Kamoa-Kakula Copper Project Mines a Record 250,000 Tonnes of Development Ore Grading 4.85% Copper in November, Accelerating Both Grade and Tonnage of Copper Ore Added to the Project's Surface Stockpiles
Newsfile Corp - 25 minutes ago
Pre-production ore stockpiles now hold 1.25 million tonnes grading 3.75% copper, containing more than 46,700 tonnes of copper
Underground development totalling 2,163 metres completed in November; more than 26.8 kilometres now complete - 9.0 kilometres ahead of plan
Access to Kakula's +8% copper ore in the centre of deposit established with the connection of northern and southern main access tunnels in early November
In November, Kakula's central connection development produced 93,000 tonnes grading 4.95% copper from the southern decline, including 41,000 tonnes of high-grade ore grading 7.82% copper, and 124,000 tonnes grading 5.03% copper from the northern decline
Overall progress of Kamoa-Kakula's first phase, 3.8 Mtpa mining and milling operation now approximately 63% complete, with first copper concentrate production scheduled for July 2021