3)
|
The income from mine operations for the quarter ended March 31, 2017
includes a non-cash impact of $4.3 million relating to the resolution of the export duty claim in Argentina. Income
(loss) from mine operations for the quarter ended December 31, 2016, includes $5.7 million of severance provision and a
non-cash write-down of supplies inventory and VAT receivable of $3.7 million.
|
(4)
|
Does not include exploration or development of the Chinchillas
project.
|
Mine production
The operation produced a total of 1.9 million ounces of silver from processing of stockpiles, a 28% increase compared to the
first quarter of 2017.
Ore was milled at an average rate of 4,903 tonnes per day in the second quarter, 23% above the mill's nominal throughput of
4,000 tonnes per day. Ore milled in the second quarter of 2017 contained an average silver grade of 185 g/t, 28% higher than the
145 g/t reported in the first quarter of 2017 due to better than expected grades in the stockpiles. The average silver recovery
in the second quarter was 73.5%, higher than the 72.6% recovery in the previous quarter, in line with the higher silver mill feed
grade.
We finalized our joint venture, Puna Operations, to combine the Pirquitas mine with Golden Arrow Corporation's ("Golden
Arrow") Chinchillas project on May 31, 2017. The joint venture is comprised of our Pirquitas
property and the Chinchillas project and is owned on a 75%/25% basis by each company, respectively. We are the joint venture
operator. As a result of the joint venture, our attributable share of production in the second quarter was 1.8 million ounces of
silver and attributable sales were 1.5 million ounces.
Mine operating costs
Cash costs and AISC per payable ounce of silver sold are non-GAAP financial measures. Please see "Cautionary Note Regarding
Non-GAAP Measures".
Cash costs, which include cost of inventory, treatment and refining costs and by-product credits, decreased by 4% to
$12.15 per payable ounce of silver sold in the second quarter of 2017 from $12.68 per payable ounce of silver sold in the first quarter of 2017, principally due to the higher grade of
the stockpiled ore processed. In the second quarter of 2017, the stockpile inventory costs include approximately $3.30 per payable ounce of inventory costs that were previously incurred.
AISC of $12.78 per payable ounce of silver sold were 14% lower in the second quarter of 2017
than the $14.82 per payable ounce of silver sold in the first quarter of 2017 due to lower cash
costs and lower sustaining capital per payable ounce of silver sold.
Mine sales
We recognized sales of 1.7 million ounces of silver in the second quarter of 2017, higher than the 1.4 million ounces in the
first quarter of 2017, as a result of higher production due to processing of higher grade stockpiles. Attributable sales were 1.5
million ounces of silver in the second quarter of 2017 marginally higher than the 1.4 million ounces in the previous quarter.
Chinchillas project, Argentina
The development of the Chinchillas project was initiated on June 1, 2017 following the
completion and filing of the National Instrument 43-101 – Standards of Disclosure for Mineral Projects ("NI 43-101")
technical report on May 31, 2017 and the formation of Puna Operations. The project scope consists
of developing the open pit mine at Chinchillas for delivery of ore to the existing Pirquitas processing plant. Ore will be
transported from the Chinchillas site via conventional 40 tonne trucks on an existing nationally operated road which will be
upgraded to safely transport ore and to minimize environmental and community impacts.
Work at the Chinchillas site will include construction of related mine infrastructure consisting of administration buildings,
haul truck repair shop and ancillary works. Mine design and planning commenced to refine the pre-feasibility study work and
tender packages for the associated supporting infrastructure are expected to be released in the third quarter of 2017. Start of
pre-stripping activities and infrastructure construction is dependent on the issuance of permits which are expected late in the
third quarter of 2017. The project anticipates approximately six months of pre-stripping with associated stockpiling of mined
ore.
Ongoing work at the Pirquitas property will include pumping and piping for tailings deposition in the exhausted open pit and a
dome over the crushed ore stockpile. Minor process plant modifications are required to the existing flotation circuit to process
the Chinchillas silver-zinc-lead ore.
Also, with the Chinchillas deposit as a base load ore source for the Pirquitas plant, we re-evaluated the potential for a
small tonnage Pirquitas underground operation to provide an additional, high grade ore stream to the plant. The initial desktop
study showed that this project is sufficiently attractive to justify more detailed studies in the second half of 2017. If these
are positive, we would look to undertake a preliminary economic assessment in 2018.
