TORONTO, May 02, 2018 (GLOBE NEWSWIRE) -- Hudbay Minerals Inc. (“Hudbay” or the “company”)
(TSX:HBM)(NYSE:HBM) today released its first quarter 2018 financial results. All amounts are in U.S. dollars, unless otherwise
noted.
Summary:
- Net profit of $41.4 million and earnings per share of $0.16 in the first quarter of 2018, compared to a net loss of $10.0
million (restated) and loss per share of $0.04 (restated) in the first quarter of 2017
- Operating cash flow1 of $131.8 million in the first quarter of 2018, a 64% increase from the first quarter of
2017
- Production of copper, gold and silver in concentrate increased by approximately 13%, 50% and 32%, respectively, in the first
quarter of 2018 compared to the first quarter of 2017 as a result of higher milled throughput at all operations
- Reduced net debt2 position by $37.7 million and improved liquidity during the first quarter 2018; as at March 31,
2018, Hudbay had net debt of $585.4 million and total available liquidity of $810 million, including $392.8 million in
cash
- Consolidated cash cost2, net of by-product credits, of $0.98 per pound of copper, an 11% increase from the first
quarter of 2017
- Consolidated all-in sustaining cash cost2, net of by-product credits, of $1.45 per pound of copper in the first
quarter of 2018, down slightly from $1.46 in the first quarter of 2017
- Peru precious metals production expected to be 15,000 ounces lower than initial guidance as a result of anticipated delay in
mining of Pampacancha, with the majority of the estimated $45 million of Peru growth capital expected to be deferred to 2019;
expected to meet all other production and cost guidance for 2018
- Test mining of Lalor gold Zone 25 has confirmed the possibility of utilizing selective methods for the gold zone to mine
fewer tonnes at a higher grade than reported in the current mineral resource estimate; trade-off studies to assess the mining and
processing options for the gold mineral resources at Lalor are ongoing
Net profit and earnings per share in the first quarter of 2018 were $41.4 million and $0.16, respectively,
compared to a net loss and loss per share of $10.0 million (restated) and $0.04 (restated), respectively, in the first quarter of
2017.
In the first quarter of 2018, operating cash flow before changes in non‑cash working capital increased to $131.8
million, compared to $80.6 million in the first quarter of 2017, mainly as a result of higher copper sales volumes and higher
realized prices of all metals.
“We began the first few months of the year much like we ended last year, by continuing to grow our positive free
cash flow and reduce debt,” said Alan Hair, president and chief executive officer. “In 2018, we will look to further increase
operating cash flow and reduce net debt. We are also focused on completing the ramp-up of base metal ore production at Lalor and
beginning production from the gold zones, both of which progressed well during the first quarter of 2018, as well as moving
Rosemont through the permitting process.”
Net profit and earnings per share in the first quarter of 2018 were affected by, among other things, the
following items:
|
|
|
|
|
|
|
|
|
|
|
|
Pre-tax gain
(loss) |
|
After-tax gain
(loss) |
|
Per share
gain (loss) |
|
|
|
|
($
millions) |
($
millions) |
|
($/share) |
|
|
|
|
|
|
|
|
|
|
|
Changes in accounting standards |
(3.4 |
) |
|
(3.8 |
) |
|
(0.01 |
) |
|
|
Foreign exchange gain |
4.0 |
|
|
3.4 |
|
|
0.01 |
|
|
|
Mark-to-market adjustments of various items |
10.2 |
|
|
8.5 |
|
|
0.03 |
|
|
|
Pampacancha delivery obligation |
(7.2 |
) |
|
(7.2 |
) |
|
(0.03 |
) |
|
|
Non-cash deferred tax adjustments |
- |
|
|
(2.8 |
) |
|
(0.01 |
) |
|
|
|
|
|
|
|
|
|
|
Effective January 1, 2018, a new revenue accounting standard issued by the International Accounting Standards
Board was implemented and applied retrospectively. Under the new standard, Hudbay’s stream agreements with Wheaton Precious Metals
now incorporate a significant financing component. The accretion of financing expense on the deferred revenue balance increases the
deferred revenue balance over time and the resulting higher deferred revenue balance is amortized to revenue, resulting in higher
revenue per ounce of metal sold under the stream, and higher finance expense. The impact to the first quarter of 2018 is an
increase to gross margin of $12.8 million, offset by an increase in finance expenses of $16.2 million. The net impact to after-tax
earnings per share is a loss of $0.01. All of these changes are non-cash.
