RE: A haulage road for CliffsCouple of million?? Very funny.
Just the aggregate will cost more than 50 millions (for the 5 millions cubic meters needed) and that is not even considering the costs of restauration of borrow pits... and the what about bridges and culverts!
One year... again laughable! This is just the time needed to get the environmental department to agree to use the said borrow pits for aggregate!
Only viable solution would be an ice road to haul vital equipement during winter... No way they are going to use it for ore... even with 100% chromite and all the PGM you want!
Raz