Redevelopment plan to bring Kipushi’s Big Zinc Zone into
production in less than two years, with life-of-mine average annual production
rate of 225,000 tonnes of zinc and cash costs of US$0.48/lb of
zinc
Big Zinc Zone has estimated 10.2 million tonnes of Measured and Indicated Mineral
Resources grading 34.9% zinc
Successful restoration of production to establish Kipushi as the world’s highest-grade
major zinc mine
After-tax NPV of US$683 million and
35% IRR, based on long-term zinc price of
US$1.10/lb, with pre-production capital of US$337
million
Kipushi has after-tax NPV of US$1.2
billion and IRR of 51% at current zinc price of approximately
US$1.40/lb
Memorandum of understanding signed with leading mining contractor Byrnecut
Memorandum of understanding to rebuild railway spur line signed with
DRC national railway to facilitate exports of concentrate
KIPUSHI, Democratic Republic of Congo, Dec. 13, 2017 (GLOBE NEWSWIRE) -- Robert Friedland, Executive Chairman of Ivanhoe
Mines (TSX:IVN) (OTCQX:IVPAF), and Lars-Eric Johansson, Chief Executive Officer, today announced the positive
findings of an independent, pre-feasibility study (PFS) for the planned redevelopment of the
company’s historic, high-grade, Kipushi zinc-copper-silver-germanium mine.
The study anticipates annual production of an average of 381,000 tonnes of zinc concentrate over an
11-year initial mine life at a total cash cost of approximately US$0.48 per pound of
zinc.
The PFS focuses on the initial mining of Kipushi’s Big Zinc Zone, which has an
estimated 10.2 million tonnes of Measured and Indicated Mineral Resources grading 34.9% zinc. The planned return
to production would establish Kipushi as the world’s highest-grade major zinc mine. Its exceptional zinc grade is more than twice
as high as the Measured and Indicated Mineral Resources of the world’s next-highest-grade zinc project, according to Wood
Mackenzie, a leading, international industry research and consulting group (see Figure 2).
Independent research by Wood Mackenzie concludes that the Kipushi Project could rank among the
world’s largest zinc mines.
Figure 1: World’s 10 largest zinc mines, showing estimated annual zinc production and zinc head grades
(ranked by forecasted production by 2020).
http://www.globenewswire.com/NewsRoom/AttachmentNg/b39d5d90-c213-492f-b11f-a93c2eae6e77
Source: Wood Mackenzie
Note: Independent research by Wood Mackenzie concludes that at the forecast production and head grade, the Kipushi Project, once
in production, will rank among the world’s largest zinc mines. Wood Mackenzie compared the Kipushi Project’s life-of-mine average
annual zinc production and zinc head grade of 225,000 tonnes and 32%, respectively, against production and zinc head grade
forecasts for 2020.
Given the significant, very-high-grade zinc resource at Kipushi, which is rich in potential by-product credits including copper,
silver and germanium and the ongoing exploration campaign at Kipushi, Ivanhoe and the Gécamines technical team are continuing to
investigate additional downstream processing options.
“The pre-feasibility study is the latest validation that Kipushi has the resources to become one of the world’s largest
and lowest-cost zinc producers, plus the potential to also produce significant quantities of copper, silver and
germanium,” said Mr. Friedland.
“Discussions are continuing with potential strategic partners and lenders to support our continuing advance toward a new
era of production at Kipushi. We’ve made significant progress in upgrading the mine’s underground infrastructure
and now we have a much clearer path to a resumption of production from this incredibly rich orebody.”
Mr. Johansson said that a definitive feasibility study, to further refine and optimize the project’s
economics, is underway and is expected to be completed in the second half of 2018.
“Since acquiring our 68% interest in the Kipushi Project in 2011, our team has worked closely with our partner,
Gécamines, to move the project forward,” he added.
“During that time, we’ve seen zinc prices rally from less than US$1.00 per pound to
well over US$1.40. We’re confident that the long-term supply and demand fundamentals should
support a strong zinc price for a long time to come.”
The Kipushi Project is operated by Kipushi Corporation
(KICO), a joint venture between Ivanhoe Mines (68%)
and Gécamines (32%), the DRC’s state-owned mining
company.
Highlights of the PFS, based on a long-term zinc price of US$1.10/lb,
include:
- After-tax net present value (NPV) at an 8% real discount rate of
US$683 million.
- After-tax real internal rate of return (IRR) of 35.3%.
- After-tax project payback period of 2.2 years.
- Pre-production capital costs, including contingency, estimated at US$337 million.
- Existing surface and underground infrastructure allows for significantly lower capital costs than comparable
greenfield development projects.
- Life-of-mine average planned zinc concentrate production of 381,000 dry tonnes per annum, with a concentrate grade of
59% zinc, is expected to rank Kipushi, once in production, among the world’s largest zinc mines (Figure 1).
- Life-of-mine average cash cost of US$0.48/lb of zinc is expected to rank Kipushi,
once in production, in the bottom quartile of the cash cost curve for zinc producers globally (Figure 11).
The PFS was prepared by OreWin Pty. Ltd., MSA Group
(Pty.) Ltd., SRK Consulting, Murray & Roberts, Golder Associates and
MDM Engineering, a subsidiary of Amec Foster Wheeler. The PFS was
prepared in compliance with Canadian National Instrument 43-101 – Standards of Disclosure for Mineral Projects (NI
43-101).