During the first quarter of 2018, Hudbay recognized an obligation to deliver additional precious metal credits
to Wheaton Precious Metals as a result of the company’s expectation that mining at the Pampacancha deposit will not begin until
2019.
Compared to the first quarter of 2017, production of copper, gold and silver in concentrate in the first quarter
of 2018 increased as a result of higher milled throughput at all of Hudbay’s operations together with higher grades for precious
metals in Manitoba. Zinc production decreased by 6% as Lalor zinc grades have declined in line with the mine plan.
In the first quarter of 2018, consolidated cash cost per pound of copper produced, net of by-product credits,
was $0.98, an increase compared to $0.88 in the same period last year. The increase is mainly due to increased operating costs at
Hudbay’s 777 and Reed mines in Manitoba as the mines approach the later stages of their lives and reduced capitalized stripping at
Constancia, resulting in higher operating expense. Incorporating sustaining capital, capitalized exploration, royalties and
corporate selling and administrative expenses, consolidated all-in sustaining cash cost per pound of copper produced, net of
by-product credits, in the first quarter of 2018 was $1.45, down slightly from $1.46 in the first quarter of 2017.
Cash and cash equivalents increased by $36.3 million during the first quarter of 2018 to $392.8 million at March
31, 2018. This increase was mainly a result of cash generated from operating activities of $131.4 million. This inflow was partly
offset by $48.7 million of financing expenditures primarily driven by $37.4 million in interest paid on outstanding debt, and $46.0
million of investing activities primarily at Hudbay’s Peru and Manitoba operations.
Net debt declined by $37.7 million from December 31, 2017 to $585.4 million at March 31, 2018, as a result of
cash flow from Hudbay’s operations. At March 31, 2018, total liquidity, including cash and available credit facilities, was $810.0
million, up from $777.9 million at December 31, 2017.
Financial Condition
($000s) |
Mar. 31,
2018 |
Dec. 31, 2017
(Restated) |
Cash and cash equivalents |
392,796 |
356,499 |
Total long-term debt |
978,190 |
979,575 |
Net debt1 |
585,394 |
623,076 |
Working capital |
335,800 |
251,388 |
Total assets |
4,690,748 |
4,728,016 |
Equity |
2,145,321 |
2,112,345 |
1 Net debt is a non-IFRS financial performance measure with no standardized definition under IFRS. For further
information, please see page 6 of this news release.
Financial
Performance |
|
Three months ended |
($000s except per share and cash cost
amounts) |
|
Mar. 31 |
|
|
|
|
2018
|
2017
(Restated) |
Revenue |
|
|
386,656 |
261,767 |
|
Cost of sales |
|
|
265,885 |
205,121 |
|
Profit before tax |
|
|
73,103 |
4,637 |
|
Profit (loss) for the period |
|
|
41,445 |
(10,029) |
|
Basic and diluted earnings (loss) per share |
|
|
0.16 |
(0.04) |
|
Operating cash flow before change in non-cash
working capital |
|
|
131,791 |
80,595 |
|
|
Production and Cost
Performance |
Three months
ended |
Three
months ended |
|
|
Mar. 31, 2018 |
Mar. 31, 2017 |
|
|
|
Peru |
Manitoba |
Total |
Peru |
Manitoba |
Total |
|
Contained metal in concentrate
produced1 |
|
|
|
|
|
|
|
|
Copper |
tonnes |
31,551 |
7,655 |
|
39,206 |
27,211 |
7,520 |
|
34,731 |
|
|
|
Gold |
oz |
5,418 |
25,675 |
|
31,093 |
3,935 |
16,788 |
|
20,723 |
|
|
|
Silver |
oz |
645,886 |
331,252 |
|
977,138 |
539,534 |
198,360 |
|
737,894 |
|
|
|
Zinc |
tonnes |
- |
28,782 |
|
28,782 |
- |
30,570 |
|
30,570 |
|
Payable
metal in concentrate sold |
|
|
|
|
|
|
|
|
|
Copper |
tonnes |
29,568 |
6,938 |
|
36,506 |
18,565 |
7,850 |
|
26,415 |
|
|
|
Gold |
oz |
4,907 |
21,150 |
|
26,057 |
1,475 |
23,995 |
|
25,470 |
|
|
|
Silver |
oz |
595,630 |
290,826 |
|
886,456 |
383,263 |
293,302 |
|
676,565 |
|
|
|
Refined zinc2 |
tonnes |
- |
25,452 |
|
25,452 |
- |
26,832 |
|
26,832 |
|
|
|
Cash cost3 |
$/lb |
1.32 |
(0.38) |
|
0.98 |
1.30 |
(0.66) |
|
0.88 |
|
Sustaining cash cost3 |
