VANCOUVER, March 28, 2019 /PRNewswire/ - Alexco
Resource Corp. (NYSE American: AXU, TSX: AXR) ("Alexco" or the "Corporation") is pleased to announce the results of an
independent pre-feasibility study ("PFS") on its 100% owned Keno Hill Silver project ("Keno Hill" or the "Project") in
Yukon, Canada.
Highlights of the PFS:
Note that all dollar amounts referenced herein are in Canadian dollars ("CAD") unless indicated otherwise.
- Project pre-tax and after-tax net present value ("NPV") is $136.4 million ("M") and
$101.3 M (5% discount rate), respectively, and pre-tax and after-tax internal rate of return
("IRR") is 84% and 74%, respectively, at an assumed average life of mine ("LOM") silver ("Ag") price of US$17.90 per ounce ("oz").
- At current spot metal prices 1 and USD/CAD foreign exchange rate, the project has a pre-tax and after-tax NPV of
$101.7 M and $79.9 M (5% discount rate), respectively, and a
pre-tax and after-tax IRR of 63% and 57%, respectively.
- LOM average annualized mine production is projected to be 154,000 tonnes ("t") per year over an approximately eight (8)
year project life at an average feed grade of 804 grams per tonne ("g/t") Ag, 2.98% lead ("Pb"), 4.13% zinc ("Zn") and 0.34 g/t
gold ("Au").
- Total payable metals in concentrate are approximately 27.2 M oz of Ag, 67.2 M pounds ("lbs") of Zn, 65.4 M lbs of Pb over an eight (8) year mine life.
Average annualized contained silver in concentrate is 4.0 M oz per year, based on full production
years.
- Initial capital costs are estimated to be $23.2 M comprised of $17.9
M of surface and underground development costs to reach mill commissioning plus an additional $5.3 M of net working capital for two (2) months of mill operations ramp-up prior to positive cash flow.
- Total sustaining capital (including underground development and property, plant and equipment ("PP&E")) is estimated to
be $76.5 M, which excludes the initial capital of $23.2 M. Direct
operating costs of $321/t of ore are estimated over the LOM.
- Upon achieving commercial production, Alexco has calculated all-in sustaining costs ("AISC") (contained Ag, by-product
basis) over the LOM to be US$11.98/oz of Ag. At current spot prices1 over the LOM, the
calculated AISC is US$10.86/oz of Ag.
|
Footnote:
|
1.
|
Current spot prices are calculated as of March 22, 2019 using the
following assumptions: Ag US$15.46/oz, Au US$1311.30/oz, Pb US$0.9187/lb, Zn US$ 1.2961/lb and USD/CAD exchange rate of
$0.75.
|
Alexco Chairman and CEO, Clynton Nauman, commented, "The results of the PFS reflect the
exceptional asset we have in Keno Hill and demonstrate a robust high margin primary silver operation that can produce
approximately four million ounces of silver per year. The operational and economic metrics of the PFS show an improvement over
the previous preliminary economic assessment ("PEA") in nearly all categories including a higher NPV, increased annual silver
production, reduced capital requirements, improved operating costs and productivities, increased mine tonnage and throughput,
lower LOM AISC and an impressive IRR. With the results of the PFS now in hand, we are now on a clear path to production at
Keno Hill."
Pre-Feasibility Study
The PFS includes existing mineral resource estimates for the Flame & Moth, Bellekeno, Lucky Queen and Onek deposits, and an updated resource estimate for the Bermingham deposit. In addition, mineral reserve
estimates are provided for assessment of underground mining operations for all of the deposits with the exception of the
Onek deposit. The PFS was compiled by Mining Plus Canada Consulting Ltd. ("Mining Plus") with
contributions from a team of qualified persons and firms. The PFS assesses underground mining operations in all four (4)
deposits, with two deposits in concurrent production at all times, feeding an existing conventional flotation mill to produce
mineral concentrates containing silver, lead, zinc and gold.
* See "Cautionary Note to Investors regarding Mineral Reserve and Resource Estimates" below.
