TORONTO, Feb. 15, 2018 (GLOBE NEWSWIRE) -- Emerita Resources Corp. (“Emerita” or the “Company”) (TSX
VENTURE:EMO) has commenced its exploration program at the Salobro zinc project in Brazil (the “Salobro Project”) and it has decided
to fast track the Salobro Project in order to reach a development and construction decision. The Company has recently
completed an internal scoping study, including a conceptual mine plan, based on the existing drill hole data base. This preliminary
development plan will be used to guide exploration and suggests that an opportunity exists to meaningfully advance the timeline to
reach a development decision on the Salobro Project on an accelerated time line. The Company’s work to date also confirms
that the mineralization at the Salobro Project is open for expansion up dip, along strike and down dip.
The following are the Salobro Project key completed and upcoming milestones:
- Internal Scoping Study - Preliminary engineering and conceptual mining plan – completed
- Completion of the acquisition of the Salobro Project – Expected to be completed by the end of March 2018
- File NI 43-101 technical report – Expected to be completed by the end of March 2018
- Announce Updated NI 43-101 Resource: Expected to be completed by end of Q2 2018. The resampling of existing drill core is in
progress to allow for QA/QC and conversion of the historical resource to a NI 43-101 resource
- Commence exploration drilling: Diamond drilling expected to commence the first week of March 2018
- NI 43-101 Preliminary Economic Assessment - Expected to complete and announce by the end of Q3 2018
- Begin permitting process - Expected to obtain the terms of reference from the state environmental agency to commence baseline
studies in Q3 2018 for the Environmental Impact Assessment /RIMA study
- Prefeasibility study – Expected to complete and announce by Q3 2019
- Permits to commence mine development - Expected by Q2 2020
Michael Timmins, CEO of Emerita, commented: “Salobro has consistently exceeded our expectations during our
scoping and analysis phase. We are encouraged by the outcome of this early mine study and are very excited to have the
opportunity to utilize our award-winning mine building team in Brazil to fast track the development of Salobro. Our
preliminary engineering and mine plan which was completed by PROMINAS, a highly regarded engineering firm based in Belo
Horizonte, provides strong support for an aggressive exploration and development approach and continued investment into the region
and our people. Given the confidence we have in the scoping work and the well-established process for permitting in this region of
Brazil we aim to have the mine development permits in hand within 24-36 months.”
About the Salobro Project
The Salobro Project is located in Minas Gerais State, Brazil in an area well serviced with infrastructure
including a zinc smelter, paved roads, rail, water and power. The excellent access allows for year round project activities
and provides for a cost effective field program.
The deposit remains open for further expansion. The Company has laid out a program designed to advance the
project as quickly as possible to a point where a development decision can be made. Resampling of the existing drill core is
underway and will provide the QA/QC data in support of completing an NI 43-101 compliant resource estimate. The drill program
for the resource expansion has been tendered and will commence as soon as permits are in place, which is expected to be early March
2018. The results of the initial work program are expected to provide the necessary data for completing the initial
economic evaluation of the Salobro Project deposit.
A summary of the historical resource estimate can be found on the Company’s website in a report entitled
“Mineralizações De Zinco E Chumbo Do Depósito Salobro, Porteirinha (Mg) (2006)”. According to this report, the Salobro Project
deposit is estimated to contain 8.3 million tonnes grading 7.12% zinc and lead. A “qualified person”, as defined in
National Instrument 43-101 (“NI 43-101”), has not done sufficient work on behalf of Emerita to classify the historical estimate as
a current mineral resource and Emerita is not treating the historical estimate as a current mineral resource or mineral
reserve. Further work must be completed in order to demonstrate whether a reasonable expectation for commercial
extraction exists. The mineral resource estimate is a historical estimate and should not be relied upon.
Qualified Person
Each of Dr. Fernando Tallarico, P.Geo., and Carlos Cravo Costa, P.Geo., is a “qualified person” as such term is
defined in NI 43-101 and has reviewed and approved the technical information related to the Salobro Project included in this press
release and have approved its dissemination.
About Emerita Resources Corp.
Emerita is a natural resource company engaged in the acquisition, exploration and development of mineral
properties in Europe, with a primary focus on exploring in Spain and Brazil. The Company’s corporate office and technical teams are
based in Sevilla, Spain and Belo Horizonte, Brazil with an administrative office in Toronto, Canada.
For further information, contact:
Helia Bento
+1 416 309 4293 (Toronto)
info@emeritaresources.com
Cautionary Note Regarding Forward-looking Information
This press release contains “forward-looking information” within the meaning of applicable Canadian securities
legislation. Forward-looking information includes, without limitation, statements regarding the Salobro Project, the mineralization
at the Salobro Project, the Company’s ability to achieve the milestones related to the Salobro Project, the Company’s ability to
advance the Salobro Project and reach a development decision in the near term, and the Company’s future plans. Generally,
forward-looking information can be identified by the use of forward-looking terminology such as “plans”, “expects” or “does not
expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or “does not anticipate”, or
“believes”, or variations of such words and phrases or state that certain actions, events or results “may”, “could”, “would”,
“might” or “will be taken”, “occur” or “be achieved”. Forward-looking information is subject to known and unknown risks,
uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Emerita, as
the case may be, to be materially different from those expressed or implied by such forward-looking information, including but not
limited to: general business, economic, competitive, geopolitical and social uncertainties; the actual results of current
exploration activities; risks associated with operation in foreign jurisdictions; ability to successfully integrate purchased
properties or mining rights awarded; foreign operations risks; and other risks inherent in the mining industry. Although Emerita
has attempted to identify important factors that could cause actual results to differ materially from those contained in
forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There
can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially
from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking information.
Emerita does not undertake to update any forward-looking information, except in accordance with applicable securities laws.
NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE
POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.