$/lb |
1.47 |
1.03 |
|
|
1.61 |
0.28 |
|
|
|
All-in sustaining cash
cost3 |
$/lb |
|
|
1.45 |
|
|
1.46 |
|
1 Metal reported in concentrate is prior to deductions
associated with smelter contract terms.
2 Includes refined zinc metal sold and payable zinc in concentrate sold
3 Cash cost, sustaining cash cost and all-in sustaining cash cost per pound of copper produced, net of by-product
credits, are non-IFRS financial performance measures with no standardized definition under IFRS. For further information,
please see page 6 of this news release. |
|
Peru Operations Review
During the first quarter of 2018, the Peru operations produced 31,551 tonnes of copper, which was approximately
16% higher than production in the first quarter of 2017 as a result of improved ore throughput, offset by lower grades in line with
the mine plan. Copper equivalent production in the first quarter of 2018 was higher than in the same period in 2017 as there were
higher gold grades and higher mill throughput, partially offset by lower copper grades.
Recoveries of copper, gold and silver were slightly higher in the first quarter of 2018, compared to the same
period in 2017. Improved recoveries were due to continued plant optimization and processing less transitional ore types.
Combined mine, mill and G&A unit operating costs in the first quarter of 2018 were 3% lower than the same
period in 2017. The lower combined unit costs are mostly related to higher mill throughput partially offset by higher mining costs
due to a decrease in the mining costs that are capitalized.
Cash cost per pound of copper produced, net of by-product credits, for the three months ended March 31, 2018 was
$1.32, an increase of 2% from the same period in 2017 mainly as a result of lower capitalized mining costs and higher freight and
treatment and refining costs, partially offset by higher copper production and by-product credits.
Sustaining cash cost per pound of copper produced, net of by-product credits, for the three months ended March
31, 2018 was $1.47, a decrease of 9% from the same period in 2017 as a result of the factors noted above as well as reduced
sustaining capital expenditures in heavy civil works.
Hudbay completed a twin hole drill program in the fourth quarter of 2017 that confirmed the extent of the
positive grade bias that has existed since the commencement of production at Constancia. The company also constructed a new
resource model that formed the basis for a new mine plan and technical report for Constancia. The 2018 Technical Report includes an
updated mine plan showing an increase to the total metal contained in the estimated mineral reserves. The new mine plan also
reflects updated throughput, recoveries and capital and operating cost assumptions for the remaining life of mine at
Constancia.
The 2018 Technical Report assumes that mining of the high-grade Pampacancha satellite deposit will commence in
2019, which is one year later than contemplated by the previous technical report. Although negotiations to secure surface rights
over the Pampacancha deposit continue to progress and Hudbay has been granted access to the land to carry out early-works
activities, the company anticipates a one year delay to mining at Pampacancha. In the interim, the company will continue to mine
higher-grade ore from the main Constancia pit.
Manitoba Operations Review
During the first quarter of 2018, the Manitoba operations produced 28,782 tonnes of zinc, 7,655 tonnes of copper
and 30,407 ounces of gold-equivalent precious metals. Production of gold and silver was higher than the same quarter in 2017 by 53%
and 67%, respectively, as a result of higher precious metal grades at both Lalor and 777. Zinc production was 6% lower compared to
the same period of 2017 as a result of lower grades at Lalor in line with the mine plan. Copper production remained consistent
compared to the same period in 2017. Production of all metals in Manitoba for full year 2018 is forecast to be within the guidance
ranges.
