8 jan 2014 NR regarding FPF-1 modification works / londoner7londoner, I think I found the statement that led some to the conclusion that the new FPF-1 oil/gas processing unit has a higher capacity than the original one (8 jan 2014):
"The extended duration of the works is attributable to the longer than estimated time required to install the new, rather than refurbished, oil and gas processing plant on the vessel. While this is now scheduled to take longer than if the original equipment on the FPF-1 had been re-used, the new facilities are designed to ensure that a quality vessel capable of achieving high operational uptime performance is deployed on the hub."