Details of Mineral Resource Estimates
The Mineral Resource used in the PFS has an effective date of January 23, 2016, and was estimated using The Canadian Institute
of Mining, Metallurgy and Petroleum (CIM) Best Practice Guidelines and is reported in accordance with the 2014 CIM Definition
Standards established by the Canadian Institute of Mining, Metallurgy and Petroleum. The Mineral Resource is classified into the
Measured, Indicated and Inferred categories as shown in Table 1 for the predominantly zinc-rich bodies and in Table 2 for the
predominantly copper-rich bodies.
The Mineral Resource estimate was based on the results of 84 holes drilled at Kipushi by Ivanhoe Mines and an additional 107
historical holes drilled by Gécamines. Ivanhoe completed its drilling program for the Mineral Resource estimate in October 2015.
Mineral Resource estimates were completed below the 1,150-metre-level on the Big Zinc Zone, Southern Zinc Zone, Fault Zone and
Série Récurrente Zone. The Mineral Resources were categorized either as zinc-rich resources or copper-rich resources, depending on
the most abundant metal. The Big Zinc and Southern Zinc zones have been tabulated using zinc cut-offs and are shown in Table 1; the
Fault Zone, the Fault Zone Splay and Série Récurrente Zone have been tabulated using copper cut-offs and are shown in Table 2. For
the zinc-rich zones, the Mineral Resource is reported at a base-case cut-off grade of 7.0% zinc and the copper-rich zones at a
base-case cut-off grade of 1.5% copper.
Table 1: Kipushi zinc-rich Mineral Resource at 7% zinc cut-off grade, 23 January 2016
Zone |
Category |
Tonnes
(millions) |
Zn
% |
Cu
% |
Pb
% |
Ag
g/t |
Co
ppm |
Ge
g/t |
Big Zinc |
Measured |
3.59 |
38.39 |
0.67 |
0.36 |
18 |
17 |
54 |
Indicated |
6.60 |
32.99 |
0.63 |
1.29 |
20 |
14 |
50 |
Inferred |
0.98 |
36.96 |
0.79 |
0.14 |
7 |
16 |
62 |
Southern Zinc |
Indicated |
0.00 |
- |
- |
- |
- |
- |
- |
Inferred |
0.89 |
18.70 |
1.61 |
1.70 |
13 |
15 |
43 |
Total |
Measured |
3.59 |
38.39 |
0.67 |
0.36 |
18 |
17 |
54 |
Indicated |
6.60 |
32.99 |
0.63 |
1.29 |
20 |
14 |
50 |
Measured &
Indicated |
10.18 |
34.89 |
0.65 |
0.96 |
19 |
15 |
51 |
Inferred |
1.87 |
28.24 |
1.18 |
0.88 |
10 |
15 |
53 |
Contained metal quantities |
Zone |
Category |
Tonnes
(millions) |
Zn
(million lbs) |
Cu
(million lbs) |
Pb
(million lbs) |
Ag
(million oz) |
Co
(million
lbs) |
Ge
(million
oz) |
Big Zinc |
Measured |
3.59 |
3,035.8 |
53.1 |
28.7 |
2.08 |
0.13 |
6.18 |
Indicated |
6.60 |
4,797.4 |
91.9 |
187.7 |
4.15 |
0.20 |
10.54 |
Inferred |
0.98 |
797.2 |
17.1 |
3.0 |
0.23 |
0.03 |
1.96 |
Southern Zinc |
Indicated |
0.00 |
0.0 |
0.0 |
0.0 |
0.00 |
0.00 |
0.00 |
Inferred |
0.89 |
368.6 |
31.8 |
33.5 |
0.38 |
0.03 |
1.23 |
Total |
Measured |
3.59 |
3,035.8 |
53.1 |
28.7 |
2.08 |
0.13 |
6.18 |
Indicated |
6.60 |
4,797.4 |
91.9 |
187.7 |
4.15 |
0.20 |
10.54 |
Measured &
Indicated |
10.18 |
7,833.3 |
144.9 |
216.4 |
6.22 |
0.33 |
16.71 |
Inferred |
1.87 |
1,168.7 |
49.6 |
36.8 |
0.61 |
0.06 |
3.21 |
Notes:
- All tabulated data has been rounded and as a result minor computational errors may occur.
- Mineral Resources that are not Mineral Reserves have no demonstrated economic viability.
- The Mineral Resource is reported as the total in-situ Mineral Resource and on a 100% project basis.
- Metal quantities are reported in multiples of Troy Ounces or Avoirdupois Pounds.
- The cut-off grade calculation was based on the following assumptions: zinc price of US$1.02 /lb, mining cost of US$50 /tonne,
processing cost of US$10 /tonne, G&A and holding cost of US$10 /tonne, transport of 55% Zn concentrate at US$375 /tonne, 90%
zinc recovery and 85% payable zinc.