Ore mined at Hudbay’s Manitoba operations during the first quarter of 2018 increased by 2% compared to the same
period in 2017 as a result of higher production at the Lalor and Reed mines, partially offset by lower production at the 777 mine.
Unit operating costs for all mines for the first quarter of 2018 increased by 23% compared to the same period in 2017. The increase
is a function of higher mobile and fixed infrastructure maintenance costs and higher expensed development costs.
Ore mined at Lalor increased as the ramp-up of production continued and the mine transitioned to higher gold and
copper grades with lower zinc as outlined in the life of mine plan. Higher unit costs reflect increased cement rock filling,
extensive cable bolting as well as continued operating and capital development that are required to increase Lalor’s production
rate to 4,500 tonnes per day, which is on track to be completed by the third quarter of 2018. The commissioning of the paste
backfill plant, which is on track for mid-2018, is expected to improve scoop availability and provide flexibility to the mine
planning and sequencing.
The Reed mine maintained consistent production and benefited from higher copper grades as Hudbay mines out Zone
10 at depth. Hudbay is no longer capitalizing development costs at Reed with the pending closure of the mine in the third quarter
of 2018, resulting in higher unit operating costs compared to prior periods.
Ore mined at 777 declined as ground conditions warranted rehabilitation of headings and a more conservative
stope sequence in order to adapt to more challenging operating conditions as the mine ages. Higher 777 unit operating costs were
driven by higher mobile and fixed infrastructure maintenance costs and ground rehabilitation work completed in the quarter,
together with the impact of lower production.
Ore processed in Flin Flon in the first quarter of 2018 was 5% higher than the same period in 2017 as a result
of increased ore availability due to the transfer of excess Lalor ore to the Flin Flon concentrator. Copper and precious metals
recoveries were higher in the first quarter of 2018 compared to the first quarter in 2017 as a result of higher head grades. Unit
operating costs at the Flin Flon concentrator were 9% higher in the first quarter of 2018 compared to the same period in 2017 as a
result of increased material handling costs driven by the management of large stockpiles, and initial difficulties in processing
Lalor ore through the Flin Flon concentrator crushing plant due to the impact of cold winter weather. Ore processed at the Stall
concentrator in the first quarter of 2018 was 5% higher compared to the same period in 2017 as a result of improved mechanical
reliability. Unit operating costs at the Stall concentrator were 24% lower in the first quarter of 2018 compared to the first
quarter of 2017 as damage to the crusher in December 2016 had necessitated the use of higher-cost temporary crushing facilities
during the first quarter of 2017.
Manitoba combined mine, mill and G&A unit operating costs in the first quarter of 2018 were 16% higher than
in the same period in 2017 as a result of higher costs at Hudbay’s mines and the Flin Flon concentrator. Combined unit costs are
expected to be within the guidance range for 2018, as the higher costs in the first quarter were caused in part by the colder than
normal winter.
Cash cost per pound of copper produced, net of by-product credits, in the first quarter of 2018 was negative
$0.38. This was higher compared to the same period in 2017, primarily as a result of the factors affecting unit operating costs
described above. Sustaining cash cost per pound of copper produced, net of by-product credits, in the first quarter of 2018 was
$1.03, compared to $0.28 in the prior year period as a result of the same factors described above and planned increased sustaining
and exploration capital spending.
Lalor Gold Zone Update
The Lalor mine plan for 2018 includes some mining of the gold zone for processing at Flin Flon, which was
included in Hudbay’s precious metals guidance issued in January. Trade-off studies have been ongoing in order to assess the mining
and processing options for the gold mineral resources at Lalor. Test mining of Zone 25 began in February 2018 in order to better
understand the characteristics of the gold zone and to inform the evaluation of options for its processing. The test mining has
confirmed the possibility of utilizing selective methods to mine fewer tonnes at a higher grade than reported in the current
mineral resource estimate. Year to date, Hudbay has mined 4,500 tonnes at 14.5 g/t, confirming the opportunity to operate
successfully at a higher cut-off grade. A batch sample of gold-rich ore sent to the Flin Flon concentrator in late 2017 achieved
gold recoveries of 65%. Currently, the gold ore is being shipped to Flin Flon for processing.