Other Projects
SIB project, Canada
Late in the second quarter of 2017, we mobilized two core drills to the SIB exploration project located near the high grade,
past-producing Eskay Creek mine in northwest British Columbia. At
the SIB project, we hold a 3-year option to acquire a controlling interest in the project and plan to spend $3.0 million during 2017 exploring the property by drilling between 6,000 and 9,000 meters in six to ten
diamond drillholes.
The exploration target is for precious metal enriched massive sulphides, and the SIB project boasts the only mineralization
similar to Eskay Creek in the district. At the SIB project, previous work has defined a near
surface zone of high grade gold-silver bearing massive sulphide mineralization. Our 2017 exploration program aims to identify any
extensions to this precious metal enriched massive sulphide zone. To date, three holes have been completed in 2,770 meters of
drilling and have successfully encountered the targeted geology over a strike length of at least 1,000 meters. Analytical results
are anticipated in the third quarter of 2017.
Outlook
This section of the news release provides management's production and cost estimates. See "Cautionary Note Regarding
Forward-Looking Statements."
Due to strong operating performance at all three mines through the first half of 2017 and a continued positive operating
outlook for the second half of 2017, we are improving certain guidance metrics. In addition, with the combination of the
Pirquitas and Chinchillas properties into Puna Operations on May 31, 2017, we have 75% ownership
and attributable production from that date.
At the Marigold mine, annual cash costs midpoint guidance is being reduced by $25 to between
$640 and $670 per payable ounce of gold sold from previous guidance of between $655 and $705 per payable ounce of gold sold, reflecting continued lower diesel prices. Annual production
guidance is unchanged but, due to the lower grades of ore stacked in the first half of the year, third quarter gold production is
expected to be approximately 40,000 to 45,000 ounces with cash costs commensurately higher before expected notable improvement in
the final quarter of the year. Capital guidance at the Marigold mine remains unchanged while capitalized stripping increases
marginally to $20 million reflecting the higher strip ratio in the first quarter.
The Seabee Gold Operation mill continues to operate at higher throughput levels, which combined with the completion of the
Santoy ventilation upgrade project enables production guidance to be increased to between 75,000 and 85,000 ounces of gold. Cash
costs and remaining guidance metrics remain unchanged.
At Puna Operations, higher than expected grades within stockpiles combined with continued high throughput rates and better
than planned recoveries enable silver production guidance to be increased to between 5.0 and 6.0 million ounces. Production in
the third quarter is expected to be stronger than the fourth quarter as progressively lower grade stockpiles are processed. As a
result of the stronger production and ongoing positive cost performance, cash costs midpoint guidance is reduced by $1.50 to between $12.50 and $14.00 per payable ounce of silver sold. Cash costs
include approximately $3.50 per ounce related to historical stockpile value. Capital expenditure
guidance remains unchanged.
Subject to permitting, Puna Operations is expected to start the development of the Chinchillas project towards the end of the
third quarter of 2017. The Chinchillas project is expected to produce on average 8.4 million ounces of annual silver equivalent
production over an eight-year operating life with a modest initial capital investment of $81
million on a 100% basis. We are responsible to fund 75% of development costs and our partner is required to contribute 25%
of development costs, net of any cash generated by the operation utilized to fund development. The full details of our Business
Combination Agreement with Golden Arrow dated September 30, 2015,
setting out the terms and conditions for the formation of the joint venture were set out in our news release dated October 1, 2015.
