Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.

Harte Gold Announces Positive PEA For the Sugar Zone Project

TORONTO, May 03, 2018 (GLOBE NEWSWIRE) -- HARTE GOLD CORP. (“Harte Gold” or the “Company”) (TSX:HRT) (OTC:HRTFF) (Frankfurt:H4O) is pleased to announce the results of a positive Preliminary Economic Assessment (“PEA”) for the Company’s 100% owned Sugar Zone Project (“Sugar Zone” or the “Project”), near White River, Northern Ontario.

Highlights:

  • 80,700 ounces of average annual gold production at a C1 cash cost of US$507/oz Au and AISC of US$708/oz Au over an 11 year mine life from 2019 onwards.
  • 904,000 ounces of total recovered gold production over mine life, approximately two thirds of the combined Indicated and Inferred Mineral Resources announced February 15, 2018.
  • The PEA studied a phased development approach with a goal of achieving near-term cash flow while minimizing initial underground development work, starting at 540 tpd at the Sugar Zone, increasing to 1,400 tpd by year 2021 as access to the Middle Zone Mineral Resources are incorporated into the mine plan.
    • The benefit of mining the higher grade areas of the Sugar and Middle Zones in parallel is expected to increase average annual gold production to over 100,000 ounces from 2021 to 2025.
    • 54,500 ounces of average annual gold production is targeted for 2019 and 2020.
    • C$58 million remains to be spent in 2018 as of March 31, 2018, on process plant completion, underground development and working capital.  Process plant construction is over 80% complete.  The Company expects to be starting production by July 2018.
  • Management have identified a number of opportunities, outside the scope of the mine plan studied in the PEA, which could further improve the mine plan and economics of the Project.  These opportunities, while still being explored, were recognized based on the positive infill drilling and mine plan optimizations, currently underway.
  • The following table summarizes NPV and IRR at various gold price and exchange rate sensitivities:

NPV and IRR Summary

  Unit Gold Price Sensitivities
US$1,150/oz PEA Pricing US$1,350/oz
Macro Parameters        
Gold Price US$/oz $ 1,150   $ 1,250   $ 1,350  
Exchange Rate CAD:USD   0.80     0.80     0.80  
Pre-Tax NPV and IRR        
NPV @ 5% M C$ $ 263   $ 344   $ 425  
IRR  %   40 %   50 %   60 %
Post-Tax NPV and IRR        
NPV @ 5% M C$ $ 189   $ 244   $ 299  
IRR  %   34 %   42 %   50 %

Stephen G. Roman, President and CEO of Harte Gold, commented “The PEA demonstrates an economically robust, low cost operation with a scalable mine plan designed to match underground development.  With a target of 1,400 tonnes per day producing over 100,000 ounces per year, Harte Gold will have the cash flow to continue property wide exploration and the ability to target high impact acquisition opportunities.”

Mr. Roman added “We are particularly encouraged by the value opportunities being explored.   As illustrated with previous infill drilling, grade is expected to improve as we tighten spacing, which will have a significant, positive effect on the diluted head grade mined and the number of ounces incorporated into the mine plan.  There are over 500,000 ounces of resource currently not included within the PEA mine plan.  As we continue drilling, we expect the economics of the Sugar Zone Project should only improve.”

PEA Summary
The PEA was prepared by P&E Mining Consultants Inc. and is summarized as follows:

PEA Base Case Summary Parameters

Input Unit Value
Macro Parameters    
Gold Price US$/oz $ 1,250  
Exchange Rate CAD:USD   0.80  
Physical Parameters    
Total Tonnes Processed (Life of Mine) Tonnes   4,539,800  
Average Annual Throughput (2019+) tpa   403,000  
Diluted Head Grade Au g/t   6.5  
Gold Recovery %   95.4 %
Mine Life Years   12  
Total Ounces Recovered Ounces   904,000  
Average Annual Production (2019 – 2020) Ounces   54,500  
Average Annual Production (2021 – 2025) Ounces   106,900  
Average Annual Production (LOM) Ounces   80,700  
Peak Annual Production (2024) Ounces   121,400  
Cost Parameters    
Mining Costs C$/tonne $ 90.83  
Processing Costs C$/tonne $ 28.71  
Site G&A C$/tonne $ 8.46  
Total Costs C$/tonne $ 128.01  
Capital Cost (LOM)    
Underground Development M C$ $ 176  
Equipment M C$ $ 5  
Infrastructure M C$ $ 24  
Tailings Expansion M C$ $ 18  
Process Plant Construction M C$ $ 59  
Cost Summary    
LOM Average Cost US$/oz $ 507  
LOM ASIC US$/oz $ 708  

Mineral Resource
The Mineral Resource incorporated into the PEA is based on the National Instrument (“NI 43-101”) 43-101 Mineral Resource Estimate with an effective date of February 15, 2018.