Table 2: Kipushi copper-rich Mineral Resource at 1.5% copper cut-off grade, 23 January 2016
Zone |
Category |
Tonnes
(millions) |
Cu
% |
Zn
% |
Pb
% |
Ag
g/t |
Co
ppm |
Ge
g/t |
Fault Zone |
Measured |
0.14 |
2.78 |
1.25 |
0.05 |
19 |
107 |
20 |
Indicated |
1.01 |
4.17 |
2.64 |
0.09 |
23 |
216 |
20 |
Inferred |
0.94 |
2.94 |
5.81 |
0.18 |
22 |
112 |
26 |
Série Récurrenté |
Indicated |
0.48 |
4.01 |
3.82 |
0.02 |
21 |
56 |
6 |
Inferred |
0.34 |
2.57 |
1.02 |
0.06 |
8 |
29 |
1 |
Fault Zone
Splay |
Inferred |
0.35 |
4.99 |
15.81 |
0.005 |
20 |
127 |
81 |
Total |
Measured |
0.14 |
2.78 |
1.25 |
0.05 |
19 |
107 |
20 |
Indicated |
1.49 |
4.12 |
3.02 |
0.07 |
22 |
165 |
15 |
Measured &
Indicated |
1.63 |
4.01 |
2.87 |
0.06 |
22 |
160 |
16 |
Inferred |
1.64 |
3.30 |
6.97 |
0.12 |
19 |
98 |
33 |
Contained metal quantities |
Zone |
Category |
Tonnes
(millions) |
Cu lbs
(millions) |
Zn lbs
(millions) |
Pb lbs
(millions) |
Ag oz
(millions) |
Co lbs
(millions) |
Ge oz
(millions) |
Fault Zone |
Measured |
0.14 |
8.5 |
3.8 |
0.2 |
0.09 |
0.03 |
0.09 |
Indicated |
1.01 |
93.2 |
59.1 |
1.9 |
0.75 |
0.48 |
0.64 |
Inferred |
0.94 |
61.1 |
120.9 |
3.8 |
0.68 |
0.23 |
0.79 |
Série Récurrenté |
Indicated |
0.48 |
42.4 |
40.5 |
0.2 |
0.32 |
0.06 |
0.09 |
Inferred |
0.34 |
19.4 |
7.7 |
0.4 |
0.09 |
0.02 |
0.01 |
Fault Zone
Splay |
Inferred |
0.35 |
38.9 |
123.3 |
0.0 |
0.23 |
0.10 |
0.92 |
Total |
Measured |
0.14 |
8.5 |
3.8 |
0.2 |
0.09 |
0.03 |
0.09 |
Indicated |
1.49 |
135.7 |
99.6 |
2.1 |
1.08 |
0.54 |
0.73 |
Measured &
Indicated |
1.63 |
144.1 |
103.4 |
2.3 |
1.16 |
0.58 |
0.82 |
Inferred |
1.64 |
119.4 |
251.8 |
4.3 |
1.00 |
0.35 |
1.73 |
Notes:
- All tabulated data has been rounded and as a result minor computational errors may occur.
- Mineral Resources that are not Mineral Reserves have no demonstrated economic viability.
- The Mineral Resource is reported as the total in-situ Mineral Resource and on a 100% project basis.
- Metal quantities are reported in multiples of Troy Ounces or Avoirdupois Pounds.
- The cut-off grade calculation was based on the following assumptions: copper price of US$2.97 /lb, mining cost of
US$50/tonne, processing cost of US$10/tonne, G&A and holding cost of US$10/tonne, 90% copper recovery and 96% payable
copper.
Exploration drilling conducted by Ivanhoe Mines in 2015 successfully confirmed that both the Big Zinc Zone and Fault Zone remain
open at depth and to the south. Additional high-grade copper-zinc-germanium mineralization also was discovered in the Fault Zone
and in the Fault Zone Splay in the immediate footwall of the Fault Zone.
Figure 2: World’s top 20 zinc projects, by contained zinc.
http://www.globenewswire.com/NewsRoom/AttachmentNg/9fafa5c8-d81f-47f6-9ac1-1c1f495f1db0
Source: Wood Mackenzie.
Note: All tonnes and zinc grades of the above-mentioned projects (except for Kipushi) are based on public disclosure and have
been compiled by Wood Mackenzie.
Initial Mineral Reserve estimate for the Kipushi 2017 PFS
The Kipushi 2017 PFS Mineral Reserve has been estimated by Qualified Person Bernie Peters, Technical Director –
Mining, OreWin Pty. Ltd., using the 2014 CIM Definition Standards. The Mineral Reserve is based on the January 2016 Mineral
Resource. The effective date of the Mineral Reserve statement is December 5, 2017.
Table 3. Kipushi 2017 PFS Mineral Reserve Statement
Category |
Tonnage
(Mt) |
Zinc
(%) |
Zinc
(Contained kt) |
Proven Mineral
Reserve |
3.10 |
35.41 |
1,098 |
Probable
Mineral Reserve |
5.48 |
30.29 |
1,660 |
Total
Mineral Reserve |
8.58 |
32.14 |
2,758 |
Notes:
- Effective date of the Mineral Reserves is 12 December 2017.
- Net Smelter Return (NSR) is used to define the Mineral Reserve cut-offs, therefore cut-off is denominated in US$/t. By
definition the cut-off is the point at which the costs are equal to the NSR. An elevated cut-off grade of US$135/t NSR (14.03%
Zn) was used to define the mining shapes. The marginal cut-off grade has been calculated to be US$51/t NSR (3.43% Zn).