Revised Operating Guidance
|
|
Marigold mine
|
|
Seabee Gold Operation
|
|
Puna Operations
(75% interest) (3)
|
Gold Production
|
oz
|
205,000 - 215,000
|
|
75,000 - 85,000
|
|
—
|
Silver Production
|
Moz
|
—
|
|
—
|
|
5.0 - 6.0
|
Cash Costs per Payable Ounce Sold (1)
|
$/oz
|
640 - 670
|
|
575 - 625
|
|
12.50 - 14.00
|
Capital Expenditures
|
$M
|
30
|
|
8
|
|
5
|
Capitalized Stripping / Capitalized Development
|
$M
|
20
|
|
11
|
|
—
|
Exploration Expenditures (2)
|
$M
|
5
|
|
5
|
|
—
|
Our original guidance for the full year 2017 was as follows:
Original Operating Guidance
|
|
Marigold mine
|
|
Seabee Gold Operation
|
|
Puna Operations
(75% interest) (3)
|
Gold Production
|
oz
|
205,000 - 215,000
|
|
72,000 - 82,000
|
|
—
|
Silver Production
|
Moz
|
—
|
|
—
|
|
4.5 - 5.5
|
Cash Costs per Payable Ounce Sold (1)
|
$/oz
|
655 - 705
|
|
575 - 625
|
|
13.50 - 16.00
|
Capital Expenditures
|
$M
|
30
|
|
8
|
|
5
|
Capitalized Stripping / Capitalized Development
|
$M
|
17
|
|
11
|
|
—
|
Exploration Expenditures (2)
|
$M
|
5
|
|
5
|
|
—
|
|
|
(1)
|
We report the non-GAAP financial measure of cash costs per payable ounce
of gold and silver sold to manage and evaluate operating performance at the Marigold mine, the Seabee Gold Operation and
Puna Operations. See "Cautionary Note Regarding Non-GAAP Measures".
|
(2)
|
Includes capitalized and expensed exploration expenses.
|
(3)
|
Shown on a 100% basis.
|
|
|
Consolidated Financial Summary
Selected Financial Data (1)
|
|
|
|
|
|
|
Three months ended June 30
|
|
Six months ended June 30
|
|
2017
|
|
2016
|
|
2017
|
|
2016
|
|
$
|
|
$
|
|
$
|
|
$
|
Revenue
|
116,982
|
|
118,775
|
|
234,887
|
|
220,288
|
Income from mine operations
|
29,462
|
|
44,062
|
|
69,551
|
|
67,360
|
Operating income
|
46,193
|
|
24,237
|
|
71,002
|
|
38,851
|
Net income
|
37,747
|
|
12,482
|
|
52,795
|
|
14,783
|
Basic attributable income per share
|
0.31
|
|
0.13
|
|
0.44
|
|
0.17
|
Adjusted attributable income before tax (2)
|
15,551
|
|
26,661
|
|
38,487
|
|
38,261
|
Adjusted attributable net income (2)
|
13,017
|
|
23,622
|
|
32,826
|
|
31,664
|
Adjusted basic attributable income per share (2)
|
0.11
|
|
0.25
|
|
0.27
|
|
0.36
|
Cash generated by operating activities
|
38,614
|
|
30,162
|
|
69,258
|
|
43,487
|
Cash (used in) investing activities
|
(26,311)
|
|
(2,796)
|
|
(44,431)
|
|
(8,640)
|
Cash generated by (used in) financing activities
|
550
|
|
(12,329)
|
|
885
|
|
(13,999)
|
|
|
|
|
Financial Position
|
|
|
June 30, 2017
|
|
December 31, 2016
|
Cash and cash equivalents
|
|
|
353,530
|
|
327,127
|
Marketable securities
|
|
|
174,587
|
|
148,944
|
Current assets (including cash and cash equivalents)
|
|
|
755,770
|
|
704,240
|
Current liabilities
|
|
|
77,959
|
|
144,306
|
Working capital (2)
|
|
|
677,811
|
|
559,934
|
Total assets
|
|
|
1,514,567
|
|
1,438,688
|
|
|
(1)
|
All values are presented in thousands of U.S. dollars, except per share
amounts.
|
(2)
|
We report non-GAAP measures including adjusted attributable income
before- and after-tax and adjusted basic attributable income per share and working capital, to manage and evaluate our
operating performance. Please see "Cautionary Note Regarding Non-GAAP Measures".
|
Quarterly financial summary
The 2% decrease in quarterly revenue compared to the second quarter of 2016 was mainly due lower silver sales partially offset
by higher gold sales. We sold 22% more payable ounces of gold from the Marigold mine and 58% more payable ounces of gold from the
Seabee Gold Operation in the second quarter of 2017 than in the second quarter of 2016, during which we acquired the Seabee Gold
Operation, due to strong production at each operation. Due to the planned lower production from processing stockpiles at Puna
Operations, 36% less ounces of silver were sold relative to the comparative period.