Mineral Resource Estimate, at 3.0 g/t Au Cut-Off1-6

  Zone Tonnes Grade

(g/t Au)
Contained Gold (ounces)
Indicated Sugar Zone 2,148,000 8.6 594,700
Middle Zone 460,000 8.1 119,500
Total 2,607,000 8.5 714,200
Inferred Sugar Zone 1,802,000 6.4 369,300
Middle Zone 1,788,000 6.8 391,500
Total 3,590,000 6.6 760,800


(1) Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability.
(2) The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
(3) The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could be upgraded to an Indicated Mineral Resource with continued exploration.
(4) The Mineral Resources in the PEA were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.
(5) Advanced Exploration Bulk Sample mined out area removed from the model.
(6) The 3g/t Au cut-off was derived from US$1,250 Au price, US$0.80 exchange rate, C$86/t mining cost, C$28/t processing cost, C$5/t G&A cost, C$10/t sustaining Capex, US$5/oz refining cost, 96% processing recovery and US$115/oz shipping, smelting and royalty charges (averaged across total production).

Mineable Mineralization for Mine Planning Purposes
For purposes of mine planning, and after factoring in planned dilution, varying cut-off grades for stope and low grade development material, the Potentially Mineable Mineralization is comprised of 4.5 million tonnes at a diluted grade of 6.5 g/t Au, containing 941,000 ounces of gold.

Potentially Mineable Mineralization For Mine Planning

  Zone Tonnes Diluted Grade

(g/t Au)
Contained Gold (ounces)
Indicated Sugar Zone 2,057,000 7.2 474,000
Middle Zone 451,000 6.8 98,000
Total 2,508,000 7.1 571,000
Inferred Sugar Zone 731,000 6.0 141,000
Middle Zone 1,260,000 5.6 228,000
Total 1,991,000 5.8 370,000

Some figures may not add up due to rounding

The Potentially Mineable Mineralization was determined using several cut-off grades ranging from 3.5 g/t Au for stope cut-off grades, down to 1.5 g/t Au for low grade development, with an average 4.3 g/t Au cut-off grade applied that included mine development capital costs.

Approximately 534,000 ounces of the Mineral Resources were excluded from the PEA mine plan due to drill density and lower grade mineralization.  A majority of the mineralization excluded is classified as Inferred Mineral Resources, located below the Sugar Zone North Ramp at 500 metres depth and the Middle Zone Ramp at 750 metres depth, illustrated in the following longitudinal projections.

Photos accompanying this announcement are available at

http://resource.globenewswire.com/Resource/Download/d5e59c9d-b1ff-4f03-a13a-368846bc044c

http://resource.globenewswire.com/Resource/Download/e4b85afe-9b1e-45b8-89ac-9cb714c55d6f

Mine Plan

Longitudinal longhole retreat stoping was selected as the mining method based on a favourable geometry, geotechnical understanding and the success of the Bulk Sample program completed in 2017.  Both the mineralized material and the host rock are sufficiently competent to support the void sizes required for effective longhole stoping.  Paste backfill will be the primary fill type.

A level-by-level, bottom up stope sequence was applied to the stopes within each mining block.  The Sugar Zone stope design was based on 15 metre levels, 50 metre lengths and factoring in 38% dilution.  The Middle Zone stope design was based on 20 metre levels, 30 metre lengths and factoring in 28% dilution.

The Sugar Zone North and South ramp stopes are targeted first, to maximize near-term production and minimize pre-production development costs.  These areas are lower in grade for the first 18 months and will be mined before reaching higher grade stopes below.  Average diluted grade over the first 18 months of production is 5.5 g/t Au.

During years 2020 to 2025, the higher grade areas of both the Sugar and Middle Zones will be accessible, providing access to high grade stopes averaging a diluted head grade of 7.3 g/t Au during this period.

From 2025 onward, the Inferred Mineral Resource currently classified as lower grade are mined at an assumed diluted grade averaging 5.3 g/t Au.

Longitudinal projections illustrating the diluted mining grades and mining sequence by year are provided below. 

