RE:Verde newsletter linkUpdate on Plant 2: The energy meter cubicle and the vibrating sieve arrived at Plant 2 last week. The vibrating sieve separates the material that needs to be re-crushed from the material that can go directly to the storage shed. The bulk storage shed is under construction, and its cover modules are being assembled. About 45% of Plant 2's interlocked paving blocks arrived, and the electric house's foundation is concluded. The crushed material storage shed's retaining wall is currently under construction. The development of the masonry structure and the construction of the basement for cable storage will be initiated next week.