Key PFS metrics (and assumptions) are as follows:
Production Profile
|
Total Tonnes Mined/Milled
|
1,177,379 t
|
LOM Diluted Mill Feed Grades
|
804 g/t Ag, 2.98% Pb, 4.13% Zn
|
Total Payable Silver in Concentrate
|
27.2 M oz
|
Current Project Life
|
8 years
|
Metallurgical Recoveries
|
95.6% Ag, 88.6% Pb, 73.6% Zn
|
LOM Average Mill Throughput
|
430 tonnes per day ("tpd")
|
Annualized Silver in Concentrate 1
|
4.0 M oz/yr
|
LOM Net Smelter Return ("NSR")
|
$554/t
|
LOM AISC
|
US$11.98
|
Capital Requirements
|
Pre-Production/Development Capital Cost
|
$17.9 M
|
Working Capital Ramp-Up
|
$5.3M
|
LOM Sustaining Capital 2
|
$76.5 M
|
Operating Costs
|
Underground Mining Direct
|
$201/t
|
Milling
|
$61/t
|
G&A
|
$59/t
|
Total Direct Operating Cost
|
$321/t
|
LOM Sustaining Capital 2
|
$68/t
|
Economics
|
|
Pre-Tax
|
After-Tax
|
Cash Flow
|
$174.1M
|
$129.4M
|
NPV (5%)
|
$136.4M
|
$101.3M
|
IRR
|
83.7%
|
74.2%
|
Payback Period 2
|
26 months
|
27 months
|
Notes:
|
1.
|
Based only on full production years
|
2.
|
Calculated after initial capital costs are incurred
|
The economic parameters are based on a metal price forecast with the following assumptions: US$15.75/oz Ag in Year 1, increasing to US$18.25/oz in Year 4 and long-term;
US$0.96/lb lead in Year 1, increasing to US$1.00/lb long-term;
US$1.25/lb zinc in Year 1, decreasing to US$1.22/lb long-term; and
USD/CAD foreign exchange of US$0.75 in Year 1, increasing to US$0.77
long-term.
Alexco President, Brad Thrall, commented, "The results reflected in this PFS include an
optimized mine plan for Flame & Moth with increased tonnes and reduced development relative to the previous PEA. Similarly,
at Bermingham we have a 65% or 142,000 tonne increase to the mine plan primarily as a result of 2018 exploration success at this
deposit. Furthermore, the silver production from the Bermingham mineral reserve incorporates only one-third of the current
Bermingham silver indicated mineral resource and is therefore a reflection of the potential upside at Bermingham, which will be a
focus of ongoing mine optimization and expansion studies. With over 1,000 meters ("m") of development completed at Flame &
Moth and Bermingham at the end of 2018, we are in a position to initiate mill operations and achieve concentrate production
within 5-7 months after making a production decision for Keno Hill. Finally, with over 75% of projected revenue from Ag and a LOM
Ag equivalent ("AgEq") grade of 1,136 g/t 1, Keno Hill represents an exceptional silver development project with
relatively low capital intensity and is now on a path to become Canada's only primary silver
producer."