In parallel, Hudbay is continuing exploration in an attempt to further extend gold- and copper-rich veins down
plunge from the existing resources and targeting possible extensions of the base metals lenses both up and down plunge from known
resources. Highlights from the drill program that focused on extensions of gold- and copper-rich veins, each of which is outside of
the current reserve, are provided in the below table.
Hole ID |
From
(m) |
To
(m) |
Intercept
(m) |
Depth
(m) |
Estimated true
width(m)1 |
Cu
(%)2 |
Au
(g/t)2 |
189W01 |
1197.0 |
1205.0 |
8.0 |
1154 |
7.1 |
0.1 |
9.3 |
193W01 |
1041.2 |
1046.5 |
5.4 |
1028 |
4.1 |
1.1 |
2.8 |
267W01 |
1120.8 |
1127.2 |
6.3 |
1098 |
4.5 |
2.7 |
11.3 |
273 |
1211.8 |
1215.8 |
4 |
1202 |
2.9 |
1.9 |
1.2 |
283 |
1242.7 |
1249.0 |
6.3 |
1240 |
4.2 |
7.8 |
5.9 |
283W02 |
1270.8 |
1276.3 |
5.5 |
1263 |
4.1 |
7.8 |
2.5 |
296 |
1227.5 |
1233.0 |
5.5 |
1184 |
4.2 |
5.2 |
5.6 |
296W01 |
1220.5 |
1228.3 |
7.8 |
1175 |
6.1 |
3.7 |
5.4 |
1 True widths are estimated based on drill angle and interpreted geometry of mineralization.
2 All gold and copper values are uncut.
In 2018, Hudbay will continue to conduct test mining of the gold lenses, which will support continued trade-off
studies to assess the mining and processing options for Lalor gold and advance the permitting process for the potential
refurbishment of the New Britannia mill. Ongoing exploration is targeted at converting gold mineral resources to mineral reserves
at Lalor and greenfield gold exploration efforts in Snow Lake.
Rosemont Developments
Work continues with the U.S. Forest Service on the draft Mine Plan of Operations, which is progressing as
planned. The remaining key federal permit outstanding is the Section 404 Water Permit from the U.S. Army Corps of Engineers.
Opponents of the Rosemont project have filed lawsuits against the U.S. Forest Service challenging, among other
things, the issuance of the Final Record of Decision in respect of Rosemont. Hudbay is confident that Rosemont’s permits will
continue to be upheld.
Outlook
Given our expectation that mining at Pampacancha will not begin until 2019, we expect that Peru precious metals
production will be 50,000 to 70,000 ounces in 2018, a decrease of 20% compared to our initial 2018 guidance issued on January 17,
2018 and consistent with the 25% sensitivity noted in our initial guidance.3 The majority of the estimated $45 million
of Peru growth capital, which includes expenditures for developing the Pampacancha deposit and acquiring surface rights from the
local community, is expected to be deferred to 2019. Based on results to date, we expect to meet all other production and cost
guidance for 2018.
Non-IFRS Financial Performance Measures
Net debt is shown in this news release because it is a performance measure used by the company to assess its
financial position. Cash cost, sustaining and all-in sustaining cash cost per pound of copper produced are shown because the
company believes they help investors and management assess the performance of its operations, including the margin generated by the
operations and the company. These measures do not have a meaning prescribed by IFRS and are therefore unlikely to be comparable to
similar measures presented by other issuers. These measures should not be considered in isolation or as a substitute for measures
prepared in accordance with IFRS and are not necessarily indicative of operating profit or cash flow from operations as determined
under IFRS. Other companies may calculate these measures differently. For further details on these measures, including
reconciliations to the most comparable IFRS measures, please refer to page 27 of Hudbay’s management’s discussion and analysis for
the three months ended March 31, 2018 available on SEDAR at www.sedar.com and EDGAR at www.sec.gov.