A photo accompanying this announcement is available at http://resource.globenewswire.com/Resource/Download/b65aa266-2c9b-494f-ab5d-0acd2e5cdc8c

Initial mine production is targeted at a nominal rate of 540 tpd and will increase as underground development continues as per the schedule below:

Phased Mine Production Schedule

Phase 1 Mining Rate:
540 tpd
(2018 – 2019)
  • Initial operations are permitted to operate at 540 tpd
  • Low risk ramp-up to commercial production
  • Use of mine contractors in early years limits mining risk
  • Process plant to operate up to 800 tpd, augmented by surface stockpiles
Phase 2 Mining Rate:
800 tpd
(2020)
  • Existing surface and underground mining infrastructure is sufficient to support increased throughput
  • Increase throughput via notification to Canadian Environmental Assessment Agency (“CEAA”)
Phase 3 Mining Rate:
1,400 tpd
(2021+)
  • Throughput increased by adding second ball mill and leach circuit to eliminate concentrate shipments
  • Incorporation of the Middle Zone allows for multiple stoping areas 
  • Transition to owner operated mining
  • Impact Benefit Agreement covers all future expansions on the property

Processing and Recovery
800 tpd Process Plant
The process plant design was sized to support the initial Phase 1 mining rate of 540 tpd and Phase 2 increase of the mining rate to 800 tpd.  The process plant commences by producing both a doré bar and a bagged gold concentrate through gravity concentration and flotation circuits, respectively.  This process plant is currently under construction and is over 80% complete.  The major process steps are as follows:

  • Primary and Secondary crushing;
  • Fine feed storage (stockpile);
  • Grinding (ball mill);
  • Gravity concentration;
  • Flotation;
  • Filtration; and
  • Tailings thickening.

Increasing to 1,400 tpd
Harte Gold commissioned Halyard Inc. (“Halyard”) to prepare a study examining the Phase 3 process plant expansion to 1,400 tpd and incorporation of a flotation concentrate leaching circuit that would allow the Project to produce only a doré, rather than a combined doré and flotation concentrate output.

The simplest option to support throughput expansion is to build a parallel ball mill, gravity circuit with 600 tpd capacity, then combine flotation concentrates in a common leaching circuit. In order to minimize duplicative capital and operating costs, some level of integration in combining circuits was examined.

The Halyard study concluded that an additional process plant building is necessary to house a parallel ball mill and gravity circuit, a concentrate leaching circuit and a cyanide leach solution handling/gold recovery circuit, adjacent to the existing process plant facility.  Other areas such as crushing, feed storage and flotation equipment can be successfully combined.  Construction of the expanded process plant facility and flotation concentrate leaching circuit is expected to be completed by the end of year 2020 and operational for 2021.

The following charts illustrate the positive impact of increased production.

http://resource.globenewswire.com/Resource/Download/bd238b69-eb01-4a95-a479-d1d6ab32294e

http://resource.globenewswire.com/Resource/Download/baec1796-cf3c-4c2a-82a9-2b39c21aa8be

Capital Costs and Working Capital

Capital Costs (C$ Millions, As at March 31, 2018)

Input Pre-Production
(2018)
Sustaining
(2019+)
Total
(LOM)
Underground Development $ 12 $ 164 $ 176
Process Plant Construction $ 36 $ 23 $ 59
Underground Infrastructure $ 9 $ 15 $ 24
Tailings Expansion $ 0 $ 18 $ 18
Equipment $ 1 $ 3 $ 5
Total Capital Costs $ 58 $ 223 $ 281

Pre-Production Capital Costs
Due to  of  the  amount of work  already  completed,  very  little  additional  development  is required prior to stope production, serving to minimize commissioning risk.  The remaining work includes completing sill development on five levels, long-hole drilling in advance of stope blasting, and ventilation drift development.

Process plant construction is well underway. Detailed engineering began in Q1 2017, long lead equipment purchases were made in Q2 2017 and site construction began shortly thereafter.  The process facility is over 60% completed.  The total cost of process plant construction will be C$83 million, including the paste fill plant, tailings management, site power and other surface infrastructure, of which C$36 million remains.

No significant pre-production underground infrastructure is required.  The ventilation raise is completed and underground distribution has been upgraded.  Remaining major infrastructure items include ventilation fans, a surface substation, paste fill distribution system and various underground support investments, which will be completed over the period of May through September 2018.

