Grids nearing capacity
For ALBERTA....projection of solar development tripled just between May and June, from 2,000 to 6,000 megawatts.
"The grid operator really (was) not prepared for this rush." Grid operator AltaLink, is owned by Berkshire Hathaway.
In the province to the west, BC Hydro a few years ago 2021 underestimated future demand for electricity. Require 750 MW more. Need upgrades to transmission the grid to provde reliability for renewable energy and new transmission lines. More windfarms to be built.
As the saying goes, no transition without transmission.