Website Links
Hudbay:
www.hudbay.com
Management’s Discussion and Analysis:
http://www.hudbayminerals.com/files/doc_financials/2018/Q1/MDA181.pdf
Financial Statements:
http://www.hudbayminerals.com/files/doc_financials/2018/Q1/FS181.pdf
Conference Call and Webcast
Date: |
Thursday, May 3, 2018 |
Time: |
10 a.m. ET |
Webcast: |
www.hudbay.com
|
Dial in: |
416-849-1847 or 1-866-530-1554 |
Qualified Person
The technical and scientific information in this news release related to the Constancia mine and Rosemont
project has been approved by Cashel Meagher, P. Geo, Hudbay’s Senior Vice President and Chief Operating Officer. The technical and
scientific information related to the Manitoba sites and projects (including the Lalor gold zone) contained in this news release
has been approved by Robert Carter, P. Eng, Hudbay’s General Manager Mining Operations, Manitoba Business Unit. Messrs. Meagher and
Carter are qualified persons pursuant to NI 43‑101. For a description of the key assumptions, parameters and methods used to
estimate mineral reserves and resources, as well as data verification procedures and a general discussion of the extent to which
the estimates of scientific and technical information may be affected by any known environmental, permitting, legal title,
taxation, sociopolitical, marketing or other relevant factors, please see the Technical Reports for the company’s material
properties as filed by Hudbay on SEDAR at www.sedar.com.
Additional Information – Lalor Gold Zone Exploration Data
Information on the data verification performed on the exploration data related to the Lalor gold zone is
contained in Hudbay’s most recently filed annual information form, dated March 29, 2018, and the current technical report for
Lalor, dated March 30, 2017, each of which is filed on SEDAR at www.sedar.com. Quality Assurance/Quality Control procedures
for the Lalor exploration program include the systematic insertion of blanks, standards and duplicates into the core sample
strings. The results of the control samples are evaluated on a regular basis with batches and are re-analysed and/or resubmitted as
needed. There are no drilling, sampling, recovery or other factors that could materially affect the accuracy or reliability of the
preliminary results.
Due to the length of the Lalor gold zone drillholes and the numerous downhole deviations in azimuth and dip, the
azimuth and dip of the drill hole locations has not been reported. Instead, the table below provides the coordinates, azimuth and
dip of the mineralized intercepts that have been reported in this news release.
|
From |
To |
Azimuth at
intercept |
Dip at
intercept |
Core
Size |
Hole ID |
Easting |
Northing |
Elevation |
Easting |
Northing |
Elevation |
189W01 |
426,663 |
6,081,675 |
4,149 |
426,660 |
6,081,675 |
4,142 |
272 |
-63 |
NQ |
193W01 |
427,051 |
6,081,272 |
4,273 |
427,051 |
6,081,270 |
4,268 |
185 |
-76 |
NQ |
267W01 |
427,185 |
6,081,266 |
4,204 |
427,183 |
6,081,266 |
4,197 |
242 |
-79 |
NQ |
273 |
427,163 |
6,081,570 |
4,101 |
427,162 |
6,081,570 |
4,098 |
206 |
-79 |
NQ |
283 |
427,223 |
6,081,530 |
4,064 |
427,222 |
6,081,530 |
4,057 |
248 |
-83 |
NQ |
283W02 |
427,263 |
6,081,461 |
4,040 |
427,263 |
6,081,460 |
4,035 |
186 |
-77 |
NQ |
296 |
427,251 |
6,081,311 |
4,121 |
427,251 |
6,081,310 |
4,115 |
154 |
-76 |
NQ |
296W01 |
427,243 |
6,081,301 |
4,130 |
427,244 |
6,081,299 |
4,123 |
163 |
-73 |
NQ |
Forward-Looking Information
This news release contains forward-looking information within the meaning of applicable Canadian and United States securities
legislation. All information contained in this news release, other than statements of current and historical fact, is
forward-looking information. Often, but not always, forward-looking information can be identified by the use of words such as
“plans”, “expects”, “budget”, “guidance”, “scheduled”, “estimates”, “forecasts”, “strategy”, “target”, “intends”, “objective”,
“goal”, “understands”, “anticipates” and “believes” (and variations of these or similar words) and statements that certain actions,
events or results “may”, “could”, “would”, “should”, “might” “occur” or “be achieved” or “will be taken” (and variations of these
or similar expressions). All of the forward-looking information in this news release is qualified by this cautionary note.