Mining and Mineral Reserves
The PFS mine plan is centered on the Flame & Moth and Bermingham deposits with LOM production contributions of 60% and
30%, respectively. Supplemental mine production is sourced from the Bellekeno deposit early in the production period and from the
Lucky Queen deposit later in the mine life. The LOM production schedule includes an annualized average of 430 tpd over an
approximate eight (8) year period. Nominal production rates are an initial 250 tpd from the Bellekeno deposit, a variable 250 -
300 tpd from each of the Flame & Moth and Bermingham deposits throughout the entire mine life and 100 tpd from the Lucky
Queen deposit in the final two (2) years of the mine plan. Mining methods are predominantly mechanized cut and fill with a trend
toward long hole and drift and fill mining methods in areas of increased deposit thickness. A summary of the mineral reserve
estimates from each of the deposits included in the PFS is set out below:
|
Classification
|
Tonnes
|
Ag (g/t)
|
Pb (%)
|
Zn (%)
|
Au (g/t)
|
Contained
Ag
|
Bellekeno
|
Proven
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Probable
|
40,109
|
843
|
11.79
|
6.31
|
-
|
1,087,000
|
Lucky Queen
|
Proven
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Probable
|
70,717
|
1,244
|
2.63
|
1.38
|
0.12
|
2,829,000
|
Flame & Moth
|
Proven
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Probable
|
704,211
|
672
|
2.71
|
5.73
|
0.49
|
15,214,000
|
Bermingham
|
Proven
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Probable
|
362,343
|
972
|
2.59
|
1.32
|
0.13
|
11,324,000
|
Total
|
Proven
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Probable
|
1,177,379
|
804
|
2.98
|
4.13
|
0.34
|
30,454,000
|
Notes:
|
1.
|
Sum of all amounts may not add up to totals due to
rounding.
|
2.
|
The mineral reserves above are included in the mineral resource
estimate table in Appendix 1.
|
* See "Cautionary Note to Investors regarding Mineral Reserve and Resource Estimates" below.
|
Footnote:
|
1.
|
AgEq equivalent was calculated using PFS average LOM metal prices and
mill recoveries: Ag US$17.90/oz, recovery 96%; Pb US$1.00/lb, recovery 89%; Zn US$1.22/lb, recovery 73%; Au US$1,321/oz,
recovery 49%.
|
Processing and Infrastructure
The Keno District mill facility has a nameplate capacity of 408 tpd and employs conventional crushing, grinding, differential
flotation and dewatering processes to produce a Pb-Ag concentrate, a Zn concentrate and a filtered tailings product for storage
in an established dry stacked tailings facility or to be used underground as backfill. Ag and Pb minerals are recovered together
in a Pb-Ag concentrate and Zn minerals in a separate Zn concentrate. The mill was previously commissioned in 2011 and operated
for three (3) years and has been under enhanced care and maintenance since 2014. Silver recoveries are estimated to be 94% with
91% reporting to the Pb concentrate, thereby enhancing Ag payability. The average LOM throughput in the mill is 430 tpd over the
eight (8) year schedule, with a peak throughput to 550 tpd in the third year of the PFS schedule. This would require an amendment
to the current quartz mining license ("QML") prior to the increase in mill throughput.
Prior to resumption of mill operations, an additional 1.8 m x 3 m,
150-kilowatt ("kW") ball mill (purchased and on site) would be installed to provide expanded grinding capacity ahead of the
flotation circuit. Additional tailings filtering capacity and concentrate regrind mills will also be installed prior to mill
commissioning. Updated metallurgical recovery performance in the PFS is based on five (5) additional locked cycle flotation tests
on representative sample composites from Flame and Moth, Bermingham and Lucky Queen, as well as previous open cycle tests. Once
in commercial production, the Pb-Ag concentrate would have an expected commercial grade of 54% Pb and 17,300 g/t Ag. The
projected metallurgical performance in the PFS is as follows:
Mill Recoveries (Payable) – LOM
|
|
Into Pb-Ag Concentrate
|
Into Zn Concentrate
|
Ag %
|
91.0
|
4.6
|
Pb %
|
88.6
|
-
|
Zn %
|
-
|
73.6
|
Au %
|
49.0
|
-
|
Concentrate Production (at full production)
|
|
Pb-Ag Concentrate
|
Zn Concentrate
|
Ag g/t
|
17,316
|
704
|
Dry Tonnes
|
52,772
|
65,436
|
Pb %
|
54.0
|
-
|
Zn %
|
-
|
53.0
|
Additional pre-production site infrastructure improvements included in the PFS comprise a camp expansion, additional dry
facilities, expanded administration offices, an additional maintenance facility, electrical power grid substation at Bermingham
and a water treatment plant at Bermingham.
