VANCOUVER, Oct. 11, 2018 /CNW/ - SSR Mining Inc. (NASDAQ: SSRM)
(TSX: SSRM) ("SSR Mining") reports third quarter 2018 operating results at our three mines.
Third Quarter 2018 Operating Highlights
- Record material movement at Marigold: Moved a record 21.3 million tonnes of material, a 33% increase compared to the
second quarter.
- Strong production at Marigold: Produced 58,459 ounces of gold, an 18% increase compared to the second quarter.
- Record production at Seabee: Produced 27,831 ounces of gold from a higher ore feed grade of 9.52 g/t gold,
representing quarterly increases of 18% and 20%, respectively.
- Continued positive performance at Puna Operations: Produced 0.7 million ounces of silver, more than doubled zinc
production to 3.2 million pounds, and successfully test processed Chinchillas ore.
Paul Benson, President and CEO said, "We delivered our strongest quarter of the year with
consolidated gold equivalent production of nearly 95,000 ounces, breaking records at Marigold and Seabee while continuing to
optimize production and advancing the Chinchillas project at Puna Operations. With all three operations performing well, we
look forward to meeting or exceeding annual guidance for the seventh consecutive year."
Marigold Mine, U.S.
|
|
Q3 2018
|
Q2 2018
|
% Change (1)
|
Total material mined
|
kt
|
21,284
|
15,958
|
33.4%
|
Waste removed
|
kt
|
14,411
|
8,083
|
78.3%
|
Ore to leach pad
|
kt
|
6,873
|
7,875
|
(12.7%)
|
Strip ratio
|
w/o
|
2.1
|
1.0
|
110.0%
|
Gold grade to leach pad
|
g/t
|
0.32
|
0.42
|
(23.8%)
|
Gold recovery
|
%
|
72.3%
|
74.4%
|
(2.8%)
|
Gold produced
|
oz
|
58,459
|
49,436
|
18.3%
|
Gold sold
|
oz
|
59,612
|
46,644
|
27.8%
|
Notes:
|
(1)
|
Percent changes are calculated using rounded numbers presented in the
table.
|
In the third quarter of 2018, the Marigold mine produced 58,459 ounces of gold, an 18% quarterly increase, benefitting from
the record ore tonnes stacked in the second quarter. Gold sales totaled 59,612 ounces for the quarter due to strong
production and a decrease in bullion inventory.
During the quarter, a record 21.3 million tonnes of material were mined, a 33% increase compared to the second quarter, due to
four additional haul trucks entering service during the quarter, shorter haul distances and improved equipment
availabilities.
Approximately 6.9 million tonnes of ore were delivered to the heap leach pads, at a gold grade of 0.32 g/t. This compares to
7.9 million tonnes of ore delivered to the heap leach pads at a gold grade of 0.42 g/t in the second quarter of 2018. The
strip ratio was 2.1:1 for the quarter.
Seabee Gold Operation, Canada
|
|
Q3 2018
|
Q2 2018
|
% Change (1)
|
Total ore milled
|
t
|
88,273
|
84,010
|
5.1%
|
Ore milled per day
|
t/day
|
959
|
923
|
3.9%
|
Gold mill feed grade
|
g/t
|
9.52
|
7.95
|
19.7%
|
Gold recovery
|
%
|
97.1%
|
97.3%
|
(0.2%)
|
Gold produced
|
oz
|
27,831
|
23,582
|
18.0%
|
Gold sold (2)
|
oz
|
29,175
|
20,512
|
42.2%
|
Notes:
|
(1)
|
Percent changes are calculated using rounded numbers presented in the
table.
|
(2)
|
Beginning with the first quarter of 2018, the holder of a 3% net smelter
returns royalty elected to receive its royalty in-kind and we will no longer report these ounces within gold
sold.
|
Seabee Gold Operation produced a record 27,831 ounces of gold in the third quarter, a quarterly increase of 18%, driven by
higher average mill feed grade and increased mill throughput. Gold sales in the quarter were 29,175 ounces, 42% higher than
the second quarter.
