PolyMet Project Update at Shareholders' Meeting
PolyMet Mining Corp. (“PolyMet” or the “company”) TSX: POM; NYSE AMERICAN: PLM – is pleased to report 78.51 percent of the
eligible shares were represented at its Annual General and Special Meeting of Shareholders held on June 27, 2018 in Toronto,
Ontario, and all motions put forward by the company were passed at the meeting.
The number of directors of the company was fixed at nine and the following persons were elected as directors of the company to
hold office until the next annual general meeting. The voting results are shown below:
|
|
|
|
|
|
|
|
|
|
|
|
|
Director |
|
|
Votes For |
|
|
% For |
|
|
Votes |
|
|
% |
|
|
|
|
|
|
|
|
|
Withheld |
|
|
Withheld |
Dennis Bartlett |
|
|
140,878,560 |
|
|
99.06 |
|
|
1,331,408 |
|
|
0.93 |
Jonathan Cherry |
|
|
140,910,636 |
|
|
99.08 |
|
|
1,299,332 |
|
|
0.91 |
Mike Ciricillo |
|
|
140,127,914 |
|
|
98.53 |
|
|
2,082,054 |
|
|
1.46 |
Dr. David Dreisinger |
|
|
141,265,096 |
|
|
99.33 |
|
|
944,872 |
|
|
0.66 |
W. Ian L. Forrest |
|
|
141,235,838 |
|
|
99.31 |
|
|
974,130 |
|
|
0.68 |
Helen Harper |
|
|
140,157,856 |
|
|
98.55 |
|
|
2,052,112 |
|
|
1.44 |
Alan R. Hodnik |
|
|
141,381,755 |
|
|
99.41 |
|
|
828,213 |
|
|
0.58 |
Stephen Rowland |
|
|
140,175,103 |
|
|
98.56 |
|
|
2,034,865 |
|
|
1.43 |
Michael M. Sill |
|
|
140,668,142 |
|
|
98.91 |
|
|
1,541,826 |
|
|
1.08 |
|
|
|
|
|
|
|
|
|
|
|
|
|
In other board action, PricewaterhouseCoopers LLP was reappointed as auditors of the company and the board is authorized to fix
the remuneration to be paid to the auditors. The amended Omnibus Share Compensation Plan, as approved by shareholders in 2007,
amended and restated and confirmed from time to time, most recently by shareholders in 2015, was also approved.
Following the meeting, President and CEO Jon Cherry gave a presentation on achievements of the past year and goals for the
future.
Key highlights:
- In January 2018, the Minnesota Department of Natural Resources released the draft Permit to Mine for
public review and comment which has now closed;
- In January 2018, the Minnesota Pollution Control Agency released the draft water quality permit,
draft section 401 water quality certification, and draft air emissions permit for public review and comment which have all
closed;
- In March 2018, all remaining public comment periods for the various draft permits concluded without
extension;
- In March 2018, the company and Glencore agreed to extend the term of outstanding debentures until
March 31, 2019, reduce the interest rate on the outstanding debentures, and make available up to $80 million in additional
debentures during 2018 of which $20 million was drawn on May 7, 2018. Proceeds are being used to complete pre- and
post-permitting work, including detailed engineering and environmental cleanup, and to purchase wetland credits;
- In March 2018, the company issued an Updated Technical Report under NI 43-101 incorporating process
improvements, project improvements, and environmental controls described in the Final Environmental Impact Statement and draft
permits. The update also included detailed capital costs, operating costs, and economic valuation for the mine plan being
permitted as well as potential future production opportunities;
- In early June 2018, the U.S. Forest Service notified the company that the administrative land
exchange between the agency and PolyMet Mining would close June 28, 2018, giving the company exclusive control of the land over
the NorthMet ore body; and,
- In June 2018, the U.S. Senate passed on an 85-10 vote the National Defense Authorization Act, which
carried an amendment codifying the Superior National Forest Record of Decision in January 2017 authorizing the administrative
land exchange. The land exchange measure passed out of the House of Representatives on a 309-99 vote in November 2017 as a
stand-alone bill.
Key objectives include:
- Favorable decisions on the final state permits named above as well as from the U.S. Army Corps of
Engineers on the Final Record of Decision and 404 wetlands permit under the Clean Water Act. Note that the permitting process is
managed by the regulatory agencies and, therefore, timelines are not under our control;
- Transfer of title to the surface rights over and around the NorthMet mineral rights to PolyMet as
part of the authorized administrative land exchange. This is scheduled June 28, 2018;
- Completion of project implementation plan; and,
- Execution of a construction finance plan, subject to typical conditions precedent such as receipt of
key permits.
About PolyMet
PolyMet Mining Corp. (www.polymetmining.com) is a publicly-traded mine development company that owns 100 percent of Poly Met Mining,
Inc., a Minnesota corporation that controls 100 percent of the NorthMet copper-nickel-precious metals ore body through a long-term
lease and owns 100 percent of the Erie Plant, a large processing facility located approximately six miles from the ore body in the
established mining district of the Mesabi Iron Range in northeastern Minnesota. Poly Met Mining, Inc. has completed its Definitive
Feasibility Study. The NorthMet Final EIS was published in November 2015, preparing the way for decisions on permit applications.
NorthMet is expected to require approximately two million hours of construction labor, creating approximately 360 long-term jobs, a
level of activity that will have a significant multiplier effect in the local economy.
PolyMet Disclosures
This news release contains certain forward-looking statements concerning anticipated developments in PolyMet’s operations in
the future. Forward-looking statements are frequently, but not always, identified by words such as “expects,” “anticipates,”
“believes,” “intends,” “estimates,” “potential,” “possible,” “projects,” “plans,” and similar expressions, or statements that
events, conditions or results “will,” “may,” “could,” or “should” occur or be achieved or their negatives or other comparable
words. These forward-looking statements may include statements regarding the ability to receive environmental and operating
permits, job creation, and the effect on the local economy, or other statements that are not a statement of fact. Forward-looking
statements address future events and conditions and therefore involve inherent known and unknown risks and uncertainties. Actual
results may differ materially from those in the forward-looking statements due to risks facing PolyMet or due to actual facts
differing from the assumptions underlying its predictions.
PolyMet’s forward-looking statements are based on the beliefs, expectations and opinions of management on the date the
statements are made, and PolyMet does not assume any obligation to update forward-looking statements if circumstances or
management’s beliefs, expectations and opinions should change.
Specific reference is made to risk factors and other considerations underlying forward-looking statements discussed in
PolyMet’s most recent Annual Report on Form 40-F for the fiscal year ended December 31, 2017, and in our other filings with
Canadian securities authorities and the U.S. Securities and Exchange Commission.
The Annual Report on Form 40-F also contains the company’s mineral resource and other data as required under National
Instrument 43-101.
The TSX has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.
Click here to subscribe to Mobile Alerts for PolyMet Mining Corp.
PolyMet Mining Corp.
Media
Bruce Richardson, +1-651-389-4111
Corporate Communications
brichardson@polymetmining.com
or