Capital Costs
The Keno Hill Silver Project is a low capital intensity project due to its existing mine and mill infrastructure. The initial
capital costs of $23.2 M comprises $17.9 M of surface and underground
development costs to reach mill commissioning plus an additional $5.3M of working capital to reach
positive cash flow. PP&E expenditures in the amount of $2.8 M are being allocated to mill
upgrades to increase the grinding and filtering capacity and to complete other improvement modifications prior to reaching
commercial production.
Initial Capital Costs (CAD$ Millions)
|
Mine Development/PP&E
|
11.8
|
Mill Refurbishment
|
2.8
|
Site Infrastructure/PP&E
|
1.4
|
Owners Costs, Contingency
|
1.9
|
Total Pre-Production Capital
|
17.9
|
|
|
Working Capital
|
5.3
|
Total
|
23.2
|
Other
All of the regulatory approvals required for mining and processing activities associated with the Bellekeno, Lucky Queen and
Flame & Moth deposits are currently in place. An amendment to the QML and Water Use Licence ("WUL") are required for mining
and processing activities associated with the Bermingham deposit. Both of these license amendments are underway. The amendment to
the QML is anticipated in Q2 2019 while the amendment to the WUL is anticipated to be received in Q3 2019.
The PFS was compiled by Mining Plus with contributions from a team of Qualified Persons as defined by National Instrument
43-101 – Standards of Disclosure for Mineral Projects ("NI 43-101") as follows:
- Zach Allwright, P.Eng. of Mining Plus
- Hassan Ghaffari, P.Eng of Tetra Tech
- Gilles Arseneau, Ph.D., P.Geo. of SRK Canada Inc.
- Cliff Revering, P.Eng., of SRK Canada Inc.
- Paul Hughes, Ph.D., P.Eng. of Mining Plus
- Adrian Churcher, P.Eng. of Mining Plus
All mineral resources are classified following the CIM Definition Standards for Mineral Resources and Mineral Reserves
(May 2014), in accordance with the CIM Estimation of Mineral Resources and Mineral Reserves Best
Practice Guidelines and NI 43-101.
See "Cautionary Note to Investors regarding Mineral Reserve and Resource Estimates" below.
The disclosure in this news release of scientific and technical information regarding exploration has been reviewed and
approved by Alan McOnie, FAusIMM, Alexco's Vice President, Exploration, while that regarding mine
development and operations has been reviewed and approved by Neil Chambers, P.Eng., Mine
Superintendent, each of whom is a Qualified Person and has approved the disclosure herein. The technical information in this news
release was reviewed by Zach Allwright, P.Eng. and Adrian Churcher,
P.Eng. both of Mining Plus, Gilles Arseneau, Ph.D., P.Geo. and Cliff
Revering, P.Eng, both of SRK Canada Inc. and Hassan Ghaffari, P.Eng. of Tetra Tech, each of
whom is a Qualified Person and has approved the disclosure herein.
Conference Call Details
Alexco will hold a conference call and webcast tomorrow, March 29, 2019 at 9:00 a.m. Eastern (6:00 a.m. Pacific). To participate in the live call,
please use one of the following methods:
Dial toll free from Canada or the US:
|
1-800-319-4610
|
|
|
Dial from outside Canada or the US:
|
1-604-638-5340
|
|
|
Dial from Germany:
|
0800-180-1954
|
|
|
Dial from Switzerland:
|
0800-802-457
|
|
|
Dial from the UK
|
0800-101-2791
|
|
|
Confirmation Code#:
|
Ask to join the Alexco conference call
|
|
|
Live audio webcast:
|
www.alexcoresource.com
|
Participants should connect five to ten minutes before the call.
The conference call will be recorded and an archived audio webcast will be available at www.alexcoresource.com.
About Alexco
Alexco owns the majority of the historic high-grade Keno Hill Silver District in Canada's
Yukon Territory.
Alexco also operates a wholly-owned subsidiary business, Alexco Environmental Group, that provides mine-related environmental
services, remediation technologies and reclamation and mine closure services to both government and industry clients in
North America and elsewhere.
