nofluff on Aug 18, 2021 11:32am
The water dyke
When thry get through the dyke, that news should kick start us. When the fans arrive, that shouod b big.
When we start milling second stope, that should even help.
nf
Comment by
RockDoc1 on Aug 18, 2021 11:39am
Bad news NF. They hit the dyke on two adjacent levels, 90 feet apart vertically. Likely this means that, for this section of the orebody, they will have to contend with the dyke on every level. This problem is not going away anytime soon.
Comment by
nofluff on Aug 18, 2021 12:21pm
u r correct doc. It is the 1rst drive I am talking about. They get through and things speed up big. The deeper lateral will b quicker as they have learned much in the last couple months. The goal is to get to the highgrade long stopes as soon as possible and start milling 5000 tonnes per day. At that point we should b about 5 bags from here. nf