Sustaining Capital Costs
The largest sustaining capital item is the cost of underground development and maintaining a development rate that is sufficient to open enough working faces to support the planned mining rate.  Increasing the mine production to 1,400 tpd will require developing the ramp from the Sugar Zone to the Middle Zone, which is scheduled to begin upon the start of commercial production.  The Sugar Zone requires two ramps, the Sugar Zone North Ramp and Sugar Zone South Ramp, developed to a depth of approximately 1,000 metres and 500 metres, respectively.  The Sugar Zone ramps incorporate linking ramps at approximately 180 metre intervals to support ventilation, pumping, etc.

Approximately C$23 million of sustaining capital has been budgeted for the process plant throughput expansion to 1,400 tpd, which requires the following modifications:

  • Additional cone crusher to increase capacity of the crushing circuit.
  • A second parallel ball mill.
  • Storage modifications and additional conveyors for the second ball mill.
  • Three additional flotation cells.
  • Concentrate regrind and leaching equipment.

To support expansion of operations, the tailings management capacity will need to be increased over the life of mine.  The initial expansion involves a second raise of the tailings dam in Q3 2020 and thereafter, development of a second tailings management facility, which was included as part of the approved environmental assessment.

Opportunities To Enhance Project Value
The Company has recognized several areas for opportunity to further enhance value at the Sugar Zone Project.

Area of Focus Opportunities to Explore Management Target
Higher Head Grade
  • During previous Mineral Resource model updates, increasing drill density when converting Inferred to Indicated Mineral Resource and better classification has led to improved average Mineral Resource grades in the Indicated classification.  This trend is likely to continue.
  • Recent drilling in the Middle Zone (occurring after the database cut-off for this Mineral Resource model update) has increased the Indicated metal content per level in the Middle Zone.  Au grade has maintained or improved and this is expected to continue.
  • Improve head grade
  • Target: 7.0 to 8.0 g/t Au
Convert Additional PEA Mineral Resource Into Mine Plan
  • A significant amount of the NI 43-101 Inferred Mineral Resources at the Sugar and Middle Zones were excluded from the PEA mine plan due to wide drill spacing resulting in lower grades.
  • Infill drilling is underway in these areas and could substantially upgrade the Mineral Resources and add an additional +500,000 Au ounces currently not factored into the mine plan
  • Increase mineable resource
  • Target: Add +500,000 ounces to mine plan
Grow Property Wide Mineral Resource Base
  • The Sugar and Middle Zones remain open at depth and on strike.
  • Incorporating new zones such as the Wolf Zone and the Footwall Zone will increase Mineral Resources and extend mine life.
  • A property wide, systematic exploration programs across the remainder of the 80,000 hectare property are underway with significant potential to add additional deposits.
  • TBD
 
Optimize Mine Plan Scheduling,  Reduce Mining Cost
  • Sublevel spacings are considered conservative in an effort to minimize dilution. Mine optimization with further geotechnical analysis and data is likely to provide opportunities to increase stope dimensions and/or level interval, providing a cost and productivity benefit.
  • Sill drift dimensions are expected to be optimized as drill and blast practices and equipment are honed during the ramp-up phase. Any modification to the sill development profile has the potential to increase the grade mined from the sills. Sill development accounts for approximately 20% of total mill feed production, but is 3 times the cost of drilling and blasting the stopes.
  • Optimization of the mining sequence within each mining block has the potential to reduce the amount of remote mucking and thereby provide productivity and cost benefits. The mine plan incorporates a level-by-level, bottom-up mining sequence for each mining block (typically four levels), which simplifies planning and logistics, however stopes that span multiple levels and dimensioned according to local geotechnical limits have the potential to improve productivity.
  • The assumed underlying contractor mining costs in the PEA appear conservative.  As the mining costs are improved and Harte Gold transitions to its own mining team, there will be a positive impact on cash flows.
  • Increasing the availability and implementation of battery powered equipment would provide opportunity to reduce ventilation costs, since mine ventilation is the major consumer of power in the mine.
  • Reduce mining dilution
  • Lower mining costs

Project Economics
The Project economics are summarized in the following table.  A 2.0% net smelter royalty (“NSR”) is payable over mine life.  The existing 3.5% NSR can be reduced to 2.0% on payment of $1.5 million.  The Company expects to buy down the NSR in August 2018.

NPV figures calculated on an after-tax basis factor in a 25% corporate income tax rate and 10% Ontario Mining Tax rate.

