GREY:GYPHQ - Post by User
Comment by
red911on Feb 18, 2012 9:00am
![](https://assets.stockhouse.com/kentico-cms/0342-00/images/Sprite.svg#id_Post_Views_Icon)
294 Views
Post# 19553546
RE: Cash Situation...
RE: Cash Situation...Then it is also possible they are just selling loaded carbon in raw state and not waiting for it to be processed. That would probably give them a little less cash but it would be immediate. Probably a better option for them now if available. Is it possible they have enough loaded carbon stored and coming in to finance ADR completion? I don't think there is much if any equip left to purchase. The original plan was completion Feb 1 and then commissioning starts, which can take weeks. Now they say "fully-operational" by mid to late Mar... does this include commissioning? In which case maybe ADR is from a construction standpoint 'complete'? So many questions. AN UPDATE TO CONSTRUCTION PROGRESS WOULD HELP.