- Mineral Reserves are based on a zinc price of US$1.01/b Zn and a treatment charge of US$200/t concentrate.
- Economic analysis to demonstrate the Kipushi 2017 PFS Mineral Reserve used a zinc price of US$1.10/lb Zn and a treatment
charge of US$170/t concentrate.
- Only Measured Mineral Resources were used to report Proven Mineral Reserves and only Indicated Mineral Resources were used to
report Probable Mineral Reserves.
- Mineral Reserves reported above were not additive to the Mineral Resources and are quoted on a 100% project basis.
- Totals may not match due to rounding.
Upgrading of existing underground infrastructure nearing completion
KICO has completed the refurbishment of a significant amount of underground infrastructure at the Kipushi Project, including a
series of vertical mine shafts, with associated head frames, to various depths, as well as underground mine excavations. A series
of crosscuts and ventilation infrastructure still are in working condition. The underground infrastructure also includes a series
of pumps to manage the influx of water into the mine. A schematic layout of the existing development is shown in Figure 3.
The main production shaft for the Kipushi Mine, Shaft 5 (labelled as P5 in Figure 3), is eight metres in diameter and 1,240
metres deep, and has been upgraded and re-commissioned. The main personnel and material winder has been upgraded and modernized to
meet global industry standards and safety criteria. The Shaft 5 rock-hoisting winder, which had an annual hoisting capacity of 1.8
million tonnes, is being upgraded and is expected to be fully operational early next year.
Underground upgrading work is continuing on the crusher and the rock load-out facilities at the bottom of Shaft 5 and the main
haulage way on the 1,150-metre level, between the Big Zinc access decline and Shaft 5. This work is expected to be completed before
the end of the first quarter of 2018.
Figure 3: Schematic section of Kipushi Mine
http://www.globenewswire.com/NewsRoom/AttachmentNg/01bb4cc8-07bf-4b59-85ad-72e2273c0906
MOU signed with leading mining contractor Byrnecut
Earlier this month, KICO signed a memorandum of understanding (MOU) with Byrnecut Offshore Proprietary Limited (Byrnecut), of
Perth, Australia. The MOU relates to the potential engagement of Byrnecut to provide underground mining services at Kipushi,
including cost estimation, contractor management, operational readiness and operational services.
The planned primary mining method for the Big Zinc Deposit in the PFS is sublevel long-hole, open stoping, with cemented
backfill. The crown pillars are expected to be mined once adjacent stopes are backfilled using a pillar-retreat mining method. The
Big Zinc Deposit is expected to be accessed via the existing decline and without any significant new development. The main levels
are planned to be at 60-metre vertical intervals, with sublevels at 30-metre intervals.
Figure 4: Planned and existing development at Kipushi
http://www.globenewswire.com/NewsRoom/AttachmentNg/ba9622fb-00c5-49e2-adae-f7a1413ba23b
Optimized zinc processing methodology for the PFS
Based on additional metallurgical test work and trade-off studies, Ivanhoe revised the planned process-plant design
for the PFS. The optimized plant utilizes dense media separation (DMS), followed by milling and a flotation recovery plant. DMS is
a simple density-concentration technique that preliminary test work has shown yields positive results for the Kipushi material,
which has a sufficient density differential between the waste rock (predominantly dolomite) and mineralization (sphalerite). The
addition of milling and a flotation recovery plant resulted in an overall recovery of 89.6%, producing a consistent high-grade
concentrate of 58.9% contained zinc. The improved concentrate grade results in lower transportation costs as compared to the
Kipushi 2016 PEA.
Infrastructure
The Kipushi Project includes surface mining and processing infrastructure, concentrator, offices, workshops and a connection to
the national power grid. Electricity is supplied by the DRC’s state power company, Société Nationale d’Electricité (SNEL), from two
transmission lines from Lubumbashi. Pylons are in place for a third line.
The surface infrastructure is owned by Gécamines. KICO has entered into an agreement to use the surface rights on the Kipushi
Project to the extent required for its operations.
An abundant supply of process water from the underground dewatering operations is expected to provide adequate water for
processing and mining operations.
The overall proposed site layout is shown in Figure 5.
Figure 5: Kipushi Project’s proposed site layout
http://www.globenewswire.com/NewsRoom/AttachmentNg/ee96d88d-b0e1-4b46-872e-cceaeb7de39f
Concentrate exports via newly rebuilt spur line to DRC
national railway
On October 30, 2017, Ivanhoe Mines and the DRC’s state-owned railway company, Société Nationale des Chemins de Fer du Congo
(SNCC), signed a MOU to rebuild 34 kilometres of track to connect the Kipushi Mine with the DRC national railway at Munama, south
of the mining capital of Lubumbashi.
Under the terms of the MOU, Ivanhoe has appointed R&H Rail (Pty) Ltd. to conduct a front-end engineering design study to
assess the scope and cost of rebuilding the spur line from the Kipushi Mine to the main Lubumbashi-Sakania railway at Munama. The
study has begun and construction on the Kipushi-Munama spur line could start in late 2018. Ivanhoe will finance the estimated US$32
million (plus contingency) capital cost for the rebuilding, which is included within the overall Kipushi 2017 PFS capital cost.