Income from mine operations in the second quarter of 2017 generated a gross margin of 25%, lower than the 37% margin in the
second quarter of 2016 due to higher cost of sales at Puna Operations where we are processing stockpiles from prior periods. Net
income for the second quarter of 2017 of $37.7 million was 202% higher than the comparative quarter
due to continued strong performance and the positive impact of an impairment reversal of the Pirquitas plant of $24.4 million resulting from its life extension following the formation of Puna Operations.
Cash generated by operating activities increased significantly to $38.6 million compared to
$30.2 million in the second quarter of 2016. Strong production at the Marigold mine and the Seabee
Gold Operation resulted in higher volumes of gold sold at lower unit costs, which generated significantly higher cash from
operating activities. In the second quarter of 2017, we paid $4.8 million of principal and interest
under the terms of the tax moratorium system in Argentina into which we entered on March 31, 2017. We used $26.3 million in investing activities in the second
quarter of 2017 compared to $2.8 million in the second quarter of 2016 mainly due to the
Chinchillas project option exercise payment of $13.0 million while the second quarter of 2016
benefited from $16.9 million of cash acquired with our acquisition of the Seabee Gold Operation. In
the second quarter of 2017, our investment in property, plant and equipment was $13.8 million
compared to $22.1 million in the comparative quarter of 2016. Investment in plant and equipment was
$6.8 million lower, underground development at the Seabee Gold Operation was $1.4 million higher and capitalized stripping at the Marigold mine was $2.9
million lower. In the comparative quarter of 2016 we repaid a total of $15.9 million of bank
loans.
Year-to-date financial summary
The 7% increase in revenue compared to the first half of 2016 was due to an 8% increase in equivalent payable gold ounces sold
and higher realized prices of gold by 1% and silver by 11%. The increase in gold ounces sold was largely due to sales from the
Seabee Gold Operation, which we acquired in May 2016, partially offset by 46% lower silver ounces
sold from Puna Operations.
Income from mine operations in the first half of 2017 generated a gross margin of 30%, comparable to the 31% margin in the
first half of 2016 as higher precious metals prices, lower cost of sales at the Marigold mine and the addition of the Seabee Gold
Operation were offset by higher cost of sales at Puna Operations. In the first half of 2017, the resolution of our export duty
claim in Argentina resulted in a $4.3 million reduction to cost of
sales. Net income for the first half of 2017 was also positively impacted by an impairment reversal of the Pirquitas plant of
$24.4 million resulting from its life extension following the formation of Puna
Operations.
Cash generated by operating activities increased significantly to $69.3 million compared to
$43.5 million in the first half of 2016. Higher prices of gold and silver and higher volumes of
gold sold at lower unit costs generated significantly higher cash from operating activities. In the first half of 2017, we paid
$8.2 million of principal and interest under the terms of the tax moratorium system in Argentina into which we entered on March 31, 2017. This included $3.4 million of initial payment, representing 5% of our export duty liability, and subsequent monthly
installments. We used $44.4 million in investing activities in the first half of 2017 compared to
$8.6 million in the first half of 2016. This was mainly due to the Chinchillas project option
exercise payment of $13.0 million in the current period compared to the receipt of $16.9 million of cash as part of the acquisition of the Seabee Gold Operation. Investment in plant and
equipment was lower by $3.2 million but we invested more in capitalized stripping at the Marigold
mine by $2.4 million and in underground development at the Seabee Gold Operation by $3.9 million in the first half of 2017 than in the comparative period of 2016. In the first half of 2016, we
also received $4.4 million from the sale of marketable securities. In the first half of 2016 we
repaid $17.6 million of bank loans.
Qualified Persons
The scientific and technical information contained in this news release relating to the Marigold mine has been reviewed and
approved by Thomas Rice and James N. Carver, each of whom is a SME
Registered Member and a Qualified Person under NI 43-101. Mr. Rice is our Technical Services Manager and Mr. Carver is our Chief
Geologist at the Marigold mine. The scientific and technical data contained in this news release relating to the Seabee Gold
Operation has been reviewed and approved by Cameron Chapman, P.Eng., and Jeffrey Kulas, P. Geo., each of whom is a Qualified Person under NI 43-101. Mr. Chapman is our General Manager
and Mr. Kulas is our Manager Geology, Mining Operations at the Seabee Gold Operation. The scientific and technical information
contained in this news release relating to Puna Operations has been reviewed and approved by Bruce
Butcher, P.Eng., and F. Carl Edmunds, P. Geo., each of whom is a Qualified Person under NI
43-101. Mr. Butcher is our Director, Mine Planning and Mr. Edmunds is our Chief Geologist.