The mill achieved an average throughput of 959 tonnes per day, a 4% quarterly increase reflecting a higher mining rate at the
Santoy mine. Gold recovery for the quarter remained consistent at 97.1%.
Puna Operations, Argentina (1)
|
|
Q3 2018
|
Q2 2018
|
% Change (5)
|
Ore milled
|
kt
|
308
|
396
|
(22.2%)
|
Silver mill feed grade
|
g/t
|
96
|
110
|
(12.7%)
|
Zinc mill feed grade (2)
|
%
|
1.25%
|
0.71%
|
76.1%
|
Silver recovery
|
%
|
69.9%
|
68.1%
|
2.6%
|
Zinc recovery (2)
|
%
|
38.1%
|
31.5%
|
21.0%
|
Silver produced
|
koz
|
666
|
954
|
(30.2%)
|
Silver produced (attributable) (4)
|
koz
|
500
|
716
|
(30.2%)
|
Lead produced (3)
|
klbs
|
372
|
-
|
NA
|
Lead produced (attributable) (3) (4)
|
klbs
|
279
|
-
|
NA
|
Zinc produced (2)
|
klbs
|
3,241
|
1,521
|
113.1%
|
Zinc produced (attributable) (2) (4)
|
klbs
|
2,431
|
1,141
|
113.1%
|
Silver sold
|
koz
|
623
|
1,142
|
(45.4%)
|
Silver sold (attributable) (4)
|
koz
|
467
|
857
|
(45.5%)
|
Zinc sold (2)
|
klbs
|
383
|
-
|
NA
|
Zinc sold (attributable) (2) (4)
|
klbs
|
287
|
-
|
NA
|
Notes:
|
(1)
|
Figures are on 100% basis unless otherwise noted.
|
(2)
|
Data for zinc recovery, production and sales relate only to zinc in zinc
concentrate.
|
(3)
|
Data for lead production relates only to lead in lead-silver
concentrate. "NA" indicates data not applicable due to no comparable data available in Q2
2018.
|
(4)
|
Figures are on a 75% attributable basis.
|
(5)
|
Percent changes are calculated using rounded numbers presented in the
table. "NA" indicates data not applicable due to no comparable data available in Q2 2018.
|
During the third quarter of 2018, Puna Operations produced 0.7 million ounces of silver and 3.2 million pounds of zinc,
reflecting a shift to processing of stockpiles with higher zinc content. Silver sales were 0.6 million ounces for the
quarter, marginally lower than production. We re-commenced zinc concentrate sales during the third quarter, selling 0.4
million pounds with a ramp-up in zinc sales anticipated through the fourth quarter.
Ore was milled at an average rate of 3,348 tonnes per day in the third quarter, 23% below the second quarter, due to planned
major mill maintenance occurring in July and test processing of Chinchillas ore. Ore milled in the third quarter contained
an average silver grade of 96 g/t, 13% lower than the 110 g/t average silver grade in the second quarter, consistent with
processing of increasingly lower grade stockpiles. The average silver recovery in the third quarter was 70%, a 3%
improvement compared to the previous quarter.
Pre-stripping activities at the Chinchillas site continued to advance during the quarter. Approximately 2.1 million tonnes of
waste and 0.3 million tonnes of ore were mined, with ore grades reconciling well to the geological model. Approximately
73,000 tonnes of ore from the Chinchillas pit were delivered to the Pirquitas site, of which approximately 39,000 tonnes were
processed in two separate test runs as part of the project execution. The tests successfully validated metallurgical
performance of the ore and produced saleable lead-silver and zinc concentrates. Data related to pre-commercial processing
of ore from the Chinchillas site is included in the table above.
