RE:From TD this morningBest part of that TD commentary:
We are forecasting 11.9Mt of saleable production in FY2023 (April 2022-March 2023).
That means 50% Phase 2 capacity operation in debut FY, that is solid.
I hope the Port is ready to handle the additional material that Champion will ship.
Anyone know if/when the stacker/reclaimer arrives at the port? Seems important for loading the additional material.
In April 2021, listed as a Phase 2 Milestone:
Ordering of long lead time items, including the stacker reclaimer by Socit Ferroviaire et Portuaire de Pointe-Noire ("SFPPN").