Second Quarter 2017 Deep Sulphide Drill Results at the Marigold mine
Table 1. Second Quarter 2017 Deep Sulphide Drill Results at the Marigold mine, Nevada,
U.S.
Hole ID
|
UTM-N
(Nad27
Zone11)
|
UTM-E
(Nad27
Zone11)
|
Elevation
(masl)
|
From
(meters)
|
To
(meters)
|
Width
(meters)
|
Gold Grade
(g/ tonne)
|
Area
|
DDH6421
|
4,502,386
|
484,319
|
1,823
|
655.3
|
698.3
|
43.0
|
0.39
|
Deep
Sulphide
|
including
|
–
|
–
|
–
|
691.6
|
691.8
|
0.15
|
9.86
|
Deep
Sulphide
|
Note: Drillhole was drilled towards 180 degrees bearing at -80 degrees inclination.
Sampling and Analytical Procedures
All drill samples in respect of the Marigold mine drilling program are sent for processing and analysis to the offices of
American Assay Laboratories, Inc. ("AAL") in Sparks, Nevada which is an ISO 17025 accredited
laboratory independent from SSR Mining. Fire assay was completed on a 30-gram sample (AAL method code FA-PB30-ICP) with an
Inductively Coupled Plasma ("ICP") finish after a two acid digestion. Samples with assay results greater than 10 g/t gold
were fire assayed on a 30-gram sample (AAL method code Grav Au30) with a gravimetric finish. We employ a rigorous Quality
Assurance/Quality Control ("QA/QC") program, which includes real-time assay quality monitoring through the regular insertion of
blanks, duplicates, and certified reference material, as well as reviewing laboratory-provided QA/QC data.
Management Discussion & Analysis and Conference Call
This news release should be read in conjunction with our unaudited condensed consolidated interim financial statements and our
MD&A as filed with the Canadian Securities Administrators and available at www.sedar.com or our website at www.ssrmining.com .
- Conference call and webcast: Thursday, August 10, 2017, at 11:00 a.m.
EDT.
|
Toll-free in U.S. and Canada:
|
+1 (800) 319-4610
|
|
All other callers:
|
+1 (416) 915-3239
|
|
Webcast:
|
ir.ssrmining.com
|
Audio replay will be available for two weeks by calling:
|
Toll-free in U.S. and Canada:
|
+1 (855) 669-9658, replay code 1534
|
|
All other callers:
|
+1 (412) 317-0088, replay code 1534
|
About SSR Mining
SSR Mining, formerly Silver Standard Resources Inc., is a Canadian-based precious metals producer with three operations,
including the Marigold gold mine in Nevada, U.S., the Seabee Gold Operation in Saskatchewan, Canada and the 75% owned and operated Puna Operations joint venture in Jujuy Province,
Argentina. We also have two feasibility stage projects and a portfolio of exploration properties
in North and South America. We are committed to delivering safe production through relentless
emphasis on Operational Excellence. We are also focused on growing production and Mineral Reserves through the exploration and
acquisition of assets for accretive growth, while maintaining financial strength.
For further information contact:
W. John DeCooman, Jr.
Vice President, Business Development and Strategy
SSR Mining Inc.
Vancouver, BC
Toll free: +1 (888) 338-0046
All others: +1 (604) 689-3846
E-Mail: invest@ssrmining.com
To receive SSR Mining's news releases by e-mail, please register using the SSR Mining website at www.ssrmining.com.
Cautionary Note Regarding Forward-Looking Statements
This news release contains forward-looking information within the meaning of Canadian securities laws and forward-looking
statements within the meaning of the U.S. Private Securities Litigation Reform Act of 1995 (collectively, "forward-looking
statements"). All statements, other than statements of historical fact, are forward-looking statements.