Please visit the Alexco website at www.alexcoresource.com
Some statements ("forward-looking statements") in this news release contain forward-looking information concerning the
results of the PFS, anticipated results and developments in Alexco's operations in future periods, planned exploration and
development of its properties, plans related to its business and other matters that may occur in the future, made as of the date
of this news release. Forward looking statements may include, but are not limited to, statements with respect to results of
the PFS; future mineral exploration including the estimation of mineral reserves and mineral resources and the realization of
mineral reserve and mineral resource estimates; future mine construction and development activities; future mine operation
and production; the timing of activities and reports; the amount of estimated development and operational expenses; projected
operational and economic metrics; the success of exploration and development activities; the potential upside and growth in
respect of certain deposits comprising the Keno Hill Silver Project; anticipated permitting time lines; requirements for
additional permits (or amendments to existing permits); anticipated installation of certain infrastructure; projected equipment
and production capacity; and potential capital, revenue and sources and uses of funds. Forward-looking statements are subject to
a variety of known and unknown risks, uncertainties and other factors which could cause actual events or results to differ from
those expressed or implied by the forward-looking statements. Such factors include, among others, risks related to actual results
and timing of exploration and development activities; actual results and timing of mining activities; actual results and timing
of environmental services activities; actual results and timing of remediation and reclamation activities; conclusions of
economic evaluations; changes in project parameters as plans continue to be refined; future prices of silver, gold, lead, zinc
and other commodities; possible variations in mineable resources, grade or recovery rates; failure of plant, equipment or
processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; First Nation rights and
title; continued capitalization and commercial viability; global economic conditions; competition; and delays in obtaining
governmental approvals or financing or in the completion of development activities. Forward-looking statements are based on
certain assumptions that management believes are reasonable at the time they are made. In making the forward-looking statements
included in this news release, Alexco has applied several material assumptions, including, but not limited to, the assumption
that Alexco will be able to raise additional capital as necessary, that the assumptions, projections and estimates in the PFS
will proceed as planned, and that market fundamentals will result in sustained silver, gold, lead and zinc demand and prices.
There can be no assurance that forward-looking statements will prove to be accurate and actual results and future events could
differ materially from those anticipated in such statements. Alexco expressly disclaims any intention or obligation to update or
revise any forward-looking statements whether as a result of new information, future events or otherwise, except as otherwise
required by applicable securities legislation.
Cautionary Note to Investors regarding Mineral Reserve and Resource Estimates
This press release has been prepared in accordance with the requirements of the securities laws in effect in Canada, which differ from the requirements of United States securities
laws. The terms "mineral reserve", "proven mineral reserve" and "probable mineral reserve" are Canadian mining terms as
defined in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum (the "CIM") - CIM Definition
Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as amended. These definitions differ materially
from the definitions in SEC Industry Guide 7 ("SEC Industry Guide 7") under the United States Securities Act
of 1933, as amended. Under SEC Industry Guide 7 standards, a "final" or "bankable" feasibility study is required to report
reserves, the three-year historical average price is used in any reserve or cash flow analysis to designate reserves, and the
primary environmental analysis or report must be filed with the appropriate governmental authority.
In addition, the terms "mineral resource", "measured mineral resource", "indicated mineral resource" and "inferred mineral
resource" are defined in and required to be disclosed by NI 43-101; however, these terms are not defined terms under SEC Industry
Guide 7 and are normally not permitted to be used in reports and registration statements filed with the SEC. Investors are
cautioned not to assume that all or any part of a mineral deposit in these categories will ever be converted into SEC Industry
Guide 7 reserves. "Inferred mineral resources" have a great amount of uncertainty as to their existence, and great uncertainty as
to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be
upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of
feasibility or pre-feasibility studies, except in rare cases. Investors are cautioned not to assume that all or any part of an
inferred mineral resource exists or is economically or legally mineable. It is reasonably expected that the majority of inferred
mineral resources could be upgraded to indicated mineral resources with continued exploration. Disclosure of "contained ounces"
in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report
mineralization that does not constitute "reserves" by SEC Industry Guide 7 standards as in place tonnage and grade without
reference to unit measures.
