TORONTO, ON --(Marketwired - August 10, 2017) -
- Informed by the Ministère des Forêts, de la Faune et des Parcs ("MFFP") that the initial permit will take "additional
analysis" and that such analysis is expected to be completed in Spring 2018
- This delay will result in a postponement of the Company making a Development Decision in 2017
- Rogue will re-assess and re-prioritize opportunities across its portfolio and externally
Rogue Resources Inc. (TSX VENTURE: RRS) ("Rogue" or the "Company") is
disappointed to announce a delay in advancing its 100% owned Silicon Ridge Project ("Project"), located approximately 42
kilometres ("km") north of Baie-Saint Paul, Québec, and 4 km northeast of Sitec's operating silica mine.
The Silicon Ridge Project continues to represent an opportunity for the development of a quarrying operation with limited
environmental impacts, operating within an area that currently supports active quarrying operations co-existing with the local
wildlife. The Company has designed its project to minimize the impacts on the wildlife and other stakeholders within the
region.
The Company submitted the application for the bail d'exploitation minière permit ("BEX") in the form and content as described
in Quebec's Mining Act for its Silicon Ridge Project. Based upon communications with the representatives of the MERN, Rogue has
provided all of the required information for the Ministry to complete the application process except for the requirement that the
MFFP provides its decision on the Section 128.7 Authorization.
Rogue has also submitted the application for the Certificate of Authorization ("CofA") with Ministère de Développement
durable, de l'Environnement et de la Lutte contre les changements climatiques ("MDDELCC") and based on communications with
representatives of the MDDELCC, the Company has provided all of the required information for the Ministry to complete the
application process except for the MFFP's Section 128.7 Authorization and the BEX from the MERN.
In this regard, the Company has made numerous requests to the MFFP, including email and meeting requests, for an estimate of
when the decision on the Section 128.7 application will be reached and asked if any additional information was required to
finalize a decision. Prior to the notification provided by the MFFP this week, there were no substantive communications from the
MFFP and the Company continued to be impacted by the lack of clarity on the timing for potential sales contract negotiations and
a development decision for the project.
In a meeting today, the MFFP explained that a decision on the Section 128.7 application will not be made until a policy study
forming part of the Province-wide action plan for the development of forest-dwelling caribou habitat is completed in Spring of
2018.
"This was very surprising and a deeply disappointing message from the MFFP today. We have previously met with them on multiple
occasions and this was never mentioned as a possibility. Silicon Ridge remains a very promising project and we expect it to be a
profitable operation but now the Company will need to assess our near-term options as we will not be able to deliver on the 2017
Plan as outlined. Despite this surprising delay, the Company will continue to engage with potential buyers and attempt to arrange
financing with a view to target 2018 production following receipt of all required permits and approvals," said Sean Samson,
President and CEO of Rogue. "We are currently prioritizing our existing property portfolio and external opportunities and will
provide an update on a work plan as it is developed."
About Rogue Resources Inc.
Rogue is a mining company focused on generating positive cash flow. Not tied to any metal, it looks at rock value and good
grade deposits that can withstand all stages of the metal price cycle. The current focus is Québec's Silicon Ridge Project. For
more information visit www.rogueresources.ca
Qualified Person
The Silicon Ridge Project is under the direct supervision of Paul Davis, P.Geo., VP, Technical and Director of the Company and
a QP as defined by National Instrument 43-101. The QP has approved the scientific and technical content of this release.
On Behalf of Rogue Resources Inc.
Sean Samson
President & CEO, Director
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.
Cautionary Note Regarding Forward-Looking Statements: Certain disclosures in this release may
constitute forward-looking statements. In making the forward-looking statements in this release, the Company has applied certain
factors and assumptions that are based on the Company's current beliefs as well as assumptions made by and information currently
available to the Company, and that actual results are consistent with management's expectations. These statements include, among
others, statements with respect to development activities and their timing, resource estimates and potential mineralization, the
PEA, including estimates of capital costs, anticipated internal rates of return, mine production, processing recoveries, mine
life, estimated payback periods and net present values, plans to decide if the project and resources to be quarried. Although the
Company considers these assumptions to be reasonable based on information currently available to it, they may prove to be
incorrect, and the forward-looking statements in this release are subject to numerous risks, uncertainties and other factors that
may cause future results to differ materially from those expressed or implied in such forward-looking statements. Such risk
factors include, among others, those matters identified in its continuous disclosure filings, including its most recently filed
MD&A, changes in regulatory environments, environmental compliance, operating and capital cost escalation, ability to raise
project financing and silica pricing. Additional factors include delays in obtaining or inability to obtain required regulatory
approvals, permits or financing, risk of unexpected variation in mineral resources, grade or recovery rates, processing plant
failure, equipment or processes to operate as anticipated, of accidents, labour disputes, the risk that estimated costs will be
higher than anticipated, the risk that the proposed mine plan and recoveries will not be achieved, equipment breakdowns, bad
weather timing and success of development activities, mineral resources are not as estimated, title matters, third party
consents, operating hazards, product prices, political and economic factors, competitive factors, the effect of any delay in
obtaining required permits or approvals and general economic conditions. Should any of such assumptions prove to be incorrect or
such risks become actual events, than the value of the Company's securities may decline. Readers are cautioned not to place undue
reliance on forward-looking statements. The Company does not intend, and expressly disclaims any intention or obligation to,
update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as
required by law.