Generally, forward-looking statements can be identified by the use of words or phrases such as "expects," "anticipates,"
"plans," "projects," "estimates," "assumes," "intends," "strategy," "goals," "objectives," "potential," "believes," or variations
thereof, or stating that certain actions, events or results "may," "could," "would," "might" or "will" be taken, occur or be
achieved, or the negative of any of these terms or similar expressions. The forward-looking statements in this news release
relate to, among other things: future production of gold, silver and other metals; future costs of inventory, and cash costs,
total costs and AISC per payable ounce of gold, silver and other metals sold; expected exploration and development expenditures;
the prices of gold, silver and other metals; the timing of completion of additional drilling at the Marigold mine; the expected
increase of Mineral Reserves at the Seabee mine; the timing of commencement of drilling at the Seabee mine; the planned
exploration expenditure at the SIB project and the timing of anticipated analytical results therefrom; the timing of release of
tender packages for the Chinchillas project's supporting infrastructure; the timing of receipt of permits for construction at the
Chinchillas project; the timing of pre-stripping and stockpiling at Puna Operations; the effects of laws, regulations and
government policies affecting our operations or potential future operations; our exposure to fluctuations in ARS and interest
rates on the liability under the tax moratorium; the expected devaluation of the Argentine peso; future successful development of
our projects; expected timing of construction of and ore delivery from the Chinchillas project; expected production from the
Chinchillas project and ability to extend the life of Pirquitas operations; the sufficiency of our current working capital,
anticipated operating cash flow or our ability to raise necessary funds; estimated production rates for gold, silver and other
metals produced by us; timing of production and the cash costs and total costs of production at the Marigold mine, the Seabee
Gold Operation and Puna Operations; the estimated cost of sustaining capital; ongoing or future development plans and capital
replacement, improvement or remediation programs; the estimates of expected or anticipated economic returns from our mining
projects, including future sales of metals, concentrate or other products produced by us; our ability to expand Mineral Resources
and convert Mineral Resources into Mineral Reserves; and our plans and expectations for our properties and operations.
These forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that
could cause actual events or results to differ from those expressed or implied, including, without limitation, the following:
uncertainty of production, development plans and cost estimates for the Marigold mine, the Seabee Gold Operation, Puna Operations
and our projects; our ability to replace Mineral Reserves; our ability to obtain necessary permits for the Chinchillas project;
commodity price fluctuations; political or economic instability and unexpected regulatory changes; currency and interest rate
fluctuations; the possibility of future losses; general economic conditions; fully realizing the value of our shareholdings in
Pretium Resources Inc. and our other marketable securities, due to changes in price, liquidity or disposal cost of such
marketable securities; counterparty and market risks related to the sale of our concentrate and metals; uncertainty in the
accuracy of Mineral Reserves and Mineral Resources estimates and in our ability to extract mineralization profitably; differences
in U.S. and Canadian practices for reporting Mineral Reserves and Mineral Resources; lack of suitable infrastructure or damage to
existing infrastructure; future development risks, including start-up delays and cost overruns; our ability to obtain adequate
financing for further exploration and development programs and opportunities; uncertainty in acquiring additional commercially
mineable mineral rights; delays in obtaining or failure to obtain governmental permits, or non-compliance with our permits; our
ability to attract and retain qualified personnel and management; potential labour unrest, including labour actions by our
unionized employees at Puna Operations; the impact of governmental regulations, including health, safety and environmental
regulations, including increased costs and restrictions on operations due to compliance with such regulations; reclamation and
closure requirements for our mineral properties; failure to effectively manage our tailings facilities; social and economic
changes following closure of a mine may lead to adverse impacts and unrest; unpredictable risks and hazards related to the
development and operation of a mine or mineral property that are beyond our control; indigenous peoples' title claims and rights
to consultation and accommodation may affect our existing operations as well as development projects and future acquisitions;
assessments by taxation authorities in multiple jurisdictions; recoverability of VAT and significant delays in the collection
process in Argentina; claims and legal proceedings, including adverse rulings in litigation
against us and/or our directors or officers; compliance with anti-corruption laws and internal controls, and increased regulatory
compliance costs; complying with emerging climate change regulations and the impact of climate change, including extreme weather
conditions; fully realizing our interest in deferred consideration received in connection with recent divestitures; uncertainties
related to title to our mineral properties and the ability to obtain surface rights; the sufficiency of our insurance coverage;
civil disobedience in the countries where our mineral properties are located; operational safety and security risks; actions
required to be taken by us under human rights law; competition in the mining industry for mineral properties; our ability to
complete and successfully integrate an announced acquisition; an event of default under our convertible notes may significantly
reduce our liquidity and adversely affect our business; failure to meet covenants under our senior secured revolving credit
facility; conflicts of interest that could arise from certain of our directors' and officers' involvement with other natural
resource companies; information systems security threats; and those other various risks and uncertainties identified under the
heading "Risk Factors" in our most recent Annual Information Form filed with the Canadian securities regulatory authorities and
included in our most recent Annual Report on Form 40-F filed with the U.S. Securities and Exchange Commission ("SEC").