Accordingly, information contained in this press release regarding descriptions of the Corporation's mineral deposits may
not be comparable to similar information made public by U.S. companies subject to the reporting and disclosure requirements under
the United States federal securities laws and the rules and regulations thereunder, including
SEC Industry Guide 7.
APPENDIX 1 - MINERAL RESERVES AND MINERAL RESOURCES
The table below represents the current Keno Hill mineral resource estimate inclusive of mineral reserves in the indicated
mineral resource category. Mineral resource estimates for the Bellekeno, Flame & Moth, Onek and
Lucky Queen deposits are unchanged from the Company's prior public disclosure. The Bermingham mineral resource estimate has been
updated as disclosed in the footnote below.
|
Classification
|
Tonnes
|
Ag (g/t)
|
Pb (%)
|
Zn (%)
|
Au (g/t)
|
Contained Ag
(Oz)
|
Bellekeno
|
Indicated
|
262,000
|
585
|
3.5
|
5.3
|
n/a
|
4,927,000
|
|
Inferred
|
243,000
|
428
|
4.1
|
5.1
|
n/a
|
3,344,000
|
Lucky Queen
|
Indicated
|
132,300
|
1,167
|
2.43
|
1.63
|
0.16
|
4,964,000
|
|
Inferred
|
257,900
|
473
|
1.04
|
0.8
|
0.13
|
3,922,000
|
Flame & Moth
|
Indicated
|
1,679,000
|
498
|
1.85
|
5.33
|
0.42
|
26,883,000
|
|
Inferred
|
365,200
|
356
|
0.47
|
4.25
|
0.26
|
4,180,000
|
Onek
|
Indicated
|
700,200
|
191
|
1.24
|
11.85
|
0.6
|
4,300,000
|
|
Inferred
|
285,100
|
118
|
1.15
|
8.26
|
0.42
|
1,082,000
|
Bermingham1
|
Indicated
|
1,102,300
|
930
|
2.4
|
1.7
|
0.14
|
33,004,000
|
|
Inferred
|
509,400
|
717
|
1.7
|
1.5
|
0.15
|
11,746,000
|
Total
|
Indicated
|
3,875,800
|
594
|
2.0
|
5.3
|
0.34
|
74,078,000
|
|
Inferred
|
1,660,600
|
455
|
1.6
|
3.7
|
0.20
|
24,274,000
|
Notes:
|
1.
|
The effective date of this mineral resource table is September 26, 2018,
and is based on a revised narrow-vein interpretation prepared by Alexco on September 13, 2018. An initial vein model was
prepared by Alexco on August 28, 2018, which was predicated on a wider vein interpretation that incorporated a
significant volume of low-grade material (i.e. <100 g/t silver). Although an initial mineral resource estimate was
completed using the wider vein model, a subsequent update has been completed using the narrow-vein model to remove this
low-grade tonnage for use in the 2018 PFS study. The narrow-vein geological model was interpreted using a 100 g/t silver
cut-off grade to define the mineralized veins but otherwise estimated using the same parameters.
|
2.
|
Mineral resources for Bermingham are reported at a value per tonne cut-off
of CAD$185/t using the following metal prices and recoveries; Ag US$20.80/oz, recovery 96%; Pb US$1.05/lb, recovery 97%;
Zn US$1.20/lb, recovery 88%; Au US$1,450/oz, recovery 72%. Foreign exchange rate of $0.80 USD/CAD. All numbers have been
rounded to reflect the relative accuracy of the estimates. Mineral resources are not mineral reserves and do not have
demonstrated economic viability.
|
* See "Cautionary Note to Investors regarding Mineral Reserve and Resource Estimates" above.
View original content:http://www.prnewswire.com/news-releases/alexco-announces-positive-pre-feasibility-study-for-expanded-silver-production-at-keno-hill-silver-district-300820797.html
SOURCE Alexco Resource Corp.