Forward-looking information includes, but is not limited to, production, cost and capital and exploration
expenditure guidance, anticipated production at Hudbay’s mines and processing facilities, the anticipated timing, cost and benefits
of developing the Rosemont project and Pampacancha deposit, the anticipated impact of any delays to the start of mining the
Pampacancha deposit, the anticipated results of litigation challenging the Rosemont permitting process, anticipated exploration
plans, including the planned exploration and development strategy for the Lalor gold zones, the exploration potential at Lalor,
including the possibility of converting inferred mineral resources to higher confidence categories and establishing additional
mineral resources through testing the continuity of the mineralized zones, the anticipated continued success of utilizing a
selective mining method to mine the high grade gold zones, anticipated mine plans, anticipated metals prices and the anticipated
sensitivity of the company’s financial performance to metals prices, events that may affect its operations and development
projects, the permitting, development and financing of the Rosemont project, the potential to optimize the scale of production at
Lalor and to efficiently process the excess base metals ore and initial gold zone ore production at the Flin Flon mill, anticipated
cash flows from operations and related liquidity requirements, the anticipated effect of external factors on revenue, such as
commodity prices, estimation of mineral reserves and resources, mine life projections, reclamation costs, economic outlook,
government regulation of mining operations, and business and acquisition strategies. Forward-looking information is not, and cannot
be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions, assumptions,
estimates and analyses that, while considered reasonable by the company at the date the forward-looking information is provided,
inherently are subject to significant risks, uncertainties, contingencies and other factors that may cause actual results and
events to be materially different from those expressed or implied by the forward-looking information.
The material factors or assumptions that Hudbay identified and were applied by the company in drawing
conclusions or making forecasts or projections set out in the forward-looking information include, but are not limited to:
- the success of mining, processing, exploration and development activities;
- the scheduled maintenance and availability of the processing facilities;
- the accuracy of geological, mining and metallurgical estimates;
- anticipated metals prices and the costs of production;
- the supply and demand for metals the company produces;
- the supply and availability of all forms of energy and fuels at reasonable prices;
- no significant unanticipated operational or technical difficulties;
- the execution of Hudbay’s business and growth strategies, including the success of its strategic investments and
initiatives;
- the availability of additional financing, if needed;
- the ability to complete project targets on time and on budget and other events that may affect the company’s ability to
develop its projects;
- the timing and receipt of various regulatory, governmental and joint venture partner approvals;
- the availability of personnel for the exploration, development and operational projects and ongoing employee relations;
- the ability to secure required land rights to develop the Pampacancha deposit;
- maintaining good relations with the communities in which the company operates, including the communities surrounding the
Constancia mine and Rosemont project and First Nations communities surrounding the Lalor and Reed mines;
- no significant unanticipated challenges with stakeholders at the company’s various projects;
- no significant unanticipated events or changes relating to regulatory, environmental, health and safety matters;
- no contests over title to the company’s properties, including as a result of rights or claimed rights of aboriginal
peoples;
- the timing and possible outcome of pending litigation and no significant unanticipated litigation;
- certain tax matters, including, but not limited to current tax laws and regulations and the refund of certain value added
taxes from the Canadian and Peruvian governments; and
- no significant and continuing adverse changes in general economic conditions or conditions in the financial markets
(including commodity prices and foreign exchange rates).
