Not for distribution to the U.S. news wire services, or dissemination in the United States.
HONG KONG, Nov. 15, 2017 (GLOBE NEWSWIRE) -- Primeline Energy Holdings Inc. (“Primeline”
or the “Company”), listed on the TSX Venture Exchange Inc. under the trading symbol “PEH”, announced today the following update on
the arbitration proceedings against China National Offshore Oil Corp (“CNOOC”) and CNOOC China Limited (“CCL”) (“CNOOC
Arbitration”).
As previously announced, Primeline commenced arbitration proceedings against CNOOC and CCL under the dispute
resolution provisions of Petroleum Contract 25/34 in accordance with the UNCITRAL Arbitration Rules 1976. Primeline filed the
formal Notice of Arbitration on June 6, 2016 and the tribunal (comprised of three arbitrators) was formed on August 30, 2016 with
the seat of arbitration agreed to be Singapore. Primeline has claimed in respect of CCL’s mismanagement as operator of the LS36-1
gas field, resulting in delay in the commencement of production of LS36-1 gas field from 2013 to 2014 leading to loss of revenue,
increased cost and the project falling below its design level; and in respect of CCL’s breach of good faith and wrongful conduct as
Primeline’s agent in dealing with Zhejiang Gas and managing the Gas Sales Contract for LS36-1; and against CNOOC as guarantor of
CCL, and CNOOC’s other obligations under the Petroleum Contract and affiliated agreements.
Primeline filed the Statement of Claim together with all supporting documents on April 25, 2017, in which
Primeline has claimed that CNOOC and CCL have committed multiple material breaches of the Petroleum Contract 25/34 which entitle it
to relief including termination of the contract and other related arrangements, which claim is to be determined by the arbitral
tribunal in its final award. Primeline believes CNOOC and CCL have a significant conflict of interest in relation to their
dealings with Zhejiang Gas (in that CNOOC has an ownership interest in Zhejiang Gas) which has contributed to the above breaches
contrary to the provisions of Petroleum Contract 25/34 and PRC law (including the principles of good faith).
In accordance with the procedure fixed by the tribunal, CNOOC and CCL filed their Statement of Defence
and Counterclaim on October 17, 2017 and the parties have just exchanged details of documents requested for disclosure. Primeline
is due to file its Response to the Statement of Defence and Counterclaim on or before March 26, 2018. The final hearing of the
arbitration is scheduled for mid-September 2018.
As part of their defence and counterclaim, CNOOC and CCL have put in a counterclaim against Primeline in the
order of RMB400 million, and served a notice purporting to terminate Petroleum Contract 25/34 with effect from 15 January
2018, based on claims that Primeline should not have served a termination notice in the arbitration, was not entitled to pursue
certain other claims in the arbitration and should pay disputed amounts of approximately RMB117 million.
Petroleum Contract 25/34 provides that the claimed termination of the contract by either party on grounds of
alleged unremedied material breach of contract must have been judged and determined by a final award of the arbitral tribunal
pursuant to the provisions set out in the contract. Therefore, the relief claimed by Primeline includes a final award to determine
and confirm Primeline’s right to terminate Petroleum Contract 25/34, and affiliated arrangements, and to order CNOOC and CCL to pay
Primeline in the order of RMB2.19 billion, which represents Primeline’s wasted expenditure in connection with the LS36-1 gas field,
plus costs. If such claim for termination is not upheld, Primeline’s alternative claim is for damages arising from each of CNOOC
and CCL’s breaches of Petroleum Contract 25/34 and related agreements on the basis that the contract, under which Primeline has a
49% interest in the LS36-1 gas field, continues in effect.
Primeline does not believe that CNOOC and CCL have any valid grounds on which to terminate the Petroleum
Contract and the amount claimed to support their counter termination notice is far from material considering the size of the
project (in the order of several RMB billions). Further, in any event, under the Petroleum Contract, any purported termination by
CNOOC and CCL must be determined by final award of the arbitral tribunal in the CNOOC Arbitration, after a merits hearing.
Primeline has pointed out this contractual requirement to CNOOC and CCL but it was informed by CNOOC and CCL that they
intended to terminate and cease to comply with Petroleum Contract 25/34 and related agreements effective on January 15, 2018,
without following the contractual mechanism for termination, (i.e. without the prior determination of the tribunal by final award
in the CNOOC Arbitration).
Primeline regards CNOOC and CCL’s purported termination as an act constituting a further breach of Petroleum
Contract 25/34.
Since CCL is the Operator and agent for sales of Production from LS36-1 gas field and collects and distributes
the revenue, such purported unilateral termination by CNOOC and CCL on 15 January 2018, if unrestrained, will give rise to
immediate and serious financial consequences for Primeline, including under the terms of the loan from the banking syndicate which
provided project finance for LS 36-1 to Primeline. In particular, it will give rise to the immediate occurrence of one or more
event(s) of default under the loan agreement, triggering acceleration of all amounts owed. Such acceleration would likely
result in Primeline’s insolvency and seizure of its assets.
Primeline has therefore requested the arbitral tribunal to set a hearing date at the earliest practicable
time and related procedural directions for an application on its behalf for urgent interim relief from the arbitral tribunal to
restrain CNOOC and CCL from giving effect to their purported termination by ceasing to comply further with the Petroleum Contract
on January 15, 2018. CNOOC and CCL have opposed Primeline’s request and indicated that they will also oppose its application
for interim relief in due course. CNOOC and CCL have also proposed certain alternative arrangements which are not, however,
workable or acceptable to Primeline. The arbitral tribunal’s response to Primeline’s request for a hearing date and related
procedural directions is awaited.
Such interim relief is sought in order to ensure that any purported termination by CNOOC and CCL cannot be
effected unilaterally in the manner they intend to do but must be subject to review and determination (confirmation or rejection)
by final award of the tribunal as part of the CNOOC Arbitration. Further announcement will be made to update the progress.
About Primeline Energy Holdings Inc.
Primeline is an exploration and production company focusing exclusively on China natural resources to become a major supplier of
gas and oil to the East China market. Primeline has a 100% Contractor’s interest in, and is the operator of, the petroleum contract
with CNOOC for Block 33/07 (4,397sq km) and a 49% interest in the producing LS36-1 gas field in Block 25/34, together with CNOOC
(51% interest and acting as Operator). Both blocks are in the East China Sea. LS36-1 has been in production since July 2014. Shares
of Primeline are listed for trading on the TSX Venture Exchange under the symbol PEH.
ON BEHALF OF PRIMELINE ENERGY HOLDINGS INC.
Signed “Ming Wang”
Chief Executive Officer
Contact:
PRIMELINE ENERGY HOLDINGS INC.
Dr. Ming Wang, CEO
PH: +44 207.499.8888
Fax: +44 207.499.2288
Toll Free: 1.877.818.0688
E-Mail: IR@pehi.com
FronTier Merchant Capital Group
Robin Cook
1411-1 King Street West
Toronto, ON M5H 1A1
PH: (416) 809-1738
FAX: (866) 749-0447
E-Mail: robin@frontiermcg.com
www.frontiermcg.com
Please visit the Company’s website at www.primelineenergy.com. Should you wish to receive Company news via email, please
email robin@frontiermcg.com and specify “Primeline Energy” in the subject line.
Forward-Looking Statements
Some of the statements in this news release contain forward-looking information, which involves inherent risk and
uncertainty affecting the business of Primeline. These statements relate to Primeline’s belief that it will be successful in
obtaining an injunction restraining CNOOC and CCL from giving effect to the purported termination of the Petroleum Contract 25/34
on January 15, 2018, that it will ultimately be successful in the CNOOC Arbitration, and that Primeline’s banking Syndicate will
not demand immediate repayment of all amounts owed under the project facility. Although these statements are based on assumptions
management believes to be reasonable, actual results may vary from those anticipated in such statements. Primeline may not obtain
the injunction it is seeking, and if not CNOOC and CCL’s termination of Petroleum Contract 25/34 as of January 15, 2008 will be
effective. If Primeline does obtain the injunction it is seeking, it may nevertheless ultimately be unsuccessful in the CNOOC
Arbitration. If it is successful, Primeline may not be able to enforce the award of the arbitral tribunal. In any of
these events, Primeline’s banking Syndicate may demand immediate repayment of all amounts owed under the project facility.
This would likely result in Primeline’s insolvency, and seizure of its assets. Exploration for oil and gas is subject to the
inherent risk that it will not result in a commercial discovery.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of
the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this.