Qualified Persons
The scientific and technical data contained in this news release relating to the Marigold mine has been reviewed and approved
by James Frost, PE, a qualified person under National Instrument 43-101 – Standards of Disclosure for Mineral Projects
("NI 43-101") and our Technical Services Superintendent at the Marigold mine. The scientific and technical data contained in this
news release relating to the Seabee Gold Operation has been reviewed and approved by Cameron
Chapman, P.Eng., a qualified person under NI 43-101 and General Manager at the Seabee Gold Operation. The scientific and
technical data contained in this news release relating to Puna Operations has been reviewed and approved by Bruce Butcher, P.Eng., a qualified person under NI 43-101 and our Director, Mine
Planning.
About SSR Mining
SSR Mining Inc. is a Canadian-based precious metals producer with three operations, including the Marigold gold mine in
Nevada, U.S., the Seabee Gold Operation in Saskatchewan, Canada
and the 75% owned and operated Puna Operations joint venture in Jujuy Province, Argentina. We
also have two feasibility stage projects and a portfolio of exploration properties in North and South
America. We are committed to delivering safe production through relentless emphasis on Operational Excellence. We are also
focused on growing production and Mineral Reserves through the exploration and acquisition of assets for accretive growth, while
maintaining financial strength.
For further information contact:
W. John DeCooman, Jr.
Vice President, Business Development and Strategy
SSR Mining Inc.
Vancouver, BC
Toll free: +1 (888) 338-0046
All others: +1 (604) 689-3846
E-Mail: invest@ssrmining.com
To receive SSR Mining's news releases by e-mail, please register using the SSR Mining website at www.ssrmining.com.
Cautionary Note Regarding Forward-Looking Statements
This news release contains forward-looking information within the meaning of Canadian securities laws and forward-looking
statements within the meaning of the U.S. Private Securities Litigation Reform Act of 1995 (collectively, "forward-looking
statements") concerning the anticipated developments in our operations in future periods, and other events or conditions that may
occur or exist in the future. All statements, other than statements of historical fact, are forward-looking statements.
Generally, forward-looking statements can be identified by the use of words or phrases such as "expects," "anticipates,"
"plans," "projects," "estimates," "assumes," "intends," "strategy," "goals," "objectives," "potential," "believes," or variations
thereof, or stating that certain actions, events or results "may," "could," "would," "might" or "will" be taken, occur or be
achieved, or the negative of any of these terms or similar expressions. The forward-looking statements in this news release
relate to, among other things: future production of gold, silver and other metals; the prices of gold, silver and other metals;
the effects of laws, regulations and government policies affecting our operations or potential future operations; future
successful development of our projects; the sufficiency of our current working capital, anticipated operating cash flow or our
ability to raise necessary funds; estimated production rates for gold, silver and other metals produced by us; timing of
production at the Marigold mine, the Seabee Gold Operation and Puna Operations; timing of our exploration and development
programs; the ramp up in zinc sales at Puna Operations anticipated through the fourth quarter of 2018; the successful testing of
processed ore at Chinchillas; ongoing or future development plans and capital replacement, improvement or remediation programs;
the estimates of expected or anticipated economic returns from our mining projects, including future sales of metals, concentrate
or other products produced by us; our ability to achieve our production guidance; and our plans and expectations for our
properties and operations.
These forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that
could cause actual events or results to differ from those expressed or implied, including, without limitation, the following:
uncertainty of production, development plans and cost estimates for the Marigold mine, the Seabee Gold Operation, Puna
Operations and our projects; our ability to replace Mineral Reserves; commodity price fluctuations; political or economic
instability and unexpected regulatory changes; currency fluctuations; the possibility of future losses; general economic
conditions; counterparty and market risks related to the sale of our concentrate and metals; uncertainty in the accuracy of
Mineral Reserves and Mineral Resources estimates and in our ability to extract mineralization profitably; differences in U.S. and
Canadian practices for reporting Mineral Reserves and Mineral Resources; lack of suitable infrastructure or damage to existing
infrastructure; future development risks, including start-up delays and cost overruns; our ability to obtain adequate financing
for further exploration and development programs and opportunities; uncertainty in acquiring additional commercially mineable
mineral rights; delays in obtaining or failure to obtain governmental permits, or non-compliance with our permits; our ability to
attract and retain qualified personnel and management; the impact of governmental regulations, including health, safety and
environmental regulations, including increased costs and restrictions on operations due to compliance with such regulations;
unpredictable risks and hazards related to the development and operation of a mine or mineral property that are beyond our
control; reclamation and closure requirements for our mineral properties; potential labour unrest, including labour actions by
our unionized employees at Puna Operations; indigenous peoples' title claims and rights to consultation and accommodation may
affect our existing operations as well as development projects and future acquisitions; certain transportation risks that could
have a negative impact on our ability to operate; assessments by taxation authorities in multiple jurisdictions; recoverability
of value added tax and significant delays in the collection process in Argentina; claims and
legal proceedings, including adverse rulings in litigation against us and/or our directors or officers; compliance with
anti-corruption laws and internal controls, and increased regulatory compliance costs; complying with emerging climate change
regulations and the impact of climate change; fully realizing our interest in deferred consideration received in connection with
recent divestitures; fully realizing the value of our shareholdings in our marketable securities, due to changes in price,
liquidity or disposal cost of such marketable securities; uncertainties related to title to our mineral properties and the
ability to obtain surface rights; the sufficiency of our insurance coverage; civil disobedience in the countries where our
mineral properties are located; operational safety and security risks; actions required to be taken by us under human rights law;
competition in the mining industry for mineral properties; our ability to complete and successfully integrate an announced
acquisition; reputation loss resulting in decreased investor confidence, increased challenges in developing and maintaining
community relations and an impediment to our overall ability to advance our projects; risks normally associated with the conduct
of joint ventures; an event of default under our convertible notes may significantly reduce our liquidity and adversely affect
our business; failure to meet covenants under our senior secured revolving credit facility; information systems security threats;
conflicts of interest that could arise from certain of our directors' and officers' involvement with other natural resource
companies; other risks related to our common shares; and those other various risks and uncertainties identified under the heading
"Risk Factors" in our most recent Annual Information Form filed with the Canadian securities regulatory authorities and included
in our most recent Annual Report on Form 40-F filed with the U.S. Securities and Exchange Commission.
This list is not exhaustive of the factors that may affect any of our forward-looking statements. Our forward-looking
statements are based on what our management currently considers to be reasonable assumptions, beliefs, expectations and opinions
based on the information currently available to it. Assumptions have been made regarding, among other things, our ability to
carry on our exploration and development activities, our ability to meet our obligations under our property agreements, the
timing and results of drilling programs, the discovery of Mineral Resources and Mineral Reserves on our mineral properties, the
timely receipt of required approvals and permits, including those approvals and permits required for successful project
permitting, construction and operation of our projects, the price of the minerals we produce, the costs of operating and
exploration expenditures, our ability to operate in a safe, efficient and effective manner, our ability to obtain financing as
and when required and on reasonable terms, our ability to continue operating the Marigold mine, the Seabee Gold Operation and
Puna Operations, dilution and mining recovery assumptions, assumptions regarding stockpiles, the success of mining, processing,
exploration and development activities, the accuracy of geological, mining and metallurgical estimates, no significant
unanticipated operational or technical difficulties, maintaining good relations with the communities surrounding the Marigold
mine, the Seabee Gold Operation and Puna Operations, no significant events or changes relating to regulatory, environmental,
health and safety matters, certain tax matters and no significant and continuing adverse changes in general economic conditions
or conditions in the financial markets (including commodity prices, foreign exchange rates and inflation rates). You are
cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. We cannot assure you
that actual events, performance or results will be consistent with these forward-looking statements, and management's assumptions
may prove to be incorrect. Our forward-looking statements reflect current expectations regarding future events and operating
performance and speak only as of the date hereof and we do not assume any obligation to update forward-looking statements if
circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. For the
reasons set forth above, you should not place undue reliance on forward-looking statements.
View original content:http://www.prnewswire.com/news-releases/ssr-mining-reports-third-quarter-2018-production-results-300729908.html
SOURCE SSR Mining Inc.