The proposed export route is to utilize the SNCC network from Kipushi to Ndola, connecting to the North-South Rail Corridor from
Ndola to Durban. The North-South Rail Corridor to Durban via Zimbabwe is fully operational and has significant excess capacity.
Key projections from the Kipushi 2017 PFS
Future proposed mine production has been scheduled to maximize the mine output and meet the annual nominal capacity of 800,000
tonnes of the DMS and mill-flotation plant. The mining production forecasts are shown in Table 4. Mine, process and concentrate
production are shown in figures 6 to 8.
Table 4: Mining production statistics
Description |
Unit |
Total LOM |
5-Year
Average |
LOM
Average |
Zinc feed – tonnes processed |
Quantity Zinc Tonnes Treated |
kt |
8,581 |
777 |
780 |
Zinc Feed Grade |
% |
32.14 |
30.20 |
32.14 |
Zinc Recovery |
% |
89.61 |
88.76 |
89.61 |
Zinc Concentrate Produced |
kt (dry) |
4,196 |
354 |
381 |
Zinc Concentrate Grade |
% |
58.91 |
58.51 |
58.91 |
Contained Zinc in Concentrate |
kt |
2,472 |
207 |
225 |
Figure 6: Estimated tonnes mined and zinc feed grade
http://www.globenewswire.com/NewsRoom/AttachmentNg/2d83dc7b-155d-492c-88e4-966e3de3c84e
Figure 7: Estimated tonnes processed and zinc feed grade
http://www.globenewswire.com/NewsRoom/AttachmentNg/17e462a2-b156-4f88-bdc6-7439631bb09c
Figure 8: Concentrate and metal production
http://www.globenewswire.com/NewsRoom/AttachmentNg/0cf2cf4d-4cae-4adc-a6b0-caa0e4c314e7
Economic analysis
The estimates of cash flows have been prepared on a real basis as at January 1, 2018, and a mid-year discounting is used to
calculate the NPV.
The projected financial results for undiscounted and discounted cash flows, at a range of discount rates, IRR and payback are
shown in Table 5. The key economic assumptions for the discounted cash flow analyses are shown in Table 6. The results of NPV
sensitivity analysis to a range of zinc prices and zinc treatment charges are shown in Table 7. A comparison of the Kipushi 2017
PFS key results to the Kipushi 2016 PEA is shown in Table 8. A chart of the cumulative cash flow is shown in Figure 9.
Table 5: Financial results
Description |
Discount Rate |
Before Taxation |
After Taxation |
Net Present Value (US$M) |
Undiscounted |
1,944 |
|
1,435 |
|
|
5.0 |
% |
1,239 |
|
900 |
|
|
8.0 |
% |
953 |
|
683 |
|
|
10.0 |
% |
743 |
|
517 |
|
|
12.0 |
% |
628 |
|
431 |
|
Internal Rate of Return |
– |
|
41.7 |
% |
35.3 |
% |
Project
Payback Period (Years) |
– |
|
1.9 |
|
2.2 |
|
Table 6: Kipushi 2017 PFS zinc price and treatment
charge
Parameter |
Unit |
Economic Analysis Assumption |
Zinc
Price |
US$/lb |
1.10 |
Zinc Treatment
Charge |
US$/t
concentrate |
170 |
Table 7: After-tax NPV8% and
IRR sensitivity to zinc prices and treatment charges
Zinc Treatment
Charge (US$/t) |
Zinc Price (US$/lb) |
0.90 |
|
1.00 |
|
1.10 |
|
1.20 |
|
1.40 |
|
1.50 |
|
1.70 |
|
2.00 |
|
50 |
524 |
|
698 |
|
870 |
|
1,043 |
|
1,385 |
|
1,557 |
|
1,899 |
|
2,412 |
|
29.8 |
% |
35.8 |
% |
41.3 |
% |
46.5 |
% |
56.0 |
% |
60.5 |
% |
69.0 |
% |
80.5 |
% |
100 |
444 |
|
619 |
|
792 |
|
965 |
|
1,308 |
|
1,479 |
|
1,822 |
|
2,334 |
|
26.9 |
% |
33.2 |
% |
38.8 |
% |
44.2 |
% |
53.9 |
% |
58.4 |
% |
67.2 |
% |
78.8 |
% |
150 |
364 |
|
540 |
|
714 |
|
886 |
|
1,230 |
|
1,401 |
|
1,744 |
|
2,257 |
|
23.8 |
% |
30.4 |
% |
36.3 |
% |
41.8 |
% |
51.7 |
% |
56.4 |
% |
65.2 |
% |
77.1 |
% |
170 |
331 |
|
508 |
|
683 |
|
855 |
|
1,199 |
|
1,370 |
|
1,713 |
|
2,226 |
|
22.5 |
% |
29.2 |
% |
35.3 |
% |
40.8 |
% |
50.9 |
% |
55.5 |
% |
64.4 |
% |
76.4 |
% |
200 |
282 |
|
461 |
|
635 |
|
808 |
|
1,152 |
|
1,324 |
|
1,666 |
|
2,179 |
|
20.5 |
% |
27.4 |
% |
33.7 |
% |
39.3 |
% |
49.6 |
% |
54.3 |
% |
63.2 |
% |
75.4 |
% |
250 |
200 |
|
380 |
|
556 |
|
730 |
|
1,074 |
|
1,246 |
|
1,589 |
|
2,102 |
|
17.0 |
% |
24.4 |
% |
30.9 |
% |
36.8 |
% |
47.3 |
% |
52.1 |
% |
61.2 |
% |
73.6 |
% |
Table 8: Comparison of results from Kipushi 2017 PFS to Kipushi 2016
PEA
Item |
Unit |
2016 PEA(1) |
2017 PFS(2) |
LOM Average Zinc Ore
Processed |