This list is not exhaustive of the factors that may affect any of our forward-looking statements. Our forward-looking
statements are based on what our management considers to be reasonable assumptions, beliefs, expectations and opinions based on
the information currently available to it. Assumptions have been made regarding, among other things, our ability to carry on our
exploration and development activities, our ability to meet our obligations under our property agreements, the timing and results
of drilling programs, the discovery of Mineral Resources and Mineral Reserves on our mineral properties, the timely receipt of
required approvals and permits, including those approvals and permits required for successful project permitting, construction
and operation of our projects, the price of the minerals we produce, the costs of operating and exploration expenditures, our
ability to operate in a safe, efficient and effective manner, our ability to obtain financing as and when required and on
reasonable terms and our ability to continue operating the Marigold mine, the Seabee Gold Operation and Puna Operations. You are
cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. We cannot assure you
that actual events, performance or results will be consistent with these forward-looking statements, and management's assumptions
may prove to be incorrect. Our forward-looking statements reflect current expectations regarding future events and operating
performance and speak only as of the date hereof and we do not assume any obligation to update forward-looking statements if
circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. For the
reasons set forth above, you should not place undue reliance on forward-looking statements.
Cautionary Note to U.S. Investors
This news release includes Mineral Reserves and Mineral Resources classification terms that comply with reporting standards
in Canada and the Mineral Reserves and the Mineral Resources estimates are made in accordance
with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public
disclosure an issuer makes of scientific and technical information concerning mineral projects. These standards differ
significantly from the requirements of the SEC set out in SEC Industry Guide 7. Consequently, Mineral Reserves and Mineral
Resources information included in this news release is not comparable to similar information that would generally be disclosed by
domestic U.S. reporting companies subject to the reporting and disclosure requirements of the SEC. Under SEC standards,
mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be
economically produced or extracted at the time the reserve determination is made. In addition, the SEC's disclosure standards
normally do not permit the inclusion of information concerning "Measured Mineral Resources," "Indicated Mineral Resources" or
"Inferred Mineral Resources" or other descriptions of the amount of mineralization in mineral deposits that do not constitute
"reserves" by U.S. standards in documents filed with the SEC. U.S. investors should understand that "Inferred Mineral Resources"
have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility.
Moreover, the requirements of NI 43-101 for identification of "reserves" are also not the same as those of the SEC, and reserves
reported by us in compliance with NI 43-101 may not qualify as "reserves" under SEC standards. Accordingly, information
concerning mineral deposits set forth herein may not be comparable with information made public by companies that report in
accordance with U.S. standards.
Cautionary Note Regarding Non-GAAP Measures
This news release includes certain terms or performance measures commonly used in the mining industry that are not defined
under International Financial Reporting Standards ("IFRS"), including cash costs, total costs and AISC per payable ounce of
precious metals sold, realized metal prices, adjusted attributable income (loss) before tax, adjusted attributable income tax
(expense), adjusted net income (loss), adjusted attributable basic earnings (loss) per share and working capital. Non-GAAP
financial measures do not have any standardized meaning prescribed under IFRS and, therefore, they may not be comparable to
similar measures reported by other companies. We believe that, in addition to conventional measures prepared in accordance with
IFRS, certain investors use this information to evaluate our performance. The data presented is intended to provide additional
information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with
IFRS. These non-GAAP measures should be read in conjunction with our consolidated financial statements. Readers should refer to
"Non-GAAP and Additional GAAP Financial Measures" in section 12 of our MD&A, available under our corporate profile at
www.sedar.com or on our website at www.ssrmining.com, for a more detailed discussion of how we calculate such
measures and for a reconciliation of such measures to IFRS terms.
SOURCE SSR Mining Inc.