NPV and IRR Summary

  Unit Gold Price Sensitivities
US$1,150/oz PEA Pricing US$1,350/oz
Macro Parameters        
Gold Price US$/oz $ 1,150   $ 1,250   $ 1,350  
Exchange Rate CAD:USD   0.80     0.80     0.80  
Pre-Tax NPV and IRR        
NPV @ 5% M C$ $ 263   $ 344   $ 425  
IRR  %   40 %   50 %   60 %
Post-Tax NPV and IRR        
NPV @ 5% M C$ $ 189   $ 244   $ 299  
IRR  %   34 %   42 %   50 %

QA/QC Statement
The Company has implemented a quality assurance and control (“QA/QC”) program to ensure sampling and analysis of mine and exploration work is conducted in accordance with industry standards. Drill core is sawn in half with one half of the core shipped to Actlabs Laboratories located in Thunder Bay, ON, while the other half is retained at the Company’s core facilities in White River, ON, for future verification. Certified reference standards and blanks are inserted into the sample stream on a regular interval basis and monitored as part of the QA/QC program. Gold analysis is performed by fire assay using atomic absorption, gravimetric or pulp metallic finish.  The Mineral Resource Estimate was prepared in compliance with NI 43-101 guidelines. 

Qualified Persons and NI 43-101 Disclosure
Robert Kusins, P. Geo., Harte Gold’s Senior Mineral Resource geologist, is the Company’s Qualified Person and has prepared, supervised the preparation, or approved the scientific and technical disclosure in this news release.

Independent Qualified Person, Eugene Puritch, P.Eng., FEC, CET of P&E Mining Consultants Inc. has reviewed and approved the technical contents of this news release.

The PEA is preliminary in nature and includes Inferred Mineral Resources that are too speculative geologically to have economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty that PEA results will be realized. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

About Harte Gold Corp.
Harte Gold Corp. is focused on the exploration and development of its 100% owned Sugar Zone Property where it has recently completed a 70,000 tonne Advanced Exploration Bulk Sample at the Sugar Zone Deposit and mined 30,000 tonnes under its Phase I Commercial Production Permit. The Sugar Zone Property is located 80 kilometres east of the Hemlo Gold Camp. Using a 3 g/t Au cut-off, the Mineral Resource Estimate dated February 15, 2018 contains an Indicated Mineral Resource Estimate of 2,607,000 tonnes grading 8.52 g/t Au for 714,200 ounces of contained gold and an Inferred Mineral Resource Estimate of 3,590,000 tonnes, grading 6.59 g/t Au for 760,800 ounces of contained gold. Harte Gold also holds the Stoughton-Abitibi property located on the Destor-Porcupine Fault Zone, east of Timmins, Ontario, and adjacent to the Holloway Gold Mine.

For further information, please contact:

Stephen G. Roman
President and CEO
Tel: 416-368-0999
Email: sgr@hartegold.com
Shawn Howarth
Vice President, Corporate Development 
Tel: 416-368-0999
E-mail: sh@hartegold.com
                                                         

This presentation contains forward-looking information under Canadian securities legislation. Forward-looking information includes, but is not limited to, statements with respect to completion of any financings; Harte Gold’s development potential and timetable of its operating, development and exploration assets; Harte Gold’s ability to raise additional funds necessary; the future price of gold; the estimation of mineral reserves and mineral resources; conclusions of economic evaluation; the realization of mineral reserve estimates; the timing and amount of estimated future production, development and exploration; costs of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; currency exchange rates; government regulation of mining operations; and environmental and permitting risks. Generally, forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". All information contained in this news release, other than statements of current and historical fact, is forward looking information. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Harte Gold to be materially different from those expressed or implied by such forward-looking statements, including but not limited to those risks described in the annual information form of Harte Gold and in its public documents filed on SEDAR from time to time.

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made. Although management of Harte Gold has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Harte Gold does not undertake to update any forward-looking statements, except in accordance with applicable securities laws. Readers should also review the risks and uncertainties sections of Harte Gold’s annual and interim MD&As.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

Longitudinal Projection Showing Mineral Resource Classification At The Sugar and Middle Zones
Legend: Yellow = Indicated Mineral Resources, Grey = Inferred Mineral Resources. Scale in metres.


Longitudinal Projection Illustrating Gold Grade Contours, Infill Drill Results And Future Mine Development
Longitudinal Projection Illustrating Gold Grade Contours, Infill Drill Results And Future Mine Development


Mine Design – Grade Distribution
Mine Design – Grade Distribution


Throughput and Diluted Head Grade
Throughput and Diluted Head Grade


Annual Gold Production Over LOM
Annual Gold Production Over LOM


Primary Logo

Tags:


Get the latest news and updates from Stockhouse on social media

Follow STOCKHOUSE Today