|
|
|
Zinc Ore Mined |
kt |
939 |
780 |
Zn Ore Head Grade |
% |
32.15 |
32.14 |
Zinc Concentrate
Recovery |
% |
92.94 |
89.61 |
Zinc Concentrate
Produced |
kt (dry) |
530 |
381 |
Zinc Concentrate Grade |
% |
53.00 |
58.91 |
LOM Average Metal
Produced |
|
|
|
Zinc Produced |
Mlb |
619 |
495 |
Zinc Produced |
kt |
281 |
225 |
Key
Financial Results |
|
|
|
Pre-Production
Capital |
US$M |
409 |
337 |
Mine Site Cash Cost |
US$/lb Payable Zn |
0.12 |
0.14 |
Realization |
US$/lb Payable Zn |
0.44 |
0.35 |
Total Cash Costs After
Credits |
US$/lb Payable Zn |
0.54 |
0.48 |
Site Operating
Costs |
US$/t milled |
74.77 |
87.77 |
After Tax
NPV8% |
US$M |
533 |
683 |
After Tax IRR |
% |
30.9 |
35.3 |
Project Payback Period |
Years |
2.18 |
2.24 |
1. Based on long-term zinc price of US$1.01/lb and zinc treatment charge of US$190/t concentrate.
2. Based on long-term zinc price of US$1.10/lb and zinc treatment charge of US$170/t concentrate.
Figure 9: Cumulative cash flow
http://www.globenewswire.com/NewsRoom/AttachmentNg/58c615c6-2806-43f3-9067-c9a40276ee5e
The total capital cost estimates for Kipushi are shown in Table 9. Kipushi’s estimated low capital intensity
relative to comparable “probable” and “base case” zinc projects identified by Wood Mackenzie is highlighted in Figure 10.
Table 9: Estimated capital costs
Description |
Pre-Production
(US$M) |
Sustaining
(US$M) |
Total
(US$M) |
Mining: |
UG Mine Refurbishment |
17 |
– |
17 |
Underground Mining |
57 |
128 |
185 |
Capitalized Operating Costs |
37 |
– |
37 |
Subtotal |
112 |
128 |
239 |
Process & Infrastructure: |
Process & Infrastructure |
78 |
7 |
84 |
Railway |
32 |
– |
32 |
Capitalized Operating Costs |
7 |
– |
7 |
Subtotal |
116 |
7 |
123 |
Closure: |
Closure |
– |
20 |
20 |
Subtotal |
– |
20 |
20 |
Indirects: |
EPCM |
12 |
– |
12 |
Capitalized G&A |
11 |
– |
11 |
Subtotal |
22 |
– |
22 |
Others: |
Owners Cost |
49 |
24 |
73 |
Capital Cost Before Contingency |
300 |
178 |
478 |
Contingency |
37 |
– |
37 |
Capital Cost After Contingency |
337 |
178 |
515 |
Figure 10: Capital intensity for zinc projects
http://www.globenewswire.com/NewsRoom/AttachmentNg/1177b853-fdc2-44bf-8e9e-1fc6c96c24f7
Source: Wood Mackenzie, December 2017.
Note: All comparable “probable” and “base case” projects as identified by Wood Mackenzie. Source: Wood Mackenzie (based on
public disclosure and information gathered in the process of routine research. The Kipushi 2017 PFS has not been reviewed by Wood
Mackenzie).
Kipushi’s estimated revenues and operating costs are presented in Table 10, along with the projected net sales revenue value
attributable to each key period of operation. Kipushi’s estimated cash costs are presented in Table 11. Based on data from Wood
Mackenzie, life-of-mine average cash cost of US$0.48/lb of zinc is expected to rank Kipushi, once in production, in the bottom
quartile of the 2020 cash cost curve for zinc producers globally (see Figure 11).
Table 10: Estimated operating costs and revenues
Description |
Total
(US$M) |
5-Year Average |
LOM Average |
(US$/t Milled) |
Revenue: |
Gross
Sales Revenue |
5,095 |
550 |
594 |
Less: Realization Costs |
Transport Costs |
972 |
103 |
113 |
Treatment & Refining Charges |
713 |
77 |
83 |
Royalties |
197 |
21 |
23 |
Total
Realization Costs |
1,883 |
202 |
219 |
Net
Sales Revenue |
3,212 |
348 |
374 |
Less: Site Operating Costs |
Mining |
415 |
52 |
48 |
Processing & TSF |
194 |
23 |
23 |
General & Administration |
144 |
17 |
17 |
Total |
753 |
93 |
88 |
Operating Margin |
2,459 |
255 |
287 |
Operating Margin (%) |
48.3 |
46.4 |
48.3 |
Table 11: Estimated cash costs
Description |
5-Year Average |
LOM Average |
(US$/lb Payable Zn) |
Mine Site Cash
Cost |
0.16 |
0.14 |
Realization |
0.34 |
0.35 |
Total
Cash Costs |
0.50 |
0.48 |
Figure 11: 2020 pro-rata C1 cash costs
http://www.globenewswire.com/NewsRoom/AttachmentNg/ad143e94-1fde-41e6-bf32-4447bc559dd1
Source: Wood Mackenzie, December 2017 (based on public disclosure and information gathered in the process of routine research.
