Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Bullboard - Stock Discussion Forum Polaris Renewable Energy Inc T.PIF

Alternate Symbol(s):  RAMPF

Polaris Renewable Energy Inc. is a Canada-based company. The Company is engaged in the acquisition, development and operation of renewable energy projects in the Americas. The Company operates 72 megawatts (MW) geothermal facility in Nicaragua, three run-of-river hydroelectric facilities in Peru, with a combined capacity of approximately 33 MW, a 25 MW solar plant facility in the Dominican... see more

TSX:PIF - Post Discussion

Polaris Renewable Energy Inc > Nicaragua PPA Extension
View:
Post by LTIH1324 on Dec 17, 2020 5:12pm

Nicaragua PPA Extension

Polaris Infrastructure Inc. (TSX: PIF) ("Polaris Infrastructure" or the "Company"), a Toronto-based company engaged in the operation, acquisition and development of renewable energy projects in Latin America, is pleased to announce that its board of directors has approved revised terms to its Power Purchase Agreement ("PPA") at its San Jacinto geothermal facility in Nicaragua by its wholly-owned subsidiary Polaris Energy Nicaragua, S.A. ("PENSA").  

After extensive discussions with the Ministry of Energy and Mines in Nicaragua, the Company is proud to announce the following as it relates to the continuing commitment to provide renewable, clean, baseload power to the country of Nicaragua at long-term competitive rates:
  • The term of the PPA has been extended for an additional 10 years to January 2039.
  • A non-indexed $110.00 USD per Mwhr price versus the current $130.712 USD per Mwhr price in 2020.
  • Contractual confirmation for Polaris Infrastructure to include a Binary Unit of up to 10MW's.
  • An extension of two years to the income tax holiday such that income taxes will now be payable in 2025 versus 2023.
  • The previous price penalty clause requiring a minimum power production delivered has been eliminated.
  • The amended terms are to take effect immediately.
The amended PPA has been signed by both parties and has received consent from all project lenders and the board of directors.  The concession agreement and generation license will be amended to incorporate such changes, which we expect to be completed in January.
The desire to construct the binary unit at the San Jacinto facility, combined with the 2029 expiration of our existing PPA, provided the context to renegotiate the terms of the existing contract.  The Company believes the aforementioned parameters of this revised PPA will allow for significant realization of free cash flow over an extended period of time.  The Company is confident that the combination of the extended term, increased tax holiday, long-life of the asset and the addition of the binary unit will provide the opportunity to refinance the existing project loan on terms that are favourable to shareholders. 
The Company reiterates its continued commitment to its current dividend policy for the foreseeable future.
"The revised terms of the PPA enable Polaris to provide a competitive source of baseload, renewable energy to the Nicaraguan market.  The combination of the long-life nature of our asset and the ability to grow the production provides a win-win for both parties," commented Marc Murnaghan, CEO of Polaris Infrastructure.  "In my opinion, such new terms and the fact that our Company now has an average remaining life of over 18 years on all its PPAs should be viewed positively by market participants."
Comment by retiredcf on Dec 18, 2020 10:54am
Kudos to management for a job well done. GLTA
Comment by DocJunior on Dec 18, 2020 11:54am
More strong work from management, really happy. This should do a lot to ease the market's concerns about the risk of the Nicaraguan government pulling the rug from under PIF if they are willing to commit to a new longterm deal
The Market Update
{{currentVideo.title}} {{currentVideo.relativeTime}}
< Previous bulletin
Next bulletin >

At the Bell logo
A daily snapshot of everything
from market open to close.

{{currentVideo.companyName}}
{{currentVideo.intervieweeName}}{{currentVideo.intervieweeTitle}}
< Previous
Next >
Dealroom for high-potential pre-IPO opportunities