TORONTO, July 09, 2018 (GLOBE NEWSWIRE) -- Sandy Lake Gold Inc. (the”Company” or “SLG”) (TSX-V:SLAU) is pleased
to announce a partial award in the Arbitration Proceedings with Treasury Metals Inc. (TSX:TML) formerly Goldeye Explorations
Limited (“Goldeye”) (see Treasury Metals press release dated July 11, 2016 available at SEDAR.com).
The case centred on an option agreement between the Companies signed on April 15, 2015, on the Weebigee Project, in the Sandy
Lake district located 220 kilometers north of Red Lake, Ontario.
The Arbitral Tribunal has ruled in favour of Sandy Lake Gold Inc. on all substantive issues.
The two main issues were the amount of first year expenditures and whether Treasury Metals Inc. exercised an option to
participate as a 50% joint venture with the Company in the ownership a of a large group of claims staked around the original
Weebigee project in 2015. Treasury Metals Inc., which initiated the proceedings, had alleged that SLG had failed
to incur minimum first year expenditures of $500,000.00 on the Weebigee property as required by the May 2015 option agreement. The
Arbitral Tribunal panel ruled that in fact SLG had incurred expenditures of $1,292,130.06. in the first year.
Significantly, the Tribunal also ruled that Treasury Metals Inc. failed to fulfill the conditions for participating as a joint
venturer in the surrounding mineral claim land package of approximately 80,000 acres (2,210 claim units), and that Treasury Metals
Inc. has no ownership or any other rights over or interests in these claims.
The counterclaim of Sandy Lake Gold Inc. against Treasury Metals Inc. is pending before the Arbitral Panel and has not yet been
determined.
PROJECT UPDATE
Sandy Lake Gold Inc. currently controls approximately 104,000 acres of contiguous mineral claim holdings in the Sandy Lake
Greenstone Belt. In 2014, a limited drill program in the western part of the claim package returned high grade gold intercepts of
12.86 Au g/t over 6.85 meters and 12.17 Au g/t over 6.2 meters. (Goldeye press release April 9, 2014 available at SEDAR.com).
The Company has recently completed a VTEM airborne and ground geophysics surveys over the Phase 1 target areas. In February 2018
the Company signed a 5,000 meter drill contract and has mobilized all necessary equipment for the project. The Company is currently
negotiating an Exploration Agreement with the First Nation communities, whose Traditional Territories encompass the project.
Sandy Lake Gold Inc. looks forward to advancing the exploration and development of this emerging gold district in partnership
with the First Nations.
All scientific and technical information in this press release has been prepared under the supervision of Dan Noone, (Interim
CEO and a Director of Sandy Lake Gold), a “qualified person” within the meaning of National Instrument 43-101. Mr. Noone (B.Sc
Geology, MBA) is a member of the Australian Institute of Geoscientists.
For further information please contact:
Dan Noone
Interim Chief Executive Officer and Executive Director
(416) 628-5904
Email: info@sandylakegold.com
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy and / or accuracy of this release.
Forward Looking Statements – Certain information set forth in this news release may contain forward-looking statements that
involve substantial known and unknown risks and uncertainties. These forward-looking statements are subject to numerous risks and
uncertainties, certain of which are beyond the control of Sandy Lake, including, but not limited to the effect of any future
discussions with local First Nations, the length of time for which the event of force majeure in respect of the Weebigee Project
may continue, the nature of any resolution to the matters giving rise to such event of force majeure (if any such resolution is
reached at all), the impact of general economic conditions, industry conditions, volatility of commodity prices, currency
fluctuations, and exploration risk. Readers are cautioned that the assumptions used in the preparation of such information,
although considered reasonable at the time of preparation, may prove to be imprecise and, as such, undue reliance should not be
placed on forward-looking statements.