The risks, uncertainties, contingencies and other factors that may cause actual results to differ materially
from those expressed or implied by the forward-looking information may include, but are not limited to, risks generally associated
with the mining industry, such as economic factors (including future commodity prices, currency fluctuations, energy prices and
general cost escalation), uncertainties related to the development and operation of the company’s projects (including risks
associated with the permitting, development and economics of the Rosemont project and related legal challenges), risks related to
the exploration and development program at Lalor, including the inability to convert inferred mineral resources to higher
confidence categories and to identify additional mineral resources, and risks associated with the selective mining of the high
grade gold zones, risks related to the maturing nature of the 777 mine and the pending closure of the Reed mine and their impact on
the related Flin Flon metallurgical complex, dependence on key personnel and employee and union relations, risks related to the
schedule for mining the Pampacancha deposit (including the timing and cost of acquiring the required surface rights and the impact
of any schedule delays), risks related to political or social unrest or change, risks in respect of aboriginal and community
relations, rights and title claims, operational risks and hazards, including unanticipated environmental, industrial and geological
events and developments and the inability to insure against all risks, failure of plant, equipment, processes, transportation and
other infrastructure to operate as anticipated, compliance with government and environmental regulations, including permitting
requirements and anti-bribery legislation, depletion of the company’s reserves, volatile financial markets that may affect the
company’s ability to obtain additional financing on acceptable terms, the failure to obtain required approvals or clearances from
government authorities on a timely basis, uncertainties related to the geology, continuity, grade and estimates of mineral reserves
and resources, and the potential for variations in grade and recovery rates, uncertain costs of reclamation activities, the
company’s ability to comply with its pension and other post-retirement obligations, the company’s ability to abide by the covenants
in its debt instruments and other material contracts, tax refunds, hedging transactions, as well as the risks discussed under the
heading “Risk Factors” in Hudbay’s most recent Annual Information Form.
Should one or more risk, uncertainty, contingency or other factor materialize or should any factor or assumption
prove incorrect, actual results could vary materially from those expressed or implied in the forward-looking information.
Accordingly, you should not place undue reliance on forward-looking information. Hudbay does not assume any obligation to update or
revise any forward-looking information after the date of this news release or to explain any material difference between subsequent
actual events and any forward-looking information, except as required by applicable law.
Note to United States Investors
This news release has been prepared in accordance with the requirements of the securities laws in effect in
Canada, which may differ materially from the requirements of United States securities laws applicable to U.S. issuers.
About Hudbay
Hudbay (TSX:HBM)(NYSE:HBM) is an integrated mining company primarily producing copper concentrate (containing
copper, gold and silver), zinc concentrate and zinc metal. With assets in North and South America, the company is focused on the
discovery, production and marketing of base and precious metals. Directly and through its subsidiaries, Hudbay owns four
polymetallic mines, four ore concentrators and a zinc production facility in northern Manitoba and Saskatchewan (Canada) and Cusco
(Peru), and a copper project in Arizona (United States). The company’s growth strategy is focused on the exploration and
development of properties it already controls, as well as other mineral assets it may acquire that fit its strategic criteria.
Hudbay’s vision is to be a responsible, top-tier operator of long-life, low-cost mines in the Americas. Hudbay’s mission is to
create sustainable value through the acquisition, development and operation of high-quality, long-life deposits with exploration
potential in jurisdictions that support responsible mining, and to see the regions and communities in which the company operates
benefit from its presence. The company is governed by the Canada Business Corporations Act and its shares are listed under
the symbol "HBM" on the Toronto Stock Exchange, New York Stock Exchange and Bolsa de Valores de Lima. Hudbay also has warrants
listed under the symbol “HBM.WT” on the Toronto Stock Exchange and “HBM/WS” on the New York Stock Exchange.
For further information, please contact:
Carla Nawrocki
Director, Investor Relations
(416) 362-7362
carla.nawrocki@hudbay.com
___________________________
1 Operating cash flow before change in non-cash working capital.
2 Net debt, cash cost and all-in sustaining cash cost per pound, net of by-product credits, are not recognized under
IFRS. For a detailed description of each of these non-IFRS financial performance measures, please see the discussion under
“Non-IFRS Financial Performance Measures” beginning on page 6 of this news release.
3 Precious metals production includes gold and silver production on a gold-equivalent basis. Silver converted to gold
at a ratio of 70:1. Initial guidance for precious metals production, issued on January 17, 2018, was 65,000 to 85,000
ounces.