MONTRÉAL, March 18, 2019 /PRNewswire/ - On March 15, 2019, a
consortium which Boralex Inc. ("Boralex" or the "Corporation") (TSX: BLX) is part of submitted a bid to the French state in the
Dunkirk Offshore Wind Farm tender. Boralex has determined, after a careful review amid changes in tender's
competitive conditions and risk profile, that its interest in the consortium no longer satisfies its investment
criteria.
Through the Joint Venture Agreement entered into with the other members of the consortium, Boralex has an option to sell its
participation in the project to its current partners. Therefore, Boralex will exercise its option to sell its interest to the
other members of the consortium immediately after the tender being definitively awarded and once it is able to in accordance with
the terms of the option and in compliance with the tender and French state rules and the agreements governing the consortium.
Boralex will remain a party to the consortium until it has sold its interest in the project to the other members of the
consortium pursuant to the option. However, Boralex will continue to assist in the development of the project, both as a member
of the consortium and thereafter as a non-member. Accordingly, the consortium continues to strongly believe in the prospects and
the success of this bid for this very important project for the French Energy Transition.
Moulins du Lohan
On March 5th, Boralex received with satisfaction the decision made by the Administrative Court
of Appeal of Nantes in line with the conclusions of the Public Rapporteur concerning a project
that was interrupted in June 2017. The Moulins du Lohan project is the result of 10 years of
development efforts.
This is an important decision that confirms a truly exemplary project for the territory in terms of environment, energy and
social benefit. It is also an important decision for our entire sector in terms of legal security for investments. We will work
with our various partners in preparing to restart the work. Boralex will continue to respect its commitments for building and
operating the wind farm in the Lanouée forest, which will retain its distinct identity and uses. It is to be noted that the
counterpart could file an appeal in cassation to the Council of State. It has two months following the decision to do so. At this
stage, the Council of State considers the grounds for the decision of the Administrative Court of Appeal but does not re-examine
all the facts.
As expressed recently on March 1st 2019 while releasing our year-end results, Boralex
has a portfolio of potential projects at various stages of development totalling over 1,000 MW in France. In light of its long-term presence and deep knowledge of the French market, the Corporation has
numerous strengths to capitalize on the favourable environment in developing renewable energy, particularly wind power. The
Corporation will actively participate in the tendering system, under which an installed capacity of 3,400 MW in onshore wind
power will be awarded under 20-year contracts by the end of 2020.
About Boralex
Boralex develops, builds and operates renewable energy power facilities in Canada,
France, the United Kingdom and the
United States. A leader in the Canadian market and France's largest independent producer
of onshore wind power, the Corporation is recognized for its solid experience in optimizing its asset base in four power
generation types — wind, hydroelectric, thermal and solar. Boralex ensures sustained growth by leveraging the expertise and
diversification developed over the past 25 years. Boralex's shares and convertible debentures are listed on the Toronto Stock
Exchange under the ticker symbols BLX and BLX.DB.A, respectively. More information is available at www.boralex.com or www.sedar.com. Follow us on Facebook, LinkedIn and