The Kipushi 2017 PFS has not been reviewed by Wood Mackenzie).
Note: Represents C1 cash costs which reflect the direct cash costs of producing paid metal incorporating mining, processing and
offsite realization costs, having made appropriate allowance for the co-product revenue streams.
Figure 12: New idlers and rollers being installed on the ore conveyor belt as part of Kipushi’s
upgrading.
http://www.globenewswire.com/NewsRoom/AttachmentNg/f8061e38-af09-456f-808d-89b26e7771c9
Figure 13: Shaft 5 main pumping station at the 1,200-metre level.
http://www.globenewswire.com/NewsRoom/AttachmentNg/69ff0b04-e55b-42f8-bdb9-d39de61b97d3
Figure 14: High-grade copper drill core from Kipushi’s Série Récurrente Zone from hole KPU140 in the recently completed
underground drilling program.
http://www.globenewswire.com/NewsRoom/AttachmentNg/7ba5c512-4665-4ade-862e-901d2bd244a1
Qualified Persons, Quality Control and Assurance
The following companies have undertaken work in preparation of the Kipushi 2017 PFS:
- OreWin – Overall report preparation, mining, Mineral Reserve estimation and economic analysis.
- MSA Group – Resource and geology.
- SRK Consulting – Mine geotechnical recommendations.
- MDM Engineering – Plant and surface infrastructure.
- Murray & Roberts – Underground mining infrastructure.
- Golder Associates – Environmental and hydrogeology.
- Grindrod Rail Consultancy Services – Railway and logistics.
The independent Qualified Persons responsible for preparing the Kipushi 2017 PFS, on which the technical report will be based,
are Bernard Peters (OreWin); William Joughin (SRK Consulting); John Edwards (MDM Engineering); and Michael Robertson and Jeremy
Witley (MSA Group). Each Qualified Person has reviewed and approved the information in this news release relevant to the portion of
the Kipushi 2017 PFS for which they are responsible.
Other scientific and technical information in this news release has been reviewed and approved by Stephen Torr, P.Geo., Ivanhoe
Mines’ Vice President, Project Geology and Evaluation, a Qualified Person under the terms of NI 43-101. Mr. Torr is not independent
of Ivanhoe Mines. Mr. Torr has verified the technical data disclosed in this news release not related to the current Mineral
Resource and Mineral Reserve estimates disclosed herein.
Ivanhoe Mines maintains a comprehensive chain of custody and QA-QC program on assays from its Kipushi Project. Half-sawn core
was processed either at its preparation laboratory in Kamoa, DRC, or its exploration preparation laboratory in Kolwezi, DRC.
Prepared samples then were shipped to Bureau Veritas Minerals (BVM) Laboratories in Australia for external assay. Industry-standard
certified reference materials and blanks were inserted into the sample stream prior to dispatch to BVM. Ivanhoe Mines’ QA-QC
program has been set up in consultation with MSA Group (Pty.) Ltd., of Johannesburg.
Ivanhoe has previously filed an independent NI 43-101 Technical Report for the Kipushi Project, titled “Kipushi Zn-Cu Project,
Kipushi 2016 Preliminary Economic Assessment,” dated May 2016, which is available under the company’s SEDAR profile
at www.sedar.com and on the company’s website at www.ivanhoemines.com. The technical report
includes relevant information regarding the effective dates and the assumptions, parameters and methods of the 2016 mineral
resource estimates on the Kipushi Project cited in this news release, as well as information regarding data verification,
exploration procedures, sample preparation, analysis and security.
Ivanhoe Mines will be filing a new NI 43-101 Technical Report for the Kipushi 2017 PFS disclosed herein within 45 days of this
news release.
Wood Mackenzie provided data based on public disclosure of comparable projects for the compilation of certain figures used in
this news release; however, Wood Mackenzie did not review the Kipushi 2017 PFS.
About Ivanhoe Mines
Ivanhoe Mines is advancing its three principal projects in southern Africa: Mine development at the Platreef
platinum-palladium-gold-nickel-copper discovery on the Northern Limb of South Africa’s Bushveld Complex; mine development and
exploration at the Kamoa-Kakula copper discoveries on the Central African Copperbelt in the DRC; and upgrading at
the historic, high-grade Kipushi zinc-copper-lead-germanium mine, also on the DRC’s Copperbelt. For details, visit
www.ivanhoemines.com.
FORWARD-LOOKING STATEMENTS
Certain statements in this news release constitute “forward-looking statements” or “forward-looking information” within the
meaning of applicable securities laws. Such statements involve known and unknown risks, uncertainties and other factors, which may
cause actual results, performance or achievements of the company, the Kipushi Project, or industry results, to be materially
different from any future results, performance or achievements expressed or implied by such forward-looking statements or
information. Such statements can be identified by the use of words such as “may”, “would”, “could”, “will”, “intend”, “expect”,
“believe”, “plan”, “anticipate”, “estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state that
certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. These statements
reflect the company’s current expectations regarding future events, performance and results, and speak only as of the date of this
news release.
All of the results of the Kipushi 2017 PFS represent forward-looking information and statements. Statements in this news release
that constitute forward-looking statements or information include, but are not limited to: (1) statements regarding the
redevelopment plan to bring Kipushi’s Big Zinc Zone into production in less than two years; (2) statements regarding successful
restoration of production would establish Kipushi as the world’s highest-grade major zinc mine; (3) statements regarding the
Kipushi Project having an after-tax NPV of US$683 million and an IRR of 35.3%; (4) statements regarding Kipushi has an after-tax
NPV of US$1.2 billion and IRR of 51% at the current zinc price of approximately US$1.40/lb; (5) statements regarding pre-production
capital estimated at US$337 million; (6) statements regarding future mine production including that mine production is expected to
be at a steady-state annual mining rate of 800,000 tonnes; (7) statements regarding annual production of an average of 381,000
tonnes of zinc concentrate over an 11-year initial mine life at a total cash cost of approximately US$0.48 per pound of zinc; (8)
statements regarding independent research by Wood Mackenzie concludes that the Kipushi Project could rank among the world’s largest
zinc mines; (9) statements regarding that Kipushi has the resources to become one of the world’s largest and lowest-cost zinc
producers, plus the potential to also produce significant quantities of copper, silver and germanium; (10) statements regarding
that the planned life-of-mine average annual zinc production is 225,000 tonnes and zinc head grade is 32%; (11) statements
regarding that the project life-of-mine average cash cost of US$0.48/lb of zinc is expected to rank Kipushi, once in production, in
the bottom quartile of the cash cost curve for zinc producers globally; (12) statements regarding the work to upgrade the rock
load-out facilities at the bottom of Shaft 5 is expected to be completed before the end of the first quarter of 2018 and that the
Shaft 5 rock-hoisting winder is expected to be fully operational early next year; (13) statements regarding the proposed rail
export route for zinc concentrate to the port of Durban, South Africa; (14) statements regarding construction on the Kipushi-Munama
spur rail line could start in late 2018; and (15) statements regarding expected methods of mining and processing.
The forward-looking information and statements also includes metal price assumptions, cash flow forecasts, projected capital and
operating costs, metal recoveries, mine life and production rates, and other assumptions used in the Kipushi 2017 PFS. Readers are
cautioned that actual results may vary from those presented. The factors and assumptions used to develop the forward-looking
information, and the risks that could cause the actual results to differ materially will be presented in the body of the Technical
Report that will be filed on SEDAR at www.sedar.com and Ivanhoe Mines’ website at www.ivanhoemines.com within 45 days of this news
release.
All such forward-looking information and statements are based on certain assumptions and analyses made by Ivanhoe Mines’
management in light of their experience and perception of historical trends, current conditions and expected future developments,
as well as other factors management believe are appropriate in the circumstances. These statements, however, are subject to a
variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those
projected in the forward-looking information or statements including, but not limited to, unexpected changes in laws, rules or
regulations, or their enforcement by applicable authorities; the failure of parties to contracts to perform as agreed; social or
labour unrest; changes in commodity prices; unexpected failure or inadequacy of infrastructure, or delays in the refurbishment or
development of infrastructure, and the failure of exploration programs or other studies to deliver anticipated results or results
that would justify and support continued studies, development or operations. Other important factors that could cause actual
results to differ from these forward-looking statements also include those described under the heading "Risk Factors" in the
company's most recently filed MD&A as well as in the most recent Annual Information Form filed by Ivanhoe Mines.
Readers are cautioned not to place undue reliance on forward-looking information or statements.
This news release also contains references to estimates of Mineral Resources and Mineral Reserves. The estimation of Mineral
Resources is inherently uncertain and involves subjective judgments about many relevant factors. Mineral Resources that are not
Mineral Reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and
quality of available data, and of the assumptions made and judgments used in engineering and geological interpretation, which may
prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that may
ultimately prove to be inaccurate. Mineral Resource and Mineral Reserve estimates may have to be re-estimated based on, among other
things: (i) fluctuations in zinc or other mineral prices; (ii) results of drilling; (iii) results of metallurgical testing and
other studies; (iv) changes to proposed mining operations, including dilution; (v) the evaluation of mine plans subsequent to the
date of any estimates; and (vi) the possible failure to receive required permits, approvals and licences.
Although the forward-looking statements contained in this release are based upon what management of the company believes are
reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking
statements. These forward-looking statements are made as of the date of this release and are expressly qualified in their entirety
by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise
the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this
release.
Information contacts Investors Bill Trenaman +1.604.331.9834 Media North America: Bob Williamson +1.604.512.4856 South Africa: Jeremy Michaels +27.82.939.